HomeMy WebLinkAbout2011 CON MJC Construction - Change Order #2 Parks ADA Access Upgrades & Park Garden ProjectPARKS ADA ACCESS UPGRADES & PARK GARDEN
Specification #10-05
Contractor: MJC Construction
CHANGE ORDER NO. 2
March 17, 2011
Reason/Purpose for this Change Order:
This Change Order is at the request of the City to reduce the contract amount by $10,010.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor and the City agree to reduce line item 2a Kimball Park, 6" sidewalk replacement by 1,430
square feet at $7.00 per square foot for a total reduction of $10,010.00
Original Contract Amount
..................... $
Net change by previously authorized Change Orders...
Subtotal
Amount of this change order
New contract amount $ 231,997.50
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date -4.14%
242,007.50
242,007.50
(10,010.00)
Submitted by:
by:
City Engineer
Date
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by MJC Construction:
3�/T�//
Jimenez, MJC Construction D to
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
MJC CONSTRUCTION
Change Order #2
Parks ADA Access Upgrades & Park Garden
Barby Tipton (Engineering) Forwarded
Change Order to Contractor