AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
SAN DIEGO GAS & ELECTRIC COMPANY (SDG&E)
THIS AGREEMENT is entered into this 19th day of June, 2012, by and between the CITY
OF NATIONAL CITY, a municipal corporation (the "CITY"), and San Diego Gas & Electric
Comany (SDG&E).
RECITALS
WHEREAS, SDG&E desires to enter into a Joint Trench Agreement for installation
of electric distribution and service facilities in the trenches of Underground District No. 24 (20A
Conversion 8th Street) SDG&E project No. 532152-070, and
WHEREAS, SDG&E has submitted a Joint Trench Letter in the not -to -exceed
amount of $1,670,915 (attached Exhibit A),
NOW, THEREFORE, THE PARTIES HERETO DO MUTUALLY AGREE AS
FOLLOWS:
1. The CITY to provide trenching, backfill, substructures (concrete products, conduit,
retaining walls), pavement repair, any adjustments to final grade, required permits, and
environmental release.
2. Trench, backfill, installation of conduit system with pull string shall be accomplished to
SDG&E General Conditions and governing agency specifications.
3. SDG&E shall reimburse the City in an amount up to $1,670,915 for the joint trench costs
including SDG&E's share of cost for (1) construction, (2) general work for dry utilities, and
(3) inspections and project management. Exhibit B describes the work that is included in
shared costs. SDG&E's share of costs shall be determined by the total costs attributable
to the dry utilities divided among participating dry utilities as shown in Exhibit B
4. All increases to costs must be agreed upon by both parties, in writing, prior to the City
approving any change orders. Such approval shall not be unreasonably withheld.
5. San Diego Gas & Electric will provide and install all SDG&E materials for cabling of said
project. Delivery of SDG&E materials shall not be unreasonably delayed.
6. SDG&E will provide on -site inspection for SDG&E conduit system and substructures.
7. The CITY shall provide the as -built drawings to SDG&E.
8. The City shall provide proper documentation to SDG&E in order to collect reimbursement
from SDG&E on a regular basis as progress payments are made to the City's contractor
for SDG&E work including any approved changes. Such payments to be no less than
quarterly, nor more frequent than monthly.
9. SDG&E agrees to indemnify, defend, and hold harmless, the City of National City and its
officers and employees against and from any and all liability, loss, damage to property,
injuries to, or death of any person or persons, and all claims, demands, suits, actions,
proceedings, reasonable attorney's fees, and defense costs, of any kind or nature,
including worker's compensation claims of or by anyone whomsoever, resulting from or
arising out of SDG&E's negligent performance under this agreement.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the
date and year first above written.
CITY OF NATIONAL CITY
Morrison, Mayor
OV DOF
udia G. Sil
City Attorn
M:
San Diego Gas & Electric Company
(Corporation — .signatures of two corporate officers)
(Partnership — one signature)
Se propietorship — one signature)
;':":
• 1
(4� a:'C
(Rick Gardner)
(Print)
K6-11.0-y-11A--e-A
(Project management Mgr.)
y: (2' z`.'i -'- f
✓(Alan Marcher)
/-/10.. 41
(Print)
/
i‘cx,)<_;iJ�f
(Managdd- Project Management)
2
City's Standard Agreement — June 2008 revision
SDG
A A' Sempra Energy utility'
February 16, 2012
Steve Manganiello C.E.
City Engineer
1243 National City Blvd.
National City, Ca. 91950
San Diego Gas S Electric
8315 Century Park Court
San Diego, CA 92123-1548
FILE NO. PLA
PROJ# 532152-070
Dear Steve:
Subject: 8th Street 20A Conversion — UUD # 24, N.C. BI. To Highland Av.
SDG&E has completed the preliminary engineering review required to replace the existing
overhead electric facilities with an underground system at the above location.
A final design and cost estimate for your conversion has been prepared based on the option
that the city will bid for the following work:
• Contractor to provide trenching, backfill, substructures (concrete products, conduit,
retaining walls), pavement repair, any adjustments to final grade, required permits, and
environmental release. SDG&E General Conditions and underground standards are to
be incorporated into the bid document. In the event of inconsistencies between the
Municipal bid documents (municipal General Conditions) and SDG&E's General
Conditions, the most stringent shall prevail and will be subject to mutually agreed upon
and negotiated benefits. SDG&E underground standards can be accessed at
http://sdge.com/documents/underground-construction-standards
• San Diego Gas & Electric to furnish and install cable, pad -mounted equipment,
connections and removal of overhead facilities.
Prior t: awarding the contract, the city will submit a copy of the first, second and third
acceptable bids to SDG&E for review and approval. If approved, SDG&E will reimburse the city
for this work (based on the contractor's bid) up to our estimated value of $1,670,915. At the
completion of the contractors' portion of their work, SDG&E's overhead costs applicable to this
work, including any re -engineering fees, if applicable, will be deducted from the municipality's
20A allocation.
