HomeMy WebLinkAbout2010 CON Koch Armstrong - Change Order #1 Marina Gateway Streetscape, FY 09-10CHANGE ORDER #1
March 3, 2010
Project: Marina Gateway Streetscape Specification #08-16
Contractor: Koch -Armstrong
A Change Order is hereby recommended for the following work in the amount identified below:
Description of Change in the Contract
See Attachment "A".
Justification for Change in Contract
This change in contract is for the removal and relocation of four hundred and ninety-five (495) lineal feet of
chain link fence, posts, and gates at 23rd Street and Cleveland Avenue. This change order is necessary
because the location of the existing chain link fence is in conflict with new sidewalk improvements. In order to
accommodate the installation of the sidewalk improvements the fence must be removed. This condition was
not known at the time of the original contract because it was not shown on the plans. The work for this change
order will be performed by Koch -Armstrong, a contractor experienced with and qualified to perform such work.
Cost Reconciliation
See Attachments "A & B".
Construction Contract Accounting Summary
Original Contract Amount:
Net change by previously authorized Change Orders:
Contract amount prior to this Change Order:
Amount of this change order:
New contract amount:
Original contract time (calendar days): 120
Previously approved additional working days: 0
Additional working days for this change order: 0
Total contract time (working days): 120
(see Weekly Statement of Working Days for completion date)
Reviewed by:
A/.A
r cipal Civil Engin er ate
Agreed to and Accepted by:
d 03/C8/10
�b fcfmstrong Date
General Engineering, Inc.
cc: Contractor, Construction File, Project Manager, City Clerk
1,916,282.35
1,916,282.35
3,785.67
$ 1,920,068.02
Recommended for approval by:
1243 National City Boulevard
National City , CA 91950
Tel (619) 336-4380
Fax (619) 336-4397
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT "A" CO #1
Description of Change in the Contract
This change in contract is for the removal and relocation of four hundred and ninety-five (495) lineal feet of
chain link fence, posts, and gates at 23rd Street and Cleveland Avenue.
Cost Reconciliation
This change in the contract was reviewed and negotiated by and between the City Representatives and the
Contractor and represents the entire agreement for the work described herein and includes all costs
associated with the work including but not limited to manpower, equipment, labor, fees, taxes, insurance,
bonding, overhead, profit, etc. and there will be no other compensation. This Change Order hereby
incorporates the original contract and all its referenced documents' terms, conditions, and plans for the work
as provided by the City.
CITY OF NATIONAL CITY
Marina Gateway Streetscape
Specification No. 08-16
ATTACHMENT "B"
CO #1
ITEM
DESCRIPTION
QUANo ITY/
UNIT
UNIT PRICE
TOTAL
1
Labor
Foreman Operator (1)
10
HR
72.00
720.00
Laborer (3)
30
HR
54.00
1,620.00
Item #1 Sub -total:
2,340.00
Mark-up Cost:
20.00%
468.00
Item #1 Cost:
2,808.00
2
Material Equipment and Rentals
Crew Truck (1)
10
HR
25.00
250.00
Bobcat (1)
10
HR
25.00
250.00
Bobtail (1)
10
HR
30.15
301.50
Item #2 Sub -total:
801.50
Mark-up Cost:
15.00%
120.23
Item #2 Cost:
921.73
SUB -TOTAL
3,729.73
Bond Cost:
1.50%
55.95
CHANGE ORDER PROPOSAL TOTAL
1
LS
3,785.67
f
KOCH-ARMSTRONG GENERAL ENGINEERING,
INC.
CO-1
P.O. BOX 1190, LAKESIDE, CA 92040-0906
TEL: (619) 561-2005 FAX: (619) 561-0317
KOCH•ARMSTRONG LICENSE 194819-A
QUOTATION
10-011.2 COP-2
PAGE 1 (REVISED 3-2-10)
TO: NATIONAL CITY ATTN: BYRON WADE
1243 NATIONAL CITY BLVD. TEL: (619) 336-4380
NATIONAL CITY , CA. 91950 CELL:
FAX: (619) 336 4397
DATE: 3/4/2010 EMAIL: byronwadel@mac.com
We propose to furnish all labor, material, and equipment necessary to perform the following items of work, subject to terms and conditions stated.
