8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT
Specification No. 11-04
Contractor: Basile Construction, Inc.
CHANGE ORDER NO. 4
August 1, 2012
: Reason/Purpose for this Change Order:
!During the trenching for the underground wet utilities on 8th Street and Highland Avenue, the Contractor
`encountered additional unmarked abandoned utility conduits that were not shown as existing on the original
plans. Due to the location of the conduits, the Contractor was unable to excavate using an Excavator, as
calculated in its bid price, and was required to excavate this location by hand resulting in additional labor costs.
The City of National City and Contractor agree to the following change to the original Contract:
'The City shall pay the Contractor for the additional labor outlined above in the amount recorded and confirmed by
the field Inspector. The worker classifications and hours worked for the additional labor are specified on
:Attachment "A", which is attached hereto and incorporated herein. The Contractor and City agree that all costs
for the additional labor is included in the price of this Change Order.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
2,386,365.49
(38,734.94)
2,347,630.55
398.07
New contract amount $
Working days added: 0
Submitted bvi
Projec
Approved by:
anager
City.Engineer / Date
Percent change in Contract to date -1.61 %
2,348,028.62
Date
City Manager, required for Change Orders>$24999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represes all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, i r. ce, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are inc oor-ted herein.
Ac.-ptes ar�� agreed to by Basile Construction, Inc.:
ame: ' Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
Telephone (619) 336-4380
CALIFORNIA ,--,
TIoN L +14.r
13,11 <_=
tNCORYOskTD
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 4, Attachment "A"
Specification #11-04
Itemized Breakdwon Qty Unit Unit Cost Item Cost
1) Pipe Layer
2) Pipe Layer
3) Laborer
23.85% Labor Burden
20% Prime Contractor mark-up
23.85% Labor Burden
20% Prime Contractor mark-up
23.85% Labor Burden
20°/o Prime Contractor mark-up
2 EA 44.92 89.84
21.43
22.25
2 EA 44.92 89.84
21.43
22.25
2 EA 44.08 88.16
21.03
21.84
TOTAL AMOUNT OF CHANGE ORDER:
398.07
r
• y
CALIFORNIA.^
coCfr
ram= '.wJ / .-�-
INCOR3+ORA"f$D ...
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT
Specification No. 11-04
Contractor: Basile Construction, Inc.
;Reason/Purpose for this Change Order:
`On June 1, 2012, while trenching for underground wet utilities on 8th Street, the Contractor encountered an
)angled sewer lateral that did not comply with City's sewer lateral installation standard requiring laterals to be
installed in a perpendicular manner from the sewer main to the property connection point. To comply with the
City's sewer lateral installation standard, the Contractor was required to relocate the angled lateral to a different
:location than that which resulted in additional costs for labor, materials, and equipment.
CHANGE ORDER NO. 5
August 3, 2012
The City of National City and Contractor agree to the following change to the original Contract:
'The City shall pay the Contractor for the additional labor, equipment, and materials in the amount recorded and
:confirmed by the field Inspector. The worker classifications and hours worked for the additional labor are
'specified on Attachment "A", which is attached hereto and incorporated herein. The Contractor and City agree
that all costs for the additional labor, equipment, and materials is included in the price of this Change Order.
Original Contract Amount $ 2,386,365.49
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
(38,336.87)
2,348,028.62
707.76
New contract amount $
Working days added: 0
Sub
Project
;Approved by:
Working days subtracted: 0
Percent change in Contract to date -1.58%
cr/1/z
Engineer � Date ICity Manag Br, required for change orders>$2a999 Date
2,348,736.38
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, ins u . nc= profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incor..rated erein.
dtoby by Construction, Inc
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
1`•-..CALIFORNIA
.--
NATIONAL OTT
TNCARP6AATED
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 5, Attachment "A"
Specification #11-04
DATE: June 1, 2012
WORK PERFORMED BY: Basile Construction, Inc.
DESCRIPTION OF WORK: Lateral @ 10+35, next to power pole
DAILY ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
Hour
2.00
42.47
84.94
2)
Laborer
Hour
2.00
44.08
88.16
3)
Operator
Hour
2.00
60.08
120,16
Sub -Total Labor:
$ 293.26
Labor Burden (23.85%):
$ 69.94
Labor Markup (20%):
$ 72.64
TOTAL LABOR:
$ 435.84
MATERIALS
Unit
Qty
Rate
Total
1)
Steel Plates
Day
3.00
4.13
12.39
2)
Shoring
Day
2.00
2.57
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
5.14
$ 17.53
$ 2.63
$ 20.16
EQUIPMENT
Unit
Qty
Rate
Total
1)
Komatsu Ex 228
Hour
2.00
109.46
218.92
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
218.92
$ 32.84
$ 251.76
Total Labor: $ 435.84
Total Materials: S 20.16
Total Equipment: $ 251.76
TOTAL: $ 707.76
CALIFORNIA
NATION. ei
INCORPORATED —�
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 6
Specification No. 11-04 August 3, 2012
Contractor: Basile Construction, Inc.
Reason/Purpose
for this Change Order:
On June 25th, July 2nd, and July 3rd, while installing sewer laterals on 8th Street, the Contractor encountered
angled sewer laterals that did not comply with City's sewer lateral installation standard requiring laterals to be
installed in a perpendicular manner from the sewer main to the property connection point. To comply with the
City's sewer lateral installation standard, the Contractor was required to pothole at multiple locations to determine,',
the location where each lateral crossed the private property line.