In the case that all bids exceed the maximum reimbursable amount, SDG&E reserves the right
to reject all municipal bids and may elect to do the electric conversion trench independently. In
order to allow the City's bidding contractors to properly separate the cost of installing SDG&E's
conduit infrastructure from that of the telecommunications companies, I would like to meet with
the City and the bidding contractors prior to bid submittal. This will help ensure consistency
among the bids for the conversion trench & conduit installation phase of the project.
Please note the above costs do not include the installation of any ornamental street lights or
street light services that might be required by the City of National City. Street lighting is not
reimbursable under Rule 20. However, the City can make use of the available conversion trench
and conduit for street light conduit installation.
^ 2 February 16, 2012
The City of National City will be responsible for acquiring Joint Trench Offers. AT&T, Cox
Communications Inc., and Media 3 have planned on participating in the Joint Trench, which
minimizes costs to the joint trench utilities, lessens the amount of trench and surface repair, and
reduces the overall cost of trenching. The offers received by SDG&E are no longer valid. Once
the City acquires the offers, SDG&E can provide a courtesy review for reasonableness, at the
City's request.
Bids shall include separate line items for installation of SDG&E and the other dry utilities. Bids
are to include service conduit, but not service panel conversion work, which will be facilitated by
SDG&E.
A Pre -Construction Conference shall be held in advance of construction to coordinate with all
dry utilities participating in Joint Trench. SDG&E will be represented in the field by a Trench
Inspector. Change orders will be reviewed and approved by SDG&E's Project Manager, prior to
the work taking place.
Invoices shall be submitted to SDG&E's Project Manager. Billing can occur at completion, or on
a regular basis, not to exceed once a month, and shall include necessary invoices and support
information, satisfactory to SDG&E, to justify reimbursement. Reimbursement will occur
accordingly, after review and approval by SDG&E's Trench Inspector.
All costs and offers quoted in this letter shall become void at the end of the business day on
May 14, 2012. If business negotiations are not completed, or if you request revised costs after
that date, a cost update fee may be required. Your costs, as cited herein, are subject to change
at any time. All cost calculations are based upon SDG&E's filed tariffs, SDG&E's internal costs,
and all applicable governmental or regulatory statutes, regulations, codes and rules. Should any
change in, or addition to, those tariffs, costs, statutes, regulations, codes or rules in any way
impact these cost calculations, you will be subject to any resulting increase or decrease.
If 1 may be of further assistance or if you have any questions, please call me at the number
listed below. Our hours are 7:00 am —4:00 pm, Monday through Friday. For additional general
information, please visit our website at http://sdge.com/index.html.
Sincerely,
David D=v::..J. Emerson
Governmental Liaison Planner SDG&E
Telephone: (858) 654-1136
Attachments:
Work Order
EXHIBIT B
3
4
5
6(S)
7
8(S)
9
10
11(S)
12(S)
13(S)
14(S)
15(S)
16(S)
17(S)
18(S)
19(S)
20(S)
21(S)
22(S)
23(S)
24(S)
25(S)
26(S)
27(S)
28(S)
Mobilization/Demobilization
SWPPP Implementation
Traffic Control
Remove and Replace Sidewalk Repairs
Protection and Restoration of Private
Shoring and Bracing
Protection Post Installation per SDARSD
Construction Staking
Replace Traffic Signal Loop
Replace Signing, Striping and Pavement
Mainline Joint Trench
Private Property Service Trench
Furnish and Install Electric Conduit, 5"
Furnish and Install Electric Conduit, 4"
Furnish and Install Electric Conduit, 3
Furnish and Install Electric Conduit, 2"
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish and Install Electric Transformer
Furnish And Install Electric 3316 HH with
Fumish and Install Electric Handhole
Furnish And Install Electric 3316 HH with
Furnish And Install Electric Transformer
Adjust Handhole to Finished Grade
Concrete Encasement
LS
SF
LS
LS
EA
LS
EA
LS
LF
LF
LF
LF
LF
LF
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
LF
1
