HomeMy WebLinkAbout2009 CON Wade & Associates - Amendment #1 Project Management Services - Kimball Park Soccer FieldAMENDMENT 1 TO AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
WADE & ASSOCIATES
This Amendment #1 to Agreement is entered into this 21st day of July, 2009, by and
between the City of National City, a municipal corporation ("CITY"), and Wade & Associates a
project management firm (the "CONSULTANT").
RECITALS
A. The CITY and the CONSULTANT entered into an agreement on August 8, 2008
("the Agreement"), wherein the CONSULTANT agreed to provide Project
Management services for the Soccer Field with a not -to -exceed amount of
$24,191.80.
B. The parties desire to amend the Agreement to expand the Scope of Services to
provide additional project coordination services.
NOW, THEREFORE, the parties hereto agree that the Agreement entered into on 8th
day of August 2008, shall be amended by expanding the Scope of Services as set forth in the
attached Exhibit "A", which is incorporated herein by reference not -to -exceed $26,552.
The parties further agree that with the foregoing exception, each and every term and
provision of the Agreement dated August 1, 2008, shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date
and year first above written.
CITY OF NATIONAL CITY
By:
Ron Morrison, Mayor
APPROVED AS TO FORM:
/'J2of
George H. Eiser, III
City Attorney
WADE & ASSOCIATES
(Corporation — signatures of two corporate officers)
(Partnership — one signature)
(Sole proprietorship — one si.. - re)
By:
(Print)
adv
(Title)
By:
(Name)
(Print)
(Title)
Exhibit A
WADE & ASSOCIATES
PROJECT MANAGEMENT 656 Fifth Avenue, Suite W
San Diego, California 92101
July 1, 2009
Din Daneshfar, Principal Civil Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
RE: Project Management Services for the City of National City,
Kimball Park Soccer Field
Dear Din,
TEL (619) 244-3418
FAX (619) 794-0180
Byronwadel@mac.com
I am submitting this proposal per your request for a cost estimate to provide additional project
management services for the abovementioned project. The additional services are required
because the alternative soccer field locations and designs are required and to provide certified
payroll review and management. The project is ongoing and should be complete by January 15,
2010.
SCOPE
As the project manager for this project I will work with the City of National City, their project
inspector and the contractor to coordinate all aspects of the construction activities and public
outreach, which includes:
• Attend all meeting.
• Work with and coordinate designers and manufacturer/provider.
• Process RFI's and submittals.
• Review, negotiate, recommend and draft change orders for City approval as necessary.
• Review and recommend invoices for payment.
• Visit the construction as needed to assist in problem resolution.
• Maintain a master construction file.
• Take efforts as necessary and directed to communicate the construction activities to the
general public.
• Review certified payroll and maintain records.
• Finalize the project per City policy and standards.
See attached worksheet for cost breakdown.
Thank you for this opportunity to serve the City of National City on this project.
Sincerely,
6) __,_A--v-1- q tcL. c__A-YNgL_
Byron S. Wade
Owner/Principal Project Manager
WADE & ASSOCIATES
Fee Proposal/Cost Estimate
for
City of National City
Kimball Park Soccer Field
Estimated Hours:
#
Task
Principal
Project
Manager
Project
Manager
CAD Oper/
Admin.
Assistant
Survey
• Crew
TOTALS
1
Project Management
120
40
64
26,552
Rates
150
105
68
TOTALS
18,000
4,200
4,352
-
26,552
Estimated Reimbursable Costs:
#
Item
Type of
Units
Cost per Units
Estimated
number of
Units
TOTALS
1
B&W Copies/Prints 8 1/2" x 11"
Each
$ 0.20
-
2
Color Copies/Prints 8 1/2" x 11"
Each
S 1.00
-
3
Full Size (D Sheets) Paper
Each
S 15.00
-
4
Full Size (D Sheets) Mylars
Each
$ 30.00
-
5
CD Roms
Each
$ 5.00
-
6
Binder, 2"
Each
S 22.00
-
7
Binder, 3"
Each
S 26.00
-
8
Printing Flyers & Doorhangers (estimated)
LS
$ 1,200.00
-
Total Expenses
Total Consulting Fee (above)
Total Cost Estimate
-
26,552.00
$ 26,552.00
10% Overhead fee will be charged to subcontracted expenses.
