PARKS ADA ACCESS UPGRADES & PARK GARDEN
Specification #10-05
Contractor: MJC Construction
'iEPT.
CHANGE ORDER NO. 5
2011 JUL I LI P 3: jfille 22, 2011
Reason/Purpose for this Change Order:
The ADA improvements for the parks are complete for this phase. Any additional ADA improvements would
require more funds than are remaining and available for this budget. This reduction is $9,848.00 and represents
approximately 4% of the contract total.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor and the City agree to reduce various line items of work as represented on the attached
spreadsheet and that there will be no additional compensation or credits for this reduction in line item work.
Original Contract Amount $ 242,007.50
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
Percent change in Contract to date -6.20%
(5,160.00)
236, 847.50
(9,848.00)
226, 999.50
Submitted by:
•
Project Manager ' Date
-7— 1a/c(
ineer Date City Manager, required Tor Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by MJC Construction:
Javier Ji enez, MJC Const ction
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
k 1 _�
CITY OF NATIONAL CITY
ADAAccess Upgrades & Park Garden
Specification No. 10-05
Change Order #5, Attachment "A"
June 22, 2011
Line Item Reductions
Original Contract
Line Item Reductions
No.
Item
Unit
Quantity
Unit Price
Amount
Quantity
Amount
El Toyon Park
3
R&R 6" Sidewalk
SF
850
6.00
5,100.00
(618.00)
(3,708.00)
6
Pedramps
EA
7
1,500.00
10.500.00
(4.00)
(6,000.00)
7
New 6" curb edge
LF
400
10.00
4,000.00
(14.00)
(140.00)
Total Deductive Contract Amount $ (9,848.00)1
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
rNQURP03iA Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
MJC CONSTRUCTION
Change Order #5
Parks ADA Access Upgrades & Park Garden Project
Judy Hernandez (Engineering) Forwarded
Copy of Change Order to Contractor