CHANGE ORDER #1
April 12, 2010
Project: Police Department Waterproofing and Staircase Repair Specification: 09-20
Contractor: Industrial Coating
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
This change in contract is for the installation of concrete masonry unit joints under a window on all sides of the
Police Department and to router and seal cracks in the concrete slab at the front of the building. See
Attachment "A".
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby
incorporates the original contract and all its referenced documents' terms, conditions, and plans for the work as
provided by the City. See Attachment A.
Justification for Change in Contract
This change in contract is necessary because hairline cracks at the front of the building were discovered to be
leaking with a rain event. The sealing of the joint below all of the exterior window is necessary to prevent
future leaks. The size of the block below all the window is different than the adjacent block and was showing
signs of joint separation due to variances in heat expansion with the different sizes of block. This caulking is
flexible and will not crack as the blocks expand and shrink at varying rates.
Construction Contract Accounting Summary
Original Contract amount: $ 73,000.00
Net change by previously authorized Change Orders: $
Contract amount prior to this Change Order: $ 73,000.00
Amount of this Change Order: $ 4,283.75
New Contract amount: $ 77,283.75
Original Contract time (calendar days):
Previously approved additional working days:
Additional working days for this Change Order:
Total Contract time (working days):
(see Weekly Statement of Contract Time for completion date)
Reviewed by:
rincipal Civil Engi Tf eer z Dater
40
0
5
45
Re�r•omme ded f. approval by:
ager
Agreed to and Accepted by: A.proved by:
Industrial Coating
Date City En
cc: Contractor, Construction File, Project Manager, City Clerk
1243 National City Boulevard
National City , CA 91950
10
City Manager Date
`required for Change Orders at or exceeding $25,000.00
Tel (619) 336-4380
Fax (619) 336-4397
ATTACHMENT "A"
I+ NUS EttE U1lAl u11T
a ltr...:.�....rirl
J1lll a r +'-+esrtit lUI
2534 Oceanside Blvd- Oceanside, California 92054 Ph. 760.500.9264 Fax 760.966.0602 License number 880502
email address: z-bomb@sbcglobal.net or mmerzi@yahoo.com
TO: CITY OF NATIONAL CITY
1243 NATIONAL CITY BLVD.
NATIONAL CITY, CA 91950
SUBJECT: CONTRACT # 09-20 WATERPROOFING AND STAIRCASE REPAIR
CHANGE ORDER #001 revised
ADDITIONAL WORK AS FOLLOWS:
CONCRETE MASONRY UNIT JOINTS UNDER WINDOW
716 LINEAL FEET @ $5.50 foot MATERIALS AND LABOR $3,938.00 1 DAY
Clean, Prime, and Seal with Sika Flex Lime Stone under window around building
As stated in our meeting last years prices were 6.50$ a foot — offer 5.50$ a foot
CONCRETE SLAB AT WALL ON RAMP
43 LINEAL FEET @ 8.25 MATERIALS AND LABOR $345.75 1 DAY
Grind, Clean, Prime and Seal at Ramp entry at front by elevator
Requires additional attention in most areas
THE FOLLOWING IS OFFERED IN EXCHANGE FOR PLANT REPLACEMENT PART OF CONTRACT
PREP PRIME AND PAINT RAILS DOORS AND STAIRS FRONT AND BACK PARKING EXTERIOR
1 PRIME 2 FINISH MATERIALS AND LABOR $3200.00 3 DAYS
OVERALL PROPOSAL TOTAL: $4,283.75 WITH AN ADDITIONAL OF 2 DAYS TO PROJECT
WEATHER DELAY DAYS TO BE CALCULATED AND SUBMITTED IF NECESSARY.
M. MERZI — PRESIDENT
N.MERZI — PROJECT MANAGER —SAN DIEGO REGIONAL REP.
MARCH 16, 2010
#1
#2
PO#
Vendor
PO Amount
Adi P1 Ant;
PO Balance
73472
Industrial Coating and Restoration Services
Type of service = .
73,000.00 National City Police Dept Waterproofing
77,283.75 and Staircase Repair Project, Spec 09-20 (Construction)
7,728.38
?a unt No
Amount `: m
Balance,`
4/6/2010
011-409-500-598-1408
„7
ount.0
AcctAdjusted Amount
77, : .75
69,555.37
Invoice Nu be
Inv P mt #1
0 No.
1
2
3
4
5
Total
•',555. 7
ount._..... ._.
$
4, 283.75
Change 0rdei
escriptio.r...
CCO#1: CMU 'oints, router, & seal cracks
iunt cr; j
M1O nt. ...,,a
�atancg.
jtivoice Datci .. ;
Adjusted Account PO BS
arice
Amount
Invoice Number
C/O No,
1
2
3
4
5
ota
ount
Change 0rder Descr pt on
+- CALIFORNIA ^+�
NATIONAL CITp
POLICE DEPARTMENT WATERPROOFING & STAIRCASE REPAIR
Specification #09-20
Contractor: Industrial Coatings, Inc.
