National City Chiller Replacement Project
Specification #11-01
Contractor: Green Building Technologies, Inc. dba Green Mechanical Contractors
CHANGE ORDER NO. 1
September 2, 2011
!Reason/Purpose for this Change Order:
!Due to a clerical error, the contract mistakenly listed $415,038.00 as the original contract amount, which is
''$1,000.00 more than the correct amount of $414,038.00 found on the Contractor's Bidder's proposal.
The City of National City and Contractor agree to the following change to the original Contract:
The original contract amount on the contract for this project is amended to show an original contract amount of
$414,038.00 to match the Contractor's Bidder's proposal.
Original Contract Amount
Net change by previously authorized Change Orders...
Subtotal...
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
Percent change in Contract to date
415,038.00
$
-0.24%
415,038.00
(1,000.00)
414,038.00
Submitted by:
9-4-!/
Date
DateAl
;City Manager, required for change orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorpora t. herein.
LAccepte
Date
Note to Con. actor: If ou do n
and you may proceed under p
Originals: City Clerk, Contractor
een -Mechanical Contractors:
with this Change Order you may be directed to proceed with this work under the terms of the contract
You must comply with the contract requirements of submitting a written protest to protect your claim.
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
GREEN MECHANICAL CONTRACTORS
Change Order #1
Chiller Replacement Project
Lynn Cole (Engineering) Forwarded
Copy of Change Order to Contractor