El TOYON SOCCER FIELD
Specification #07-01
Contractor: OHNO Construction Co.
CHANGE ORDER NO. 6
March 3, 2011
Reason/Purpose for this Change Order:
This change order addresses the addition of goal post pads for the recently installed goal posts at El Toyon
Sports Field. The goal post pads will provide protection for users of the sports field. The color yellow was
;selected for visibility and safety purposes. Delete one tree for a total installation of 6 trees instead of 7.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor shall install two (2) yellow round football goal post pads to fit 6.5" diameter gooseneck goal
'posts at El Toyon Sports Field. This change order shall be paid as a lump sum and includes all materials,
equipment, labor, etc. to complete the installations. There will be no further costs to the City. The deletion on
one tree per line item #1, Additive Bid H, (-$1,600.00).
Original Contract Amount $ 440,642.20
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
181,547.73
622,189.93
(775.34)
New contract amount $
Working days added: 0
Submitted by:
Working days subtracted: 0
:City En ineer Date i rI City Manager,, required for change ordars>s24,ssa Date
................. ...
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the puce stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor. supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by OHNO Construction:
Percent change In Contract to date 41.02%
621,414.60
Name:
Note to Contra
r. If you dd not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1Z43 National city rsoulevara, rvauonol Clty, CA 91950
Tolophono (610) 336-43110
4—CALIFORNIA
NATIONAL CITY
l� INCO PO J 8D ✓
EL TOYON SOCCER FIELD
Specification #07-01
CHANGE ORDER #6, Attachment "A"
1
DESCRIPTION
Materials: Round go& post pads to fit 6.5" diameter gooseneck.
Fully encased in vinyl. Color: Yellow,
UNITS
LS
QTY
1
UNIT PRICE
$ 710.00
EXTENSION
$ 710.00
Lump Sum Price:
Contractor Mark-up (15%):
Bond (1"/0):
TOTAL:
710.00
$ 106.50
8.17
824.67
DESCRIPTION
UNITS
QTY
UNIT PRICE
EXTENSION
H #1
DEDUCT-Tipuana Tree
LS
$ 1,600.00
$ (1,600.00)
Total Change Order
$ (775.34)
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
OHNO CONSTRUCTION
Change Order #6
El Toyon Soccer Field
Construction Improvements
Judy Hernandez (Engineering) Forwarded
Change Order to Contractor.