The City of National City and Contractor agree to the following change to the original Contract:
'The City shall pay the Contractor for the additional labor, equipment, and materials in the amount recorded and
confirmed by the field Inspector. The worker classifications and hours worked for the additional labor are
specified on Attachment "A", which is attached hereto and incorporated herein. The Contractor and City agree
that all costs for the additional labor, equipment, and materials is included in the price of this Change Order.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
2,386,365.49
(37,629.11)
2,348,736.38
1,618.49
New contract amount $
Working days added: 0
Subm tte b :
Approved by:
Working days subtracted: 0
Percent change in Contract to date -1.51 %
2,350,354.87
Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, p •fit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorpora
Accepter and agr �d lofiy..Basile Construction Inc.:
Name: Date
Note to Contractor: If you do not agree with this ChangeOrder you may be directed with
to proceed this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
Telephone (619) 336-4380
CALIFORNIA
N T N L Cflp
`-- INCORYOAATi':O
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 8, Attachment "A"
Specification #11-04
DATE: June 25, July 2, and July 3
WORK PERFORMED BY: Basile Construction, Inc.
DESCRIPTION OF WORK: Pothole Unknown laterals
DAILY ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
Hour
5.50
44.08
242.44
2)
Operator
Hour
2.00
60.08
120.16
3)
Laborer
Hour
2.00
44.08
88.16
4)
Pipelayer (2)
Hour
5.00
44.92
224.60
5)
Laborer
Hour
4.00
44.08
176.32
6)
Saw Cutter
Hour
1.00
44.92
44.92
Sub -Total Labor:
Labor Burden (23.85%):
Labor Markup (20%):
TOTAL LABOR:
5 896.60
$ 213.84
$ 222.09
$ 1,332.53
MATERIALS
Unit
Qty
Rate
Total
1)
90 LB Readymix
EA
10.00
4.88
48.80
2)
Sub -Total Materials:
Materials Markup (150/0):
TOTAL MATERIALS:
48.80
$ 7.32
$ 56.12
EQUIPMENT
Unit
Qty
Rate
Total
1)
Compressor 185 Cubic Ft/Min
Hour
3.50
20.01
70.04
2)
Case Mini Excavator
Hour
2.00
49.56
99.12
3)
Equipment Truck (Saw Cutter)
Hour
1.00
30.70
30.70
Sub -Total Materials:
$ 199.86
Materials Markup (15%):
$ 29.98
TOTAL MATERIALS:
$ 229.84
Total Labor: $ 1,332.53
Total Materials: $ 56.12
Total Equipment: $ 229.84
TOTAL: $ 1,618.49
•
CALIFORNIA -
N ,TIOClint
1NCOR ORATED -.
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 7
Specification No. 11-04 August 3, 2012
Contractor: Basile Construction, Inc.
Reason/Purpose for this Change Order:
On June 28, 2012, while installing sewer on 8th Street, the Contractor encountered unmarked abandoned utility
!conduits that were not shown as existing on the original plans. Due to the location of the conduits, the Contractor
;was not permitted to excavate the location with and Excavaot per its bid and was required excavate this location
by hand and with a mini excavator resulting in additional labor and equipment costs.
The City of National City and Contractor agree to the following change to the original Contract:
The City shall pay the Contractor for the additional labor, equipment, and materials in the amount recorded and
:confirmed by the field Inspector. The worker classifications and hours worked for the additional labor are
;specified on Attachment "A", which is attached hereto and incorporated herein. The Contractor and City agree
that all costs for the additional labor, equipment, and materials is included in the price of this Change Order.
Original Contract Amount $ 2,386,365.49
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Submii ted)y
Projeanage`r
Approved by:
CI Engineer
(36,010.62)
2,350,354.87
720.89
$ 2,351,075.76
Percent change in Contract to date -1.48%
Working days subtracted: 0
Date
Date City Manager, required for Change Orders >$24.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, in • a e, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are inc • oorah d herein.
Acgreed to by Basile Construction, Inc.:
5 1 Z--.
Name: Ddte
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
Telephone (619) 336-4380
CALIFORNIA.*��
NATIONAL Orr
LJ J /
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 7, Attachment "A"
Specification #11-04
DATE: June 28, 2012
WORK PERFORMED BY: Basile Construction, Inc.
DESCRIPTION OF WORK: Excavate by hand and mini excavator
DAILY ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
Hour
1.00
44.08
44.08
2)
Operator
Hour
2.00
60.08
120.16
3)
Pipelayer
Hour
2.00
44.92
89.84
4)
Laborer
Hour
3.50
44.08
154.28
Sub -Total Labor:
$ 408.36
Labor Burden (23.85%):
$ 97.39
Labor Markup (20a/0):
$ 101.15
TOTAL LABOR:
$ 606.90
MATERIALS
Unit
Qty
Rate
Total
1)
2)
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
EQUIPMENT
Unit
Qty
Rate
Total
1)
Case Mini Excavator
Hour
2.00
49.56
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
99.12
99.12
$
14.87
$ 113.99
Total Labor: $
Total Materials: $
Total Equipment: $
606.90
113.99
TOTAL: $ 720.89
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
INCORX' t A ' Michael R. Dalia, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
Basile Construction
Change Order #4, #5, #6 and #7
8th Street Utility Undergrounding
& Sewer Replacement
Judy Hernandez (Engineering) Forwarded
Copies of Change Orders to Basile Construction