PARKS ADA ACCESS UPGRADES & PARK GARDEN
Specification #10-05
Contractor: MJC Construction
Reason/Purpose for this Change Order:
!Due to the lead time for obtaining the welded wire fence Alternate Bid "D", Vinyl Coated Change Link Fence
shall be installed in lieu of Alternate Bid "C", Welded Wire Fence.
CHANGE ORDER NO. 1
February 21, 2011
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor agrees to install all items listed in Alternate Bid "D" at the prices listed in the Contractor's
Bidder's Proposal. The Contractor also agrees not to install those items listed in Alternate Bid "C". All payments,
i.: for this change order will be paid as line item work. The City and Contractor agree that quantities of work for the
'Kimball Park portion of work equal to the difference in price between Alternate Bids "D" and "C shall be removed
`from the scope of work to make this a zero sum change order and there will be no other costs to the City.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Submitted by:
Working days subtracted: 0
Date
City'Englneer Date
242,007.50
242,007.50
Percent change in Contract to date 0.00%
City PrlSject Manager
242,007.50
O3/z/i
Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by MJC Construction:
er Jimenez, MJC Construction
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
��
i f V � �i nasG �//
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
MJC CONSTRUCTION
Change Order #1
Parks ADA Access Upgrades & Park Garden Project
Judy Hernandez (Engineering) Forwarded
Copy of Change Order to Contractor