1000
1
20
1
50
1
6,250
930
1,280
8,550
5,420
130
6
5
2
3
14
19
6
6,950
Basile Construction SDG&E
1RK' 'OR
,6'1I 00
$5,344.65
$12,759.75
$12.31
$16.756.20
$4,815.00
$353.10
$8,881.00
$251.45
$9,737.00
$79.18
$28.89
$4.92
$4.01
$2.73
$1.82
$251.45
$1,578.25
$1,535.45
$6,896.15
$9,399.95
$2,819.45
$11,984.00
S770.40
$ 12,385.25
$572.45
S802.50
$9.10
Total
$5,344.65
$12,759.75
$12,310.00
$16,756.20
$4.815.00
$7.062.00
$8,881.00
$12,572.50
$9,737.00
$494,875.00
S26,867.70
$6,297.60
$34,285.50
$14,796.60
$236.60
$1.508.70
$7,891.25
$3,070.90
$6,896.15
$9,399.95
$2.819.45
$35.952.00
$10.785.60
$12,385.25
$10.876.55
$4.815.00
$63.245.00
$747,004.80
85%
85%
85%
85%
85%
85%
85%
85°io
85%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
4,820.35
$ 10,845.79
10,463.50
$ 14,242.77
$ 4,092.75
$ 6,002.70
$ 7,548.85
$ 10,686.63
$ 8,276.45
$ 420,643.75
$ 26,867.70
$ 6,297.60
$ 34,285.50
$ 14,796.60
$ 236.60
$ 1,508.70
$ 7,891.25
$ 3,070.90
$ 6,896.15
$ 9,399.95
$ 2,819.45
$ 35.952.00
$ 10.785.60
$ 12,385.25
$ 967.28
$ 2,176.38
2,099.67
$ 2,858.04
$
821.28
1,204.54
1,514.80
$ 2,144.44
1.660.80
$ 5,391.43
$ 1,263.71
$ 6,879.93
$ 2,969.17
$ 47.48
$ 302.74
$ 1.583.51
$ 616.23
$ 1.383.82
$ 1,886.25
$ 565.77
$ 7,214.34
$ 2,164.30
$ 2.485.30
$ 10,876.55 $ 2,182.55
$ 4,815.00 $ 966.21
$ 63,245.00 $ 12,691.12
$ 672,773.55 $ 135,002.78
5,787.63
13,022.17
$ 12,563.17
$ 17,100.81
$ 4,914.03
$ 7,207.24
9,063.65
$ 12,831.07
9,937.25
$ 32,259.13
7,561.31
$ 41,165.43
$ 17,765.77
$ 284.08
$ 1,811.44
$ 9,474.76
$ 3,687.13
$ 8,279.97
$ 11,286.20
$ 3,385.22
$ 43,166.34
$ 12,949.90
$ 14,870.55
$ 13,059.10
$ 5,781.21
$ 75,936.12
$ 807,776.33
ESTIMATED TOTALS $ 749,753.33 $ 150,450.00
$ 900203,33
EXHIBIT B
1
2
3
4
5
6S
7
8 S)
9
10
Mobilization/Demobilization
SWPPP Im.lementation
Traffic Control
Remove and Re .lace Sidewalk Re .airs
Protection and Restoration of Private
Shorin_ and Bracin:
Protection Post Installation .er SDARSD
Construction Stakin•
Re.lace Traffic Sit. al Loo.
Re.lace Si: in:, Stri.in: and Pavement
11(S)
12(S)
13(S)
14(S)
15(S)
16(S)
17(S)
18(S)
19(S)
20(S)
21(S)
22(S)
23(S)
24(S)
25(S)
26(S)
LS
LS
LS
SF
LS
1
1
LS
Mainline Joint Trench
Private Pro.e Service Trench
Furnish and Install Electric Conduit, 5"
Furnish and Install Electric Conduit, 4"
Furnish and Install Electric Conduit, 3"
Furnish and Install Electric Conduit, 2"
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish And Install Electric Handhole
Furnish and Install Electric Transformer
Furnish And Install Electric 3316 HI -I with
Furnish and Install Electric Handhole
Furnish And Install Electric 3316 HH with
Furnish And Install Electric Transformer
Ad'ust Handhole to Finished Grade
Concrete Encasement
EA
LS
EA
LS
LF
LF
LF
LF
LF
LF
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
LF
1
1000
1
1
20
1
50
1
Basile Construction
tariniN11.01111111ZNAWIN
�'IiY.>Ti��h�tJ[Ix1I11♦
SDG&E
muntimm4.:15.11 :5'0
111111111MAIMIIIIIMMEIMIIIIIMM
mimiggingaimarammiging
111111M2VIIMIIMMIMMIIIMEM
5'0
6,250
930
1,280
8,550
5,420
130
6
5
2
1
1
3
14
1
19
6
6,950
$79.18
$28.89
$4.92
$4.01
$2.73
$1.82
$251.45
$1,578.25
$1,535.45
$6,896.15
$9,399.95
$2,819.45
$11,984.00
$770.40
$12,385.25
$572.45
$802.50
Total
IY]7t_Iw 11
$494,875.00
$26.867.70
$6,297.60
$34,285.50
$14,796.60
$236.60
$1,508.70
$7,891.25
$3,070.90
$6,896.15
$9,399.95
$2.819.45
$35,952.00
$10,785.60
$12.385.25
$10,876.55
$4,815.00
$747,004.80
85%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
0
$ 4,820.35
$
$ 10,845.79
$ 10,463.50
$ 14,242.77
$ 4,092.75
$ 6,002.70
$ 7,548.85
$ 10,686.63
$ 8,276.45
$ 76,979.78
$ 420,643.75
$ 26,867.70
$ 6,297.60
$ 34,285.50
$ 14,796.60
$ 236.60
$ 1,508.70
$ 7,891.25
$ 3,070.90
$ 6,896.15
$ 9,399.95
$ 2,819.45
$ 35,952.00
$ 10,785.60
$ 12,385.25
$ 10,876.55
$ 4,815.00
$ 63,245.00
$ 672,773.55
$ 967.28
$ 2,176.38
$ 2,099.67
$ 2,858.04
$ 821.28
$ 1,204.54
$ 1,514.80
$ 2,144.44
$ 1,660.80
$ 15,447.22
$ 84,408.90
$ 5,391.43
$ 1,263.71
$ • 6,879.93
$ 2,969.17
47.48
$ 302.74
$ 1,583.51
$ 616.23
$ 1,383.82
$ 1,886.25
$ 565.77
$ 7,214.34
$ 2,164.30
$ 2,485.30
$ 2,182.55
$ 966.21
$ 12,691.12
$ 135,002.78
5,787.63
$ 13,022.17
$ 12,563.17
$ 17,100.81
4,914.03
7,207.24
9,063.65
$ 12,831.07
9,937.25
$ 92,427.01
$ 505,052.65
$ 32,259.13
7,561.31
$ 41,165.43
$ 17,765.77
284.08
1,811.44
9,474.76
3,687.13
8,279.97
$ 11,286.20
3,385.22
$ 43,166.34
$ 12,949.90
$ 14,870.55