n l�eAnnQi.A
✓" Byron S. Wade
Owner/Principal Project Manager
June 21, 2009
RESOLUTION NO. 2009-177
RESOLUTION OF THE CITY COUNCIL OF
THE CITY OF NATIONAL CITY AUTHORIZING
THE MAYOR TO EXECUTE AMENDMENT
NO. 1 TO THE AGREEMENT WITH WADE
& ASSOCIATES FOR PROJECT MANAGEMENT
SERVICES FOR THE SOCCER FIELD PROJECT
IN THE AMOUNT NOT -TO -EXCEED $26,552
WHEREAS, on August 8, 2008, the City entered into an Agreement (the
"Agreement") with Wade & Associates (the "Consultant") for project management services for
the Soccer Field Project in the not -to -exceed amount of $24,191.80; and
WHEREAS, several issues with the project have dictated the need for additional
services of the consultant in the not -to -exceed amount of $26,552, and City staff recommends
approval of Amendment No. 1 to the Agreement in order to obtain these additional services,
with a not -to -exceed amount of $26,552.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute Amendment No. 1 to the Agreement with
Wade & Associates for project management services for the Soccer Field Project in an amount
not -to -exceed $26,552.
PASSED and ADOPTED this 21st day of Jul
on Morrison, Mayor
ATTEST:
ti
.emu
M. ael R. Dalla, City Clerk
APPROVED AS TO FORM:
tip .garA7ibt
George H. -Eiser, III
City Attorney
Passed and adopted by the Council of the City of National City, California, on July 21,
2009 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Parra, Sotelo-Solis, Van Deventer, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
h
City
erk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2009-177 of the City of National City, California, passed and
adopted by the Council of said City on July 21, 2009.
City Clerk of the City of National City, California
By:
Deputy
•C 'r> - `l
City of National City, California
COUNCIL AGENDA STATEMENT
,- MEETING DATE July 21, 2009
AGENDA ITEM NO.
9
ITEM TITLE Resolution of the City Council of National City approving amendment #1 to the agreement
with Wade & Associates for project management for the Soccer Field Project in the amount not -to -exceed
$26,552 and authorizing the Mayor to execute amendment #1. Funds are available in the CDBG Funds.
PREPARED BY Barby Tipton DEPARTMENT Engineering EXT. 4583
EXPLANATION
On August 8, 2008, the City entered into an agreement with Wade & Associates for project management
services for the Soccer Field Project in the not -to -exceed amount of $24,191.80.
Several issues with the project have dictated the need for additional services in the not -to -exceed amount of
$26,552. With approval of this amendment the total amount of authorized work will be $50,743.80.
The purpose of this resolution is to approve additional services and authorize the Mayor to execute the
amendment #1 to the agreement.
Environmental Review X N/A
MIS Approval J
Financial Statement
Approved By:
Funds are available in expenditure account 301-409-500-598-4076
inance Director
Account No. 301-409-500-598-4076
STAFF RECOMMENDATION
A. - • t. - 'esolution.
11/
A ' D / COMMISSION RECOMMENDATION
ATTACHMENTS (Listed Below) Resolution No.
1. Resolution
2. Agreement Amendment #1 (2 copies)
A-200 (Rev. 7/03)
RESOLUTION NO.
RESOLUTION OF THE CITY COUNCIL OF
THE CITY OF NATIONAL CITY AUTHORIZING
THE MAYOR TO EXECUTE AMENDMENT
NO. 1 TO THE AGREEMENT WITH WADE
& ASSOCIATES FOR PROJECT MANAGEMENT
SERVICES FOR THE SOCCER FIELD PROJECT
IN THE AMOUNT NOT -TO -EXCEED $26,552
WHEREAS, on August 8, 2008, the City entered into an Agreement (the
"Agreement") with Wade & Associates (the "Consultant") for project management services for
the Soccer Field Project in the not -to -exceed amount of $24,191.80; and
WHEREAS, several issues with the project have dictated the need for additional
services of the consultant in the not -to -exceed amount of $26,552, and City staff recommends
approval of Amendment No. 1 to the Agreement in order to obtain these additional services,
with a not -to -exceed amount of $26,552.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute Amendment No. 1 to the Agreement with
Wade & Associates for project management services for the Soccer Field Project in an amount
not -to -exceed $26,552.
PASSED and ADOPTED this 21st day of July, 2009.
Ron Morrison, Mayor
ATTEST:
Michael R. DaIla, City Clerk
APPROVED AS TO FORM:
George H. Eiser, Ill
City Attorney
AMENDMENT 1 TO AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
WADE & ASSOCIATES
This Amendment #1 to Agreement is entered into this 21st day of July, 2009, by and
between the City of National City, a municipal corporation ("CITY"), and Wade & Associates a
project management firm (the "CONSULTANT").
