PARKS ADA ACCESS UPGRADES & PARK GARDEN
Specification #10-05
Contractor: MJC Construction
CHANGE ORDER NO. 3
May 12, 2011
Reason/Purpose for this Change Order:
!This change order will adjust quantities of some of the items of work to make room in the budget for newly
?identified higher priority ADA complaince work in El Toyon Park. The additional work will provide ADA access
;around the Sports Field and Dog Run facilities with asphalt instead of DG for all weather access. The additional
jclearing, grubbing and grading includes removal of tree stumps, grading for new fence alignment and disposal
of excess and diliterous material to provide better ADA acccess in and around the El Toyon Park.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor agrees to perform grading, clearing, grubbing and restoration work in El Toyon Park as shown
on Attachment "A" in the amount of $4,525 and additional grading and asphalt paving as shown on Attachment
"A" in the amount of $23,200 and reduce the quantity of work in Kimball Park for the various items of work which
makes this a zero sum change order and there will be no other additional costs to the City.
Original Contract Amount $ 242,007.50
Net change by previously authorized Change Orders (10,010.00)
Subtotal 231,997.50
Amount of this change order
New contract amount $ 231,997.50
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date -4.14%
Submitted by:
City Pr ject er Date
CI ngl _ Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit. etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by MJC Construction:
aver Jimenez, MJC Construction
..5//2 2,C2//
ate
Note to Contractor. If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim,
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
ADAAccess Upgrades & Park Garden
Specification No. 10-05
Change Order #3, Attachment "A"
May 12, 2011
Line Item Reductions
Original Contract
Line Item Reductions
No.
Item
Unit
Quantity
Unit Price
Amount
Quantity
Amount
Additive Bid "A"(Kimball Park)
2a
R&R 6" Sidewalk
SF
7,585
7.00
53,095.00
(3,889.00)
(27,223.00)
4a
New 4" Sidewalk
SF
200
8.00
1,600.00
(62.75)
(502.00)
54,695.00
(27,725.00)
Extra Work
Increases
a*
Grade and Pave 2" AC at El Toyon forADA at Soccer
Field, +/- 160 tons
LS
1
23,200.00
23,200.00
1.00
23,200.00
b*
Additional clearing, grubbing and grading
LS
1
4,525.00
4,525.00
1.00
4,525.00
27,725.00
Total Change in Contract Amount
*These items will be indicated on future invoices as line items CO#3 a & b
All pay quantities for line item work on all invoices shall be for actual quantities installed only.
s
PARKS ADA ACCESS UPGRADES & PARK GARDEN
Specification #10-05
Contractor: MJC Construction
CHANGE ORDER NO. 4
May 17, 2011
Reason/Purpose for this Change Order.
This Change Order is to add pedestrian ramps, curb, gutter and sidewalk on 17th Street at the request of the
City.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor agrees to remove and dispose of existing concrete improvements and install 2 pedestrian
ramps, 20 I.f. of curb and gutter and 105 square feet of 4" sidewalk per the applicable regional standard
drawings. The work shall be completed by May 27th including cleanup and restoration. The total cost for the
work shall be $4,850 which includes but is not limited to labor, materials, equipment, fees, overhead, taxes,
subcontractors, bonds and profit and there shall be no additional cost to the City.
Original Contract Amount $ 242,007.50
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
Percent change in Contract to date -2.13%
City =
(10,010.00)
231, 997.50
4,850.00
236, 847.50
l
Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by MJC Construction:
CJavier Jr m nez, MJC Construction
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
ADAAccess Upgrades & Park Garden
Specification No. 10-05
Change Order #4, Attachment "A"
May 17. 2011
Added work on 17th
No.
Item
Unit
Quantity
Unit Price
Amount
1*
Mobilization
LS
1
300.00
300.00
2*
R&R 4" sidewalk
SF
105
6.00
630.00
3*
R&R Curb & gutter
LF
20
20.00
400.00
4*
Install pedestrian ramps
EA
2
1,500.00
3,000.00
5*
Traffic Control
LS
1
260.00
260.00
6*
Water Quality Control
LS
1
260.00
260.00
TOTAL COST
4,850.00
*These items will be indicated on future invoices as a lump sum, line item CO#4
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
MJC CONSTRUCTION
Change Order #3 and #4
Parks ADA Access Upgrades & Park Garden
Judy Hernandez (Engineering) Forwarded
Copy of Change Orders to Contractor