$ 13,059.10
5,781.21
$ 75,936.12
$ 807,776.33
ESTIMATED TOTALS
$ 749,753.33
$ 150,450.00
$ 900,203.33.
RESOLUTION NO. 2012 — 122
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE A JOINT TRENCH OFFER AGREEMENT
WITH SAN DIEGO GAS AND ELECTRIC COMPANY ("SDG&E") WHEREIN
SDG&E PAYS THE CITY UP TO THE NOT TO EXCEED AMOUNT OF $1,670,915 FOR
ACTUAL COSTS INCURRED BY THE CITY FOR THE UNDERGROUND CONVERSION
OF UTILITIES IN CONJUNCTION WITH UNDERGROUND DISTRICT NO. 24
WHEREAS, on December 20, 2005, City Council adopted Resolution No. 2005-
256 to establish Underground Utility District No. 24 on 8th Street from National City Boulevard to
Highland Avenue for the purposes of replacing overhead wires, structures, and poles with an
underground system for electric and communications services to benefit public safety, health,
and welfare; and
WHEREAS California Public Utility Commission (CPUC) Rule 20A allows for an
allocation of utility funds to municipalities for the purpose of undergrounding conversions; and
WHEREAS, SDG&E is authorized by the CPUC to convert overhead facilities to
underground in accordance with Rule 20A. Rule 20A also allows municipalities to bid portions
of the work, such as trenching, conduit, backfill, substructures, and pavement repair in an effort
to better control costs and schedule; and
WHEREAS, the City Council approved staff's recommendation to bid the project,
which included revising SDG&E's schematic design to provide detailed engineering plans and
construction documents, in an effort to generate more competitive bidding and reduce the
amount of change orders during construction; and
WHEREAS, on March 20, 2012 Council awarded the contract to Basile
Construction Inc., in the not to exceed amount of $2,386,365.49, and authorized a 25%
contingency; and
WHEREAS, the cost of the dry utility work is $1,058,640.52, and the cost of the
sewer work is $1,327,724.97. The dry utility costs for the SDG&E portion of the work will be
reimbursed with the 20A conversion funds; and
WHEREAS, SDG&E submitted a Joint Trench Offer (JTO) with the not to exceed
amount of $1,670,915 wherein SDG&E will reimburse the City on a monthly basis as progress
payments are made to the City's contractor for SDG&E work, including any approved changes.
Such payments to be no Tess than quarterly, nor more frequent than monthly.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City hereby authorizes the Mayor to execute a Joint Trench Offer Agreement with
SDG&E for the underground conversion of utilities in conjunction with Underground District No.
24, wherein SDG&E will reimburse the City on a monthly basis as progress payments are made
to the City's contractor for SDG&E work, including any approved changes or any mutually
agreed upon reimbursement payment schedule. Said Joint Offer Agreement is on file in the
Office of the City Clerk.
--- Signature Page to Follow ---
Resolution No. 2012 — 122
Page Two
PASSED and ADOPTED this 19th day of June,
orrison, Mayor
ATTEST:
/i
Michael R. Dalla, City Clerk
AROVED AS TO F M:
Claudia Ga
City Attor
Passed and adopted by the Council of the City of National City, California, on June 19,
2012 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Natividad, Rios, Sotelo-Solis, Zarate.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
/W
erk of the City f
National J
City City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2012-122 the City of National City, California, passed and adopted
by the Council of said City on June 19, 2012.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
�1
Ac: --o
MEETING DATE: June 19, 2012
AGENDA ITEM NO. 7
. PEM TITLE:
Resolution of the City Council of National City approving a Joint Trench Offer Agreement with SDG&E
wherein SDG&E shall reimburse the City up to the not -to -exceed amount of $1,670,915 for actual costs
incurred by the City and authorizing the mayor to execute agreement in conjunction with District 24 (8th
Street) aerial to underground conversion of utilities
PREPARED BY: Barby Tipton
PHONE: 336-4583
EXPLANATION:
See attached
DEPARTMENT: Development Services -Engineering
Division
APPROVED BY:
FINANCIAL STATEMENT: APPROVED:
ACCOUNT NO. APPROVED:
Funds to be deposited into account 001-409-500-598-3918
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
2
Finance
MIS
STAFF RECOMMENDATION:
Adopt the Resolution.