RECITALS
A. The CITY and the CONSULTANT entered into an agreement on August 8, 2008
("the Agreement"), wherein the CONSULTANT agreed to provide Project
Management services for the Soccer Field with a not -to -exceed amount of
$24,191.80.
B. The parties desire to amend the Agreement to expand the Scope of Services to
provide additional project coordination services.
NOW, THEREFORE, the parties hereto agree that the Agreement entered into on 8tt,
day of August 2008, shall be amended by expanding the Scope of Services as set forth in the
attached Exhibit "A", which is incorporated herein by reference not -to -exceed $26,552.
The parties further agree that with the foregoing exception, each and every term and
provision of the Agreement dated August 1, 2008, shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date
and year first above written.
CITY OF NATIONAL CITY WADE & ASSOCIATES
(Corporation - signatures of two corporate officers)
(Partnership - one signature)
(Sole proprietorship - one si.. - re)
By: By:
Ron Morrison, Mayor
(Print)
APPROVED AS TO FORM: (Title)
By:
George H. Eiser, Ill (Name)
City Attorney
(Print)
(Title)
Exhibit A
WADE & ASSOCIATES
PROJECT MANAGEMENT 656 Fifth Avenue, Suite W
San Diego, California 92101
July 1, 2009
Din Daneshfar, Principal Civil Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
RE: Project Management Services for the City of National City,
Kimball Park Soccer Field
Dear Din,
TEL (619) 244-3418
FAX (619) 794-0180
Byronwadel@mac.com
I am submitting this proposal per your request for a cost estimate to provide additional project
management services for the abovementioned project. The additional services are required
because the alternative soccer field locations and designs are required and to provide certified
payroll review and management. The project is ongoing and should be complete by January 15,
2010.
SCOPE
As the project manager for this project I will work with the City of National City, their project
inspector and the contractor to coordinate all aspects of the construction activities and public
outreach, which includes:
• Attend all meeting.
• Work with and coordinate designers and manufacturer/provider.
• Process RFI's and submittals.
• Review, negotiate, recommend and draft change orders for City approval as necessary.
• Review and recommend invoices for payment.
• Visit the construction as needed to assist in problem resolution.
• Maintain a master construction file.
• Take efforts as necessary and directed to communicate the construction activities to the
general public.
• Review certified payroll and maintain records.
• Finalize the project per City policy and standards.
See attached worksheet for cost breakdown.
Thank you for this opportunity to serve the City of National City on this project.
Sincerely,
Cmr vclu
Byron S. Wade
Owner/Principal Project Manager
WADE & ASSOCIATES
Fee Proposal/Cost Estimate
for
City of National City
Kimball Park Soccer Field
Estimated Hours:
#
Task
Principal
Project
Manager
Project
Manager
CAD Oper/
Admin.
Assistant
Survey
. Crew
TOTALS
1
Project Management
120
40
64
26,552
Rates
150
105
68
TOTALS
18,000
4,200
4,352
-
26,552
Estimated Reimbursable Costs:
#
Item
Type of
Units
Cost per Units
Estimated
number of
Units
TOTALS
1
B&W Copies/Prints 8 1/2" x 11"
Each
$ 0.20
-
2
Color Copies/Prints 8 1/2" x 11"
Each
$ 1.00
-
3
Full Size (D Sheets) Paper
Each
S 15.00
-
4
Full Size (D Sheets) Mylars
Each
$ 30.00
-
5
CD Roms
Each
S 5.00
-
6
Binder, 2"
Each
$ 22.00
-
7
Binder, 3"
Each
$ 26.00
-
8
Printing Flyers & Doorhangers (estimated)
LS
$ 1,200.00
-
Total Expenses
Total Consulting Fee (above)
Total Cost Estimate
-
26,552.00
$ 26,552.00
10% Overhead fee will be charged to subcontracted expenses.
914
ron S. Wade
Owner/Principal Project Manager
June 21, 2009
City of National City
Office of the City Clerk
1243 National City Boulevard, National City, CA 91950-4397
Michael R. Dalla, CMC - City Clerk
(619) 336-4228 Fax: (619) 336-4229
July 29, 2009
Mr. Byron Wade
Wade & Associates
656 Fifth Avenue, Suite I
San Diego, CA 92101
Dear Mr. Wade,
On July 21 st, 2009, Resolution No. 2009-177 was passed and adopted by the
City Council of the City of National City, authorizing execution of Amendment No.
1 to Agreement with Wade & Associates.
We are enclosing for your records a certified copy of the above Resolution and a
fully executed original amendment.
Michael R. Dalla, CMC
City Clerk
Enclosures