CHANGE ORDER No. 2
May 25, 2010
Reason/Purpose for this Change Order:
This change in the orginal contract is to repair the base of two (2) columns supporting the walking bridge at the
front of City Hall that were damaged as a result of the earthquake in April. The columns are cracked at the base
and although this damage does not constitute a structural emergency, the immediate repair is necessary to
prevent the structural steel within the column from rusting and losing structural integrity.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor shall repair the cracks in the columns in the following manner:
1) Saw cut around damaged / spalled areas a minimum 1/8 inch.
2) Remove deteriorated concrete and expose rebar creating a minimum surface profile of approximately 1/16"
(CSP-5).
3) Clean steel by mechanical means to remove all traces of rust and prime with Sika Armatec 110.
14) Prime concrete with a scrub coat of Sika Top 123.
15) Install Sika Top 123 Plus in lifts not to exceed 1.5 inches with a minimum of 30 minutes between lifts. Finish
j smooth.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 3 Working days subtracted: 0
Submitted by:
....:..:........................
Project Manage
°
ate CityMana er, required for Change Orders >$24 999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents at costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and there will be no further compensation. All of the terms and conditions of the orginal contract documents are
incorporated herein.
73,000.00
4,283.75
77,283.75
2,650.00
79,933.75
Date
Accepted and agreed to by Industrial Coatings, Inc.
moud Merzi ' Date 1
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
25/('
1243 National City Boulevard, National City, CA 91950
Telephhone (619) 336-4380
#1
#2
Pp#
Vendor
Po Amount
Adj PO Anit
PCB Balance
73472
Industrial Coating and Restoration Services
Type of sere c
73,000.00 National City Police Dept Waterproofing
79,933.75 and Staircase Repair Project, Spec 09-20 (Construction)
$
10,378.38
Account;M plIGERif'li.
n?ouflt ..;
9nvoiCOO atee iL,L';ad
73, 000.00
4/6/2010
Acot.Adjusted Amo t
$
69,555.37
Inv P mt #1
C/O No.
1
2
3
4
5
Total
Amount
4, 283.75
2,650.00
Change Order
Description.
CCO#1: CMU oints, router, & seal cracks
CCO#2: re.air base of 2 columns of NC Cit Hall welkin. brid.e
• 75'
Account No. �
Amount
Balance , .. .
.invoice Datea
Adjusted Account PA Balance
Amount..__.
nvgice Number
C/0 No
1
2
3
4
5
otal
Amount
Change Order Description
,►- CALIFORNIA -+
NATIONAL CI17
POLICE DEPARTMENT WATERPROOFING & STAIRCASE REPAIR
Specification #09-20
Contractor: Industrial Coatings, Inc.
CHANGE ORDER No.3
May 25, 2010
Reason/Purpose for this Change Order:
This change in the orginal contract is to move the irrigation controller from inside a security closet within the
Police Department underground parking structure to the outsideof the wall so maintenance staff can have
access to the controller without a police escort.
The City of National City and Contractor agree to the following change to the original Contract:
!The Contractor shall remove the existing irrigation controller from inside the secure area within the Police
Department underground parking garage, extend the electrical conduit and wiring to the outside of the adjacent s
wall, install a City provided irrigation clock on the exterior of the wall at a four foot height and reconnect the
;electrical and irrigation controller wiring. All conduits and wiring shall match existing in size and kind. Wall
;fasteners shall be Redheads for CMU walls for permanent installations. Contractor shall ensure that the
controller is functioning properly upon completion.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 3 Working days subtracted: 0
Submitted by:
Date ,City P
A
73,000.00
6,933.75
79,933.75
950.00
80,883.75
LEI er�b ?"/ 0
Date
City Engineer 17ate ,City Manager, required tor Change Orders >$24999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and there will be no further compensation. All of the terms and conditions of the orginal contract documents are
incorporated herein.
Accepted and agreed to by Industrial Coat'
Inc.:
�...J,..,).p..............1
u• Merzi/President Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
!'
1243 National City Boulevard, National City, CA 91950
Telephhone (619) 336-4380
#1
#2
Pam...$
Vendor, `" F
Po Amountw.
Adj POAmt
PO Balance
73472
Industrial Coating and Restoration Services
Type of service
$ 73,000.00 National City Police Dept Waterproofing
$ 80 883.75 ; and Staircase Repair Project, Spec 09-20 (Construction)
$ 11 328.38
Account No,
AAmount'
I3atance_ ..
Invoice Date ,
001-409-500-598-1408
73,000. $0
4/6/2010
A
aunt.;
69, 555.37
Acct Adjusted Amount
Invoice Number
Inv P mt #1
Total
Q10No.
1
2
3
4
5
otal
. • 555,
Amount..
4,283.75
2,650.00
950.00
Chant
Order Iescriptiort _�
CCO#1: CMU "ants, router, & seal cracks
CCO#2: re.air base of 2 columns of NC Ci Hall walkin• bride
CCO#3: move irri•ation controller from inside to outside of securit closet
Account eNoJ �
Amount,. „„
8atance " ., '•
nvoice,Dateati ,Wr
Adjusted Account PC? Balance
aunt N
nvoice Number
Total
1
2
3
4
5
Total
Artiouf t
Change Order Description .a
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone • 619-336-4229 fax
INDUSTRIAL COATING & RESTORATION SERVICES
Change Order #s 1, 2 and 3
Police Dept. Waterproofing & Staircase Repair
Judy Hernandez (Engineering) Forwarded
Copy of Change Orders to Contractor