BOARD 1 COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Joint Trench Offer Agreement
3. Resolution
On December 20, 2005, City Council adopted Resolution No. 2005-256 to establish
Underground Utility District No. 24 on 8th Street from National City Boulevard to
Highland Avenue for the purposes of replacing overhead wires, structures and poles
with an underground system for electric and communications services to benefit public
safety, health and welfare. California Public Utility Commission (CPUC) Rule 20A allows
for an allocation of utility funds to municipalities for the purpose of undergrounding
conversions. In 2011 the City's allocation was $517,959. The City's allocation balance
as of May 2012 was $3,019,844.
SDG&E is authorized by the CPUC to convert overhead facilities to underground in
accordance with Rule 20A. However, Rule 20A also allows municipalities to bid portions
of the work, such as trenching, conduit, backfill, substructures, pavement repair, etc. in
an effort to better control costs and schedule.
Council supported staff's recommendation to bid the project, which included revising
SDG&E's schematic design to provide detailed engineering plans and construction
documents, in an effort to generate more competitive bidding and reduce the amount
of change orders during construction. The 20A conversion of 8th Street between
National City Boulevard and Highland Avenue was also combined with the sewer
replacement along 8th Street in an effort to solicit more competitive bids.
On March 20, 2012 Council awarded the contract to Basile Construction Inc. in the not
to exceed amount of $2,386,365.49 and authorize a 25% contingency.
The cost of the dry utility work is $1,058,640.52 and the cost of the sewer work is
$1,327,724.97. The dry utility costs for the SDG&E portion of the work will be
reimbursed with the 20A conversion funds. AT&T, Cox Cable and Access Cable
Corporation shall pay their cost to the City per conditions of the Joint Trench
Agreements.
SDG&E submitted the Joint Trench Offer (JTO) with the not to exceed amount of
$1,670,915. The City shall collect reimbursement from SDG&E on a monthly basis as
progress payments are made to the City's contractor for SDG&E work including any
approved changes or any mutually agreed upon reimbursement payment schedule.
Any changes to this limit shall be pre -approved by SDG&E and SDG&E shall then pay for
actual services rendered should the amount exceed the offer. Such payments to be not
less than quarterly nor more frequent than monthly.
Staff recommends that Council approve the JTO agreement.
RESOLUTION NO. 2012 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE A JOINT TRENCH OFFER AGREEMENT
WITH SAN DIEGO GAS AND ELECTRIC COMPANY ("SDG&E") WHEREIN
SDG&E PAYS THE CITY UP TO THE NOT TO EXCEED AMOUNT OF $1,670,915 FOR
ACTUAL COSTS INCURRED BY THE CITY FOR THE UNDERGROUND CONVERSION
OF UTILITIES IN CONJUNCTION WITH UNDERGROUND DISTRICT NO. 24
WHEREAS, on December 20, 2005, City Council adopted Resolution No. 2005-
256 to establish Underground Utility District No. 24 on 8th Street from National City Boulevard to
Highland Avenue for the purposes of replacing overhead wires, structures, and poles with an
underground system for electric and communications services to benefit public safety, health,
and welfare; and
WHEREAS California Public Utility Commission (CPUC) Rule 20A allows for an
allocation of utility funds to municipalities for the purpose of undergrounding conversions; and
WHEREAS, SDG&E is authorized by the CPUC to convert overhead facilities to
underground in accordance with Rule 20A. Rule 20A also allows municipalities to bid portions
of the work, such as trenching, conduit, backfill, substructures, and pavement repair in an effort
to better control costs and schedule; and
WHEREAS, the City Council approved staffs recommendation to bid the project,
which included revising SDG&E's schematic design to provide detailed engineering plans and
construction documents, in an effort to generate more competitive bidding and reduce the
amount of change orders during construction; and
WHEREAS, on March 20, 2012 Council awarded the contract to Basile
Construction Inc., in the not to exceed amount of $2,386,365.49, and authorized a 25%
contingency; and
WHEREAS, the cost of the dry utility work is $1,058,640.52, and the cost of the
sewer work is $1,327,724.97. The dry utility costs for the SDG&E portion of the work will be
reimbursed with the 20A conversion funds; and
WHEREAS, SDG&E submitted a Joint Trench Offer (JTO) with the not to exceed
amount of $1,670,915 wherein SDG&E will reimburse the City on a monthly basis as progress
payments are made to the City's contractor for SDG&E work, including any approved changes.