This quotation expires 30 days from the date above and is good for work completed within one year of date above unless otherwise noted.
JOB LOCATION 23rd AND CLEVELAND AVENUE.
IDENTIFIED MARINA GATEWAY STREETSCAPE CHANGE ORDER PROPOSAL #2: RELOCATE EXISTING CHAIN LINK FENCE & GATES
ITEM
DESCRIPTION
APPROX.
QUANTITY
UNIT
UNIT PRICE
TOTAL
1
REMOVE APPROXIMATELY 495LF CHAIN LINK FENCE, POSTS & GATES. STOCKPILE ONSITE.
495
LF
LABOR
1 FOREMAN OPERATOR
10
HR
72.00
720.00
3 LABORER
30
HR
54.00
1620.00
SUBTOTAL
2340.00
MARKUP
0.20
468.00
TOTAL -LABOR
2808.00
EQUIPMENT/ RENTAL
1 CREW TRUCK
10
HR
25.00
250.00
1 BOBCAT
10
HR
25.00
250.00
1 BOBTAIL
10
HR
30.15
301.50
SUBTOTAL
801.50
MARKUP
0.15
120.23
TOTAL- EQUIPMENT/RENTAL
921.73
TOTAL- LABOR & EQUIPMENT/RENTAL
3729.73
ADD BOND
0.015
55,95
COP-17(RV.1) TOTAL
1
LS
3785.00
TERMS:
1
INCLUDES: ONE MOVE IN, PREVAILING WAGE RATES, BOND COST, STOCKPILING FENCE ONSITE, REMOVAL OF FENCE IN MOST EXPEDIANT MANNER.
2
EXCLUDES: NIGHT/ WEEKEND/ HOLIDAY WORK DAYS, ANY WORK/LABOR/ MATERIALS OR ITEM NOT SPECIFICALLY STATED IN QUOTE,
EXPORT, RESPONSIBILITY FOR DAMAGED FENCE AS A RESULT OF REMOVAL, REMOVAL OF CONCRETE FROM FENCE POSTS.
CONDITIONS:
1.Does not include permits, bonds, any form of engineering(staking, testing, inspection, etc.), base under concrete, redwood headers, striping, traffic control, or utility adjustment unless otherwise specified.
2. Monthly Progress Payments and Full Payment upon completion. Accounts are delinquent after 30 days, and they are subject to the maximum finance charge allowable by law.
3. Work to be done in accordance with plans, specifications, and quantities identified above. Koch -Armstrong General Engineering, Inc. shall be notified in writing prior to any proposed changes.
4.Subgrade to be taken from .\- .10' to balance and at or below optimum moisture before Koch -Armstrong General Engineering, Inc. begins work unless otherwise specified.
5. Any unusual conditions of subsoil encountered, such as buried slabs, underground piping, trash deposits, etc. shall be deemed cause for additional charges.
6. Required California Preliminary Lien information (California Civil Code Section 3097(3098) shall he provided to Koch -Armstrong General Engineering, Inc. before work begins.
7 Subject to Credit Approval and verification of California Preliminary Lien information.
8. Class 2 malenal if included is 314" recycled Class 2 per Caltrans Standard Specification Section 26 unless otherwise noted.
Acceptance:
Please sign and return one copy -this quotation constitutes the
sole and only agreement. Any prior agreements, negotiations,
etc., not set forth herein are of no force or effect.
Firm: NATIONAL CITY
KOCH-ARMSTRONG GENERAL ENGINEERING, INC.
By:
By:
Date FRANK HERRERA
Date
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, Califomia 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone • 619-336-4229 fax
KOCH ARMSTONG GENERAL ENGINEERING, INC.
Change Order #1
Marina Gateway Streetscape, FY 09-10
Tess Corpuz (Engineering) Forwarded
Copy of Change Order to Contractor