CHANGE ORDER #4
April 1, 2010
Project: Marina Gateway Streetscape Specification #08-16
Contractor: Koch -Armstrong
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
This change in contract is for the remvoal and disposal of approximately eighty (80) lineal feet of RCP pipe that
was discovered around the existing sewer main and encased in concrete below the rail road tracks.
Justification for Change in Contract
See Attachment "A"
Cost Reconciliation
See Attachments "A & B.
Construction Contract Accounting Summary
Original Contract Amount: 1,916,282.35
Net change by previously authorized Change Orders: 46,263.42
Contract amount prior to this Change Order: 1,962,545.77
Amount of this change order: 6,545.57
New contract amount: $ 1,969,091.34
Original contract time (calendar days): 120
Previously approved additional working days: 6
Additional working days for this change order: 1
Total contract time (working days): 127
(see Weekly Statement of Working Days for completion date)
Reviewed by:
Agreed to and Accepted by:
Lir April 6, 2010
Koch(Afmstrong — Date
General Engineering, Inc.
cc: Contractor, Construction File, Project Manager, City Clerk
Recommended for approval by:
Reviewed by:
er Date
1243 National City Boulevard
National City , CA 91950
Tel (619) 336-4380
Fax (619) 336-4397
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT "A" CO #4
Justification for Change in Contract
This change in contract is necessary because the RCP pipe found around the sewer main was not shown on
the original plans and was not known to the City during design. The RCP pipe needed to be removed in order
for the contractor to continue to remove and replace the sewer main. The removal of the concrete and RCP
pipe required the use of a breaker and required contractor to haul excess concrete and RCP pipe to the dump.
The approximately six (6) hours of labor and equipment represents the additional hours over what would have
been required to remove the existing sewer main by itself.
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby
incorporates the original contract and all its referenced documents' terms, conditions, and plans for the work
as provided by the City.
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT "B"
CO #4
ITEM
DESCRIPTION
QUANTITY/
%
UNIT
UNIT
PRICE
Running
Total
TOTAL
1
Labor
Foreman (1)
6
HR
73.94
443.64
Operator (2)
12
HR
76.02
912.24
Laborer (1)
6
HR
53.15.
318.90
Laborer(2)
12
HR
55.42
665.04
Subtotal:
2339.82
Mark-up (20%):
467.96
Item # 1 - Labor Total:
2,807.78
2
Equipment
Crew Truck
6
HR
27.43
164.58
JD 710 Backhoe
6
HR
70.05
420.30
Hitachi 790 E
6
HR
91.49
548.94
Cat 256 Skidsteer Loader
6
HR
22.08
132.48
Furakawa
6
HR
110.34
662.04
Bobtail Dump Truck
6
HR
46.46
278.76
End Dump
4
HR
98.00
392.00
Subtotal:
2.599.10
Mark-up (15%):
389.87
Item # 2 - Equipment Total:
2,988.97
3
Materials
Dump Fees
2
EA
150.00
300.00
Subtotal:
300.00
Mark-up (15%):
45.00
Item # 3 - Materials Total:
345.00
Sub -Contractor Sub -total:
6,141.75
K-A MARK-UP:
5%
307.09
Subtotal:
6,448.84
BOND:
1.50%
96.73
CHANGE ORDER PROPOSAL TOTAL
1
LS
6,545.57
-y-- CALIFORNIA
NN.IJION" � LAITY
)
INCORPORATLP
CHANGE ORDER #5
April 1, 2010
Project: Marina Gateway Streetscape Specification #08-16
Contractor: Koch -Armstrong
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
Contractor shall remove and dispose of existing concrete foundations in conflict with the new improvements on
the south side of 23rd and around the PCRs and grade the soils level to 1' behind the new walk with a
minimum 1 1/2:1 slope, spread excess soil on the lot, and re-establish the silt fence in this area.
Justification for Change in Contract
See Attachment "A".
Cost Reconciliation
See Attachments "A", "B", and "C".