Such payments to be no less than quarterly, nor more frequent than monthly.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City hereby authorizes the Mayor to execute a Joint Trench Offer Agreement with
SDG&E for the underground conversion of utilities in conjunction with Underground District No.
24, wherein SDG&E will reimburse the City on a monthly basis as progress payments are made
to the City's contractor for SDG&E work, including any approved changes or any mutually
agreed upon reimbursement payment schedule. Said Joint Offer Agreement is on file in the
Office of the City Clerk.
--- Signature Page to Follow ---
Resolution No. 2012 —
Page Two
PASSED and ADOPTED this 19th day of June, 2012.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Claudia Gacitua Silva
City Attorney
{
AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
SAN DIEGO GAS & ELECTRIC COMPANY (SDG&E)
THIS AGREEMENT is entered into this 19th day of June, 2012, by and between the CITY
OF NATIONAL CITY, a municipal corporation (the "CITY"), and San Diego Gas & Electric
Comany (SDG&E).
RECITALS
WHEREAS, SDG&E desires to enter into a Joint Trench Agreement for installation
of electric distribution and service facilities in the trenches of Underground District No. 24 (20A
Conversion 8th Street) SDG&E project No. 532152-070, and
WHEREAS, SDG&E has submitted a Joint Trench Letter in the not -to -exceed
amount of $1,670,915 (attached Exhibit A),
NOW, THEREFORE, THE PARTIES HERETO DO MUTUALLY AGREE AS
FOLLOWS:
1. The CITY to provide trenching, backfill, substructures (concrete products, conduit,
retaining walls), pavement repair, any adjustments to final grade, required permits, and
environmental release.
2. Trench, backfill, installation of conduit system with pull string shall be accomplished to
SDG&E General Conditions and governing agency specifications.
3. SDG&E shall reimburse the City in an amount up to $1,670,915 for the joint trench costs
including SDG&E's share of cost for (1) construction, (2) general work for dry utilities, and
(3) inspections and project management. Exhibit B describes the work that is included in
shared costs. SDG&E's share of costs shall be determined by the total costs attributable
to the dry utilities divided among participating dry utilities as shown in Exhibit B
4. All increases to costs must be agreed upon by both parties, in writing, prior to the City
approving any change orders. Such approval shall not be unreasonably withheld.
5. San Diego Gas & Electric will provide and install all SDG&E materials for cabling of said
project. Delivery of SDG&E materials shall not be unreasonably delayed.
6. SDG&E will provide on -site inspection for SDG&E conduit system and substructures.
7. The CITY shall provide the as -built drawings to SDG&E.
8. The City shall provide proper documentation to SDG&E in order to collect reimbursement
from SDG&E on a regular basis as progress payments are made to the City's contractor
for SDG&E work including any approved changes. Such payments to be no Tess than
quarterly, nor more frequent than monthly.
9. SDG&E agrees to indemnify, defend, and hold harmless, the City of National City and its
officers and employees against and from any and all liability, loss, damage to property,
injuries to, or death of any person or persons, and all claims, demands, suits, actions,
proceedings, reasonable attorney's fees, and defense costs, of any kind or nature,
including worker's compensation claims of or by anyone whomsoever, resulting from or
arising out of SDG&E's negligent performance under this agreement.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the
date and year first above written.
CITY OF NATIONAL CITY
By:
Ron Morrison, Mayor
APPROVED AS TO FORM:
Claudia G. Silva
City Attorney
San Diego Gas & Electric Company
(Corporation — signatures of two corporate officers)
(Partnership — one signature)
(Sole proprietorship — one signature)
By:
By:
(Rick Gardner)
vat- Go-cAN0 r
(Print)
�co�� fALkoM
(Projec management gr.)
Alan Marcher)
(Print)
( anageY Project Management)
2
2
City's Standard Agreement — June 2008 revision
spG1
A Sempra Energy utility°
February 16, 2012
Steve Manganiello C.E.
City Engineer
1243 National City Blvd.
National City, Ca. 91950
San Meg° Gas & Electric
8315 Century Park Court
San Diego, CA 92123-1548
FILE NO. PIA
PROJ# 532152-070
Dear Steve:
Subject: 8th Street 20A Conversion — UUD # 24, N.C. BI. To Highland Av.
SDG&E has completed the preliminary engineering review required to replace the existing
overhead electric facilities with an underground system at the above location.
A final design and cost estimate for your conversion has been prepared based on the option
that the city will bid for the following work:
• Contractor to provide trenching, backfill, substructures (concrete products, conduit,
retaining walls), pavement repair, any adjustments to final grade, required permits, and
environmental release. SDG&E General Conditions and underground standards are to
be incorporated into the bid document. In the event of inconsistencies between the
Municipal bid documents (municipal General Conditions) and SDG&E's General
Conditions, the most stringent shall prevail and will be subject to mutually agreed upon
and negotiated benefits. SDG&E underground standards can be accessed at
http://sdge.com/documents/underground-construction-standards
• San Diego Gas & Electric to furnish and install cable, pad -mounted equipment,
connections and removal of overhead facilities.
