El TOYON SOCCER FIELD CHANGE ORDER NO. 2
Specification #07-01 December 1, 2010
Contractor: OHNO Construction Co.
Reason/Purpose for this Change Order:
Due to new information gathered on the existing sewer main beneath the soccer field, it was determined that the
'new main can be relocated from under the field. The new alignment and grades are designed and delivered to
,the contractor. The City and contractor agree that the new sewer alignment will be done at existing line item
;prices for actual quantities places.
The City of National City and Contractor agree to the following change to the original Contract
The Contractor shall perform all of the work necessary to install the new sewer main, laterals, manholes and
connections per the drawing attached as exhibit "B". The change in quantities shall be those actually placed in
the field and are represented on attachment A. The City and contractor agree that the contractor will be paid
in accordance with the bid prices for each line item actually placed in the field and there shall be no deduction or
addition to any line item or otherwise for the work completed. Further the new alignment allows for the
installation of the new main to be done without pumping. In exchange, the contractor will upgrade the sewer
main from 10" PVC to 12" PVC at no additional cost to the City. All work shall conform to the contract
documents. The amount shown on this change order is for estimate purposes only. The actual changes to
quantities shall be shown on the respective line items and shall be paid accordingly.
Original Contract Amount $ 440,642.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Submitted by:
Pro1ec
Appr
Working days subtracted: 0
CZ._!S_(a
Date
12-1 V.--1 O
-Ci-Engineer Date 'City Manager, required for Change Orders >s24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, leans and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
18,730.53
459,372.53
10,973.70
Percent change in Contract to date 6.74%
470, 346.23
Acc pted and agreed to by OHNO Construction:
Name:', i Date
Note to C\Ontractoi: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim,
originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
—. CALIFORNIA --,
IO AL (i
:1.,J'J
MCPRYORAT
EL TOYON SOCCER FIELD
Specification #07-01
CHANGE ORDER #2, Attachment "A"
NO.
ITEM DESCRIPTION
UNTIS
QTY
PRICE
EXTENSION
14
Replace existing 10" sewer main
LF
489
$ 55.30
$ 27,041.70
15
Replace existing 8" sewer main
LF
30
$ 52.60
$ 1,578.00
16
Connection to existing sewer main
EA
3
$ 1,370.00
$ 4,110.00
17
Replace existing sewer lateral with 6" PVC
LF
275
$ 42.30
$ 11,632.50
18
Replace existing manholes
EA
2
$ 9,000.00
$ 18,000.00
19
Install 6" sewer lateral cleanout
EA
3
$ 500.00
$ 1,500.00
Subtotal
$ 63,862.20
NO.
ITEM DESCRIPTION
UNTIS
QTY
PRICE
EXTENSION
14
Replace existing 12" sewer main
LF
578
$ 55.30
$ 31,963.40
15
Replace existing 8" sewer main
LF
0
$ 52.60
$ -
16
Connection to existing sewer main
EA
2
$ 1,370.00
$ 2,740.00
17
Replace existing sewer lateral with 6" PVC
LF
275
$ 42.30
$ 11,632.50
18
Replace existing manholes
EA
3
$ 9,000.00
$ 27,000.00
19
Install 6" sewer lateral cleanout
EA
3
$ 500.00
$ 1,500.00
Subtotal
$ 74,835.90
Subtotal for original contract
$ (63,862.20)
Change Order Estimate
$ 10,973.70
* All quantities listed are approximate. Contractor will be paid only for work actually peformed and accepted by the City.
**All listed prices are approximate and listed only for purposes of obtaining estimate. Contractor will be paid only for work actually
performed and accepted by the City.
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone • 619-336-4229 fax
OHNO CONSTRUCTION
Change Order #2
El Toyon Soccer Field
Judy Hernandez (Engineering) Forwarded
Copy of Change Order to Contractor