HomeMy WebLinkAbout2012 CON Basile Construction - Change Order #19 and #20 - 8th St Utility Undergrounding4—, CALIFORNIA .a
NATIONAL CM
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT
Specification No. 11-04
Contractor: Basile Construction, Inc.
Reason/Purpose for this Change Order:
To adjust line item quantities to reflect actual AT&T quantities installed per the DBLs.
CHANGE ORDER NO. 19
November 15, 2012
The City of National City and the Contractor agree to the following change to the original Contract:
The quantities found on Attachment "A", attached hereto and incorporated herein, represent the final total
quantities installed for the Project for those respective line items.
Original Contract Amount $ 2,386,365.49
Net change by previously authorized Change Orders
7,638.36
2,394,003.85
Amount of this change order 81,897.96
New contract amount S 2,475,901.81
Working days added: 0
Subm' : • by:
Subtotal
Working days subtracted: 0 Percent change in Contract to date 3.75%
let 7/3(e Z
nitneer ---_.--------_.___-.— Date C Ma : r required for Chong.) order. >s24.9ee Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
Its price, terms and conditions. t this Change Order is approved. Contractor wit provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and ati .... associated with the work. including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, ice, etc. and that them will be no further compensation. All of the terms and conditions of the original contract documents
are . • :led . . Contractor Approval not required.
fp thy paella Construction
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 19, Attachment "A"
Specification #11-04
No.
Item
Unit Contract Quantity Actual Quan
Unit Price
Total Dollar Increase
29(S)
Trench for Telco Only
LF
775
1,825
62.06
65,163.00
30(S)
Furnish and Install Telephone 2" Conduit
IF
980
2,993
1.82
3,663.66
31(S)
Furnish and install Telephone 4" Conduit
LF
5,220
10,311
3.42
17,411.22
32(S)
Fur ishh and Install Telephone CMPH w/
Grond
EA
2
0
920.20
(1,840.40)
33(S)
Furnish and Install Telephone CPLM12
EA
4
0
624.88
(2,499.52)
34(S)
Furnish and Install Telephone Pullbox 2' x
3 x3
EA
5
5
1,888.55
35(S)
Furnish and Install Telephone Pullbox
3'x5'x4' (w/ drag off cover)
EA
1
1
3,086.95
TOTAL:
81,897.96
4— CALIFORNIA 4.4
NAT ON L
)
NCOH,pOR ATED
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 20
Specification No. 11-04
Contractor: Basile Construction, Inc.
Reason/Purpose for this Change Order:
To adjust line item quantities to reflect actual SDG&E quantities and joint mainline trench installed per the DBLs.
The City of National City, SDG&E, and Contractor agree to the following change to the original Contract:
The quantities found on Attachment "A", attached hereto and incorporated herein, represent the final total
quantities installed for the Project for those respective line items.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
Submitt- • by:
=nglneer
Date
2,386,365.49
89,536.32
2,475,901.81
136,281.27
Percent change in Contract to date 9.46%
2,612,183.08
�z-..L3-Pa_
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a co r • •le work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and repre -nts a costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, it uranc:, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are inc rporate herein. Contractor Approval not required.
Acc • pled a d ./! eed to by Basile Construction, Inc.:
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFQRNIA re.
NATIONAL C'irr
�.- INCORPORATED
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 20
Specification No. 11-04
Utility Company Acceptance Declarations
Accepted and agreed to bby_CoxCom, Inc. d/b/a Cox Communications:
Page 2 of 2
Name: Date
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Accepted and agreed to by SDG&E:
Name: Date
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Accepted and agreed to by AT&T.
Name Date
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Originals._ City Clerk Contractor Utilities cc Engineering project file Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 20, Attachment "A"
Specification #11-04
No.
Item
Unit Contract Quantity Actual Quantity
Unit Price
Delta
11(S)
Mainline Joint Trench
LF
6,250
7,759.00
79.18
119,482.62
12(S)
Private Property Service Trench
LF
930
787.00
28.89
(4,131.27)
13(5)
Furnish and Install Electric Conduit, 5"
LF
1,280
2,489.00
4.92
5,948.28
14(S)
Furnish and Install Electric Conduit, 4"
LF
8,550
9,709.00
4.01
4,647.59
15(S)
Furnish and Install Electric Conduit, 3"
LF
5,420
4,007.00
2.73
(3,857.49)
16(S)
Furnish and Install Electric Conduit, 2"
LF
130
117.00
1.82
(23.66)
17(S)
Furnish And Install Electric Handhole
Equipment Enclosure 3312 HH
EA
6
6.00
251.45
18(S)
Furnish And Install Electric Handhole
Equipment Enclosure 3313 HH with Traffic
Cover
EA
5
5.00
1,578.25
-
19(5)
Furnish And Install Electric Handhole
Equipment Enclosure 3313 HH with
Parkway Cover
EA
2
2.00
1,535.45
-
20(S)
Furnish And Install Electric Handhole
Equipment Enclosure 3314 HH with
Parkway Cover
EA
1
1.00
6,896.15
-
21(S)
Furnish And Install Electric Handhole
Equipment Enclosure 3315 HH with
Parkway Cover
EA
1
1.00
9,399.95
-
22(S)
Furnish and Install Electric Transformer
3427 Concrete Pad
EA
1
1.00
2,819.45
23(S)
Furnish And Install Electric 3316 HH with
Traffic Cover
EA
3
4.00
11,984.00
11,984.00
24(S)
Furnish and Install Electric Handhole
Equipment Enclosure 3309.2 HH
EA
14
14.00
770.40
25(S)
Furnish And Install Electric 3316 HH with
Parkway Cover
EA
1
1.00
12,385.25
26(S)
Furnish And Install Electric Transformer
3421 Concrete Pad
EA
19
19.00
572.45
27(S)
Adjust Handhole to Finished Grade
EA
6
7.00
802.50
802.50
28(S)
Concrete Encasement
LF
6,950
7,107.00
9.10
1,428.70
TOTAL:
136,281.27
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
Michael R. Dalla, CMC - City Clerk
619-336-4228 phone / 619-336-4229 fax
BASILE CONSTRUCTION
Change Order #19 and #20
8th Street Utility Undergrounding
and Sewer Replacement
Judy Hernandez (Engineering) Forwarded
Copy of Change Orders to Basile Construction