Pr io; to awarding the contract, the city will submit a copy of the first, second and third
acceptable bids to SDG&E for review and approval. If approved, SDG&E will reimburse the city
for this work (based on the contractor's bid) up to our estimated value of $1,670,915. At the
completion of the contractors' portion of their work, SDG&E's overhead costs applicable to this
work, including any re -engineering fees, if applicable, will be deducted from the municipality's
20A allocation.
In the case that all bids exceed the maximum reimbursable amount, SDG&E reserves the right
to reject all municipal bids and may elect to do the electric conversion trench independently. In
order to allow the City's bidding contractors to properly separate the cost of installing SDG&E's
conduit infrastructure from that of the telecommunications companies, I would like to meet with
the City and the bidding contractors prior to bid submittal. This will help ensure consistency
among the bids for the conversion trench & conduit installation phase of the project.
Pleasenote the above costs do not include the installation of any ornamental street lights or
street light services that might be required by the City of National City. Street lighting is not
reimbursable under Rule 20. However, the City can make use of the available conversion trench
and conduit for street light conduit installation.
3
A
2 February 16, 2012
The City of National City will be responsible for acquiring Joint Trench Offers. AT&T, Cox
Communications Inc., and Media 3 have planned on participating in the Joint Trench, which
minimizes costs to the joint trench utilities, lessens the amount of trench and surface repair, and
reduces the overall cost of trenching. The offers received by SDG&E are no longer valid. Once
the City acquires the offers, SDG&E can provide a courtesy review for reasonableness, at the
City's request.
Bids shall include separate line items for installation of SDG&E and the other dry utilities. Bids
are to include service conduit, but not service panel conversion work, which will be facilitated by
SDG&E.
A Pre -Construction Conference shall be held in advance of construction to coordinate with all
dry utilities participating in Joint Trench. SDG&E will be represented in the field by a Trench
Inspector. Change orders will be reviewed and approved by SDG&E's Project Manager, prior to
the work taking place.
Invoices shall be submitted to SDG&E's Project Manager. Billing can occur at completion, or on
a regular basis, not to exceed once a month, and shall include necessary invoices and support
information, satisfactory to SDG&E, to justify reimbursement. Reimbursement will occur
accordingly, after review and approval by SDG&E's Trench Inspector.
All costs and offers quoted in this letter shall become void at the end of the business day on
May 14, 2012. If business negotiations are not completed, or if you request revised costs after
that date, a cost update fee may be required. Your costs, as cited herein, are subject to change
at any time. All cost calculations are based upon SDG&E's filed tariffs, SDG&E's internal costs,
and all applicable governmental or regulatory statutes, regulations, codes and rules. Should any
change in, or addition to, those tariffs, costs, statutes, regulations, codes or rules in any way
impact these cost calculations, you will be subject to any resulting increase or decrease.
If I may be of further assistance or if you have any questions, please call me at the number
listed below. Our hours are 7:00 am — 4:00 pm, Monday through Friday. For additional general
information, please visit our website at http://sdge.com/index.html.
Sincerely,
Governmental Liaison Planner SDG&E
Telephone: (858) 654-1136
Attachments:
Work Order
4
EXHIBIT B
. •.
Basile Construction
SDG&E
7&5 4 A
G a
nv dP; i"#�SwtF
p
•
( ,._ x` iaa fi k .tea Y {
iF S"' fi `}
1H�'��', �fi .
�,
'Rapv3
+M
•.�,�;
y
s ,
,�"
!
1.�+bSv�a
i,', tiit
i$i
'?M1iY5Ra
M
" ��
s`5•
m
'9
a
,�„..�.
¢�
�r .�
r�x
x
ItrYf'4' N i.
�r;.. �, �.
S..&
,'Y fix". s'*u$ eku in
�,. s p•6U a
b
. .. i..