Construction Contract Accounting Summary
Original Contract Amount: 1,916,282.35
Net change by previously authorized Change Orders: 52,808.99
Contract amount prior to this Change Order: 1,969,091.34
Amount of this change order: 7,980.07
New contract amount: $ 1,977,071.41
Original contract time (calendar days): 120
Previously approved additional working days: 7
Additional working days for this change order: 0
Total contract time (working days): 127
(see Weekly Statement of Working Days for completion date)
Reviewed by:
Agreed to and Accepted by:
April 6, 2010
Koch Among `"! Date
General Engineering, Inc.
cc: Contractor, Construction File. Project Manager, City Clerk
Recommended for approval by:
ger
by:
Date
1243 National City Boulevard
National City , CA 91950
Tel (619) 336-4380
Fax (619) 336-4397
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT "A" CO #5
Justification for Change in Contract
This change in contract is necessary because the quonset hut removals south of 23rd did not remove the
foundations in the right-of-way as was the original plan. Therefore, the foundations and adjacent soils were
not shown on the plans and their removal was not part of the original scope of work. They are now in the way
of the new improvements and must be removed.
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby
incorporates the original contract and all its referenced documents' terms, conditions, and plans for the work
as provided by the City.
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT'B"
CO #5
ITEM
DESCRIPTION
QUANTITY/
/°
UNIT
UNIT
PRICE
RUNNING TOTAL
TOTAL
Labor (hourly rate includes 33% surcharge)
Operator
8
HR
76.02
608.16
Laborer 1
16
HR
53.15
850.40
Item #1 Sub -total:
1,458.56
Mark-up Cost:
20.00%
291.71
Item #1 Cost:
1,750.27
2
Equipment
Case C X80 Excavator
4
HR
50.00
200.00
936 Loader
4
HR
35.00
140.00
Item #2 Sub -total:
340.00
Mark-up Cost:
15.00%
51.00
Item #2 Cost:
391.00
3
Materials
Dump Fees
1
EA
150.00
150.00
Silt Fence
5
EA
18.22
91.10
Item #3 Sub -total.
241.10
Mark-up Cost:
15.00%
36-17
Item #3 Cost:
277.27
SUBTOTAL:
2,418,54
Bond:
1.50%
36.28
CHANGE ORDER PROPOSAL TOTAL
1
LS
2,454.82
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT"C"
CO #5
ITEM
DESCRIPTION
QUANTITY/
/o
UNIT
UNIT.
PRICE
RUNNING TOTAL
TOTAL
1
Labor
Foreman
8
HR
72.00
576.00
Operator (1)
8
HR
70.00
560.00
Laborer (2)
16
HR
52.00
832.00
Item #1 Sub -total:
1,968.00
Mark-up Cost:
20.00%
393.60
Item #1 Cost:
2,361.60
2
Equipment
Bobcat w! Breaker (2)
16
HR
50.00
800.00
Crew truck (2)
16
HR
25.00
400.00
10 Wheeler (1)
8
HR
88.00
704.00
Equipment Moves (2)
2
EA
88.00
176.00
Item #2 Sub -total:
2,080.00
Mark-up Cost:
15.00%
312.00
Item #2 Cost:
2,392.00
3
Materials
Dumo Fees (wi Reber)
6
EA
100.00
600.00
Item #3 Sub -total:
600.00
Mark-up Cost:
15.00%
90.00
Item #3 Cost:
690.00
SUBTOTAL:
5.443.60
Bond:
1.50%
81.65
CHANGE ORDER PROPOSAL TOTAL
1
LS
5,525.25
INCORPORATED
April 13, 2010
Mr. Monty Koch
President
Koch -Armstrong General Engineering, Inc.
P.O. Box 1190
Lakeside, CA 92040
Dear Mr. Koch,
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dala, CMC - City Clerk
619-336-4228 phone • 619-336-4229 fax
On April 1, 2010, Change Order #4 and #5 to contract was executed between the
City of National City and Koch -Armstrong General Engineering, Inc.
We are enclosing for your records fully executed original change orders.
Michael R. Dalla, CMC
City Clerk
Enclosure
cc: Engineering Dept.