,. , x roa a
p . ,*x
t' V
#}t H ay EN
.... r,,.:' ,
9 f L yil;(i d
Y{ZItIL E
1
Mobilization/Demobilization
LS
1
. ,• •II
'. . .1
o
$ 4,820.35
$ 967.28
$ 5787.63
2
SWPPP Implementation
LS
1
S5,344.65
$5,344.65
0%
$ -
$
3
Traffic Control
LS
1
$12,759.75
$12,759.75
85%
$ 10,845.79
$ 2.176.38
$ 13;022.17
4
Remove and Replace Sidewalk Repairs
SF
1000
$12.31
$12,310.00
85%
$ 10,463.50
$ 2,099.67
$ 12,563.17
5
Protection and Restoration of Private
LS
1
$16.756.20
$16,756.20
85%
$ 14,242.77
$ 2,858.04
$ 17,100.81
6(S)
Shoring and Bracing
LS
1
$4,815.00
S4.815.00
85%
$ 4,092,75
$ 821.28
$ 4,914.03
7
Protection Post Installation per SDARSD
EA
20
$353.10
$7,062.00
85%
$ 6,002.70
$ 1,204.54
$ 7,207.24
8(S)
Construction Staking
L.S
1
$8,881.00
$8,881.00
85%
$ 0,686.63
$
$ 2,831.07
9
Replace Traffic Signal Loop
EA
50
$251.45
$12,572 50
85 /o
$ 10 ,686.63
,144.44
2
$ ,144.44
$ 12,831.07
10
Replace Signing, Striping and Pavement
LS
1
$9,737.00
$9.737.00
85%
$ 8,276.45
$ 1.660.80
$ 9,937.25
l otal
$95,909.10
76,979.78
$ 15,447.22
S 92,427.01
sa. [y
i&',tt i a. J q`k't4!?^"r. 4 "t4s, F tyG i`x�
.. ... ,�»✓,.a,,. h„-, ,.., 6A..�.�.,�i.,'5+*�',��'.�''
� �i' �i+tAyQ'
p 1 ,+'.,t
.. ;...:.
11(S)
Mainline Joint Trench
LF
6,250
..j u
S79.18
.%%��t+��i�%`�^f�a,.'.
$494,875.00
85%
$ 420,643.75
$ 84,408.90
$ 505,052.65
12(S)
Private Property Service Trench
LF
930
$28.89
$26,867.70
100%
$ 26,867.70
$ 5.391.43
$ 32,259.13
13(S)
Furnish and Install Electric Conduit, 5"
LF
1,280
$4.92
$6.297.60
100%
$ 6,297.60
$ 1,263.71
$ 7,561.31
14(S)
Furnish and Install Electric Conduit, 4"
LF
8,550
$4.01
$34,285.50
100%
$ 34,285.50
$ 6,879.93
$ 41,165.43
15(S)
Furnish and Install Electric Conduit, 3"'
LF
5,420
$2.73
$14,796.60
100%
$ 14,796.60
$ 2,969.17
$ 17;765.77
16(S r
Furnish and Install Electric Conduit, 2"
LF
130
$1.82
$236.60
100%
$ 236.60
$ 47.48
$ 284.08
17(S)
Furnish And Install Electric Handhole
EA
6
S251.45
$1,508.70
100%
$ 1,508.70
S 302.74
$ 1,811.44
18(Sl
Furnish And Install Electric Handhole
EA
5
$1,578.25
$7.891.25
100%
$ 7,891.25
$ 1,583.51
$ 9,474.76
19(S)
Furnish And Install Electric Handhole
EA
2
$1,535.45
$3,070.90
100%
$ 3,070.90
$ 616.23
$ 3,687.13
20(S)
Furnish And Install Electric Handhole
EA
1
$6,896.15
$6,896.15
100%
$ 6,896.15
$ 1.383.82
$ 8,279.97
21(S)
Furnish And Install Electric Handhole
EA
1
$9,399.95
$9.399.95
100%
$ 9,399.95
$ 1.886.25
$ 11,286.20
22(S)
Furnish and Install Electric Transformer
EA
1
$2,819.45
$2,819.45
100%
$ 2,819.45
$ 565.77
$ 3,385.22
23(S)
Furnish And Install Electric 3316 HH with
EA
3
$11,984.00
$35.952.00
100%
$ 35,952.00
$ 7,214.34
$ 43,166.34
24(S)
Fumish and Install Electric Handhole
EA
14
$770.40
$10,785.60
100%
$ 10,785.60
$ 2,164.30
$ 12,949.90
25(S)
Furnish And Install Electric 3316 HH with
EA
1
$12.385.25
$12.385.25
100%
$ 12,385.25
$ 2,485.30
$ 14,870.55
26(S)
Furnish And Install Electric Transformer
19
$572.45
$10,876.55
100%
,
'
$ 13,059.10
27(S)
Adjust Handhole to Finished Grade
6
$802.50
$4.815.00
100%
•.
$ 5,781,21
28(S)
Concrete Encasement
6,950
$9.10
$63.245.00
100%
1
5 75,936.12
Total
$747,004.80
$ 672,773.55
$ 135,002.78
$ 807,776.33
ESTIMATED TOTALS 1 $ 749,753.33 $ 150,450.00 $
900 203.33 '
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
June 25, 2012
Mr. David Emerson
San Diego Gas and Electric
8315 Century Park Court
San Diego, CA 92123
Dear Mr. Emerson,
On June 19th, 2012, Resolution No. 2012-122 was passed and adopted by the City
Council of the City of National City, authorizing execution of a Joint Trench Offer
Agreement with San Diego Gas and Electric (SDG&E).
We are enclosing for your records a certified copy of the above Resolution and a fully
executed original Agreement.