HomeMy WebLinkAbout2012 CON Palm Engineering - Change Order #3, #4, #5- Drainage Improvements ProjectDRAINAGE PROJECT, FY 11-12
Specification No. 11-07
Contractor: Palm Engineering and Construction, Inc.
;Reason/Purpose for this Change Order:
While excavating for the installation of drainage improvements on 4th Street, the Contractor encountered an
!abandoned asbestos concrete pipe (ACP) that was not shown as existing on the original plans. At the direction
iof the Field Engineer, the Contractor removed and disposed of the ACP in accordance with applicable laws and
regulations for disposals of such pipes. This resulted in additional costs to the Contractor for additional labor,
equipment, and materials.
CHANGE ORDER NO. 3
September 27, 2012
The City of National City and Contractor agree to the following change to the original Contract:
'The Contractor agreed to remove and dispose of the abandoned ACP Pipe in accordance with applicable laws
;and regulations. The City shall pay the Contractor for the additional labor, equipment, and materials in the
amount recorded and confirmed by the Field Engineer. The worker classifications and hours worked for the
additional labor are specified on Attachment "A", which is attached hereto and incorporated herein. The
Contractor and City agree that all costs for the additional labor, equipment, and materials is included in the price
of this Change Order.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 5
i Submitted by:
Working days subtracted: 0
9zz-i2
Date
187,212.90
3,000.00
190,212.90
1,081.31
Percent change in Contract to date 2.18%
191,294.21
Date
Cit En ineer Date CityMan er, required for Change Orders 424,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and acgre d to by Palm Engineering and Construction, Inc.:
7-1
Name: toil ..9-I13#8.M,7 /
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
Telephone (619) 336-4380
DRAINAGE PROJECT, FY 11-12
Specification #11-07
CHANGE ORDER NO. 3, Attachment "A"
DATE: July 20, 2012
WORK PERFORMED BY: Palm Engineering Construction Company, Inc.
DESCRIPTION OF WORK: Remove ACP pipe
DAILY ACCOUNTING FOR TIME, EQUIPMENT AND MATERIALS
LABOR
Unit
Qty
Wage
Total
1
Laborer
Hour
3.00
48.83
146.49
2
-
3
-
4
-
Sub -Total Labor:
Labor Burden (0%):
Labor Markup (20%):
TOTAL LABOR:
$ 146.49
$
$ 29.30
$ 175.79
EQUIPMENT
Unit
Qty
Rate
Total
1
Utility Truck
Hour
3.00
30.70
92.10
2
-
3
-
4
-
Sub -Total Materials:
Equipment Markup (150/0):
TOTAL MATERIALS:
$ 92.10
$ 13.82
$ 105.92
MATERIALS
Unit
Qty
Rate
Total
1
Disposal Fee
LS
1.00
686.00
686.00
2
-
3
-
4
-
5
-
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 686.00
$ 102.90
$ 788.90
Total Labor: $ 175.79
Total Materials: $ 105.92
Total Equipment: $ 788.90
Sub -Total $ 1,070.60
Bond (1%): $ 10.71
TOTAL: § 1,081.31
DRAINAGE PROJECT, FY 11-12
Specification No. 11-07
Contractor: Palm Engineering and Construction, Inc.
Reason/Purpose for this Change Order
Upon completion of the first two phases of the Project, the Engineering Department directed the Contractor not to
complete the third phase of the project at 4th Street and D Avenue due to lack of adequate funding. Prior to this
direction, the Contractor encountered costs for potholing at the third phase that was not included in the original
!contract line items. This resulted in additional costs to the Contractor for additional labor, equipment, and
!material.
CHANGE ORDER NO. 4
September 27, 2012
The City of National City and Contractor agree to the following change to the original Contract:
!The City shall pay the Contractor for the additional labor, equipment, and materials in the amount recorded and
;confirmed by the field Inspector. The worker classifications and hours worked for the additional labor are
'specified on Attachment "A", which is attached hereto and incorporated herein. The Contractor and City agree
'that all costs for the additional labor, equipment, and materials is included in the price of this Change Order.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 5
Submitte
[CI Engineer
Working days subtracted: 0
Date
187,212.90
4,081.31
191,294.21
2,948.53
Percent change in Contract to date 3.75%
194,242.74
Date
// #4 �
Date City anager, required for Change Orders >$24 999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Palm Engineering and Construction Inc
Name AOft 9/0 H4A 7,
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
DRAINAGE PROJECT, FY 11-12
Specification #11-07
CHANGE ORDER NO. 4, Attachment "A"
DATE: 4/20/12 and 6/22/12
WORK PERFORMED BY: Palm Engineering Construction Company, Inc.
DESCRIPTION OF WORK: Pothole on 4th and D
DAILY ACCOUNTING FOR TIME, EQUIPMENT AND MATERIALS
LABOR
Unit
Qty
Wage
Total
1
Laborer 1 (4)
Hour
16.00
48.83
781.28
2
Laborer 4
Hour
4.00
50.76
203.04
3
-
4
-
Sub -Total Labor:
Labor Burden (0%):
Labor Markup (20%):
TOTAL LABOR:
$ 984.32
$ -
$ 196.86
$ 1,181.18
EQUIPMENT
Unit
Qty
Rate
Total
1
Utility Truck
Hour
12.00
30.70
368.40
2
Compressor
Hour
3.00
18.69
56.07
3
Jack Hammer
Hour
3.00
0.40
1.20
4
Wacker/Compactor
Hour
6.00
8.82
52.92
Sub -Total Materials:
$ 478.59
Equipment Markup (150/0):
$ 71.79
TOTAL MATERIALS:
$ 550.38
MATERIALS
Unit
Qty
Rate
Total
1
RAP Sub -contractor (+ 5% markup)
LS
1.00
1,032.85
1,032.85
2
-
3
-
4
-
5
-
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 1,032.85
$ 154.93
$ 1,187.78
Total Labor: $ 1,181.18
Total Materials: $ 550.38
Total Equipment: $ 1,187.78
Sub -Total $ 2,919.34
Bond (1%): $ 29.19
TOTAL: $ 2,948.53
CALiFORNIA -
NATIONAL Orr
DRAINAGE PROJECT, FY 11-12
Specification No. 11-07
Contractor: Palm Engineering and Construction, Inc.
Reason/Purpose for this Change Order:
This Change Order will reconcile all the line item work actually performed and delivered to the project.
CHANGE ORDER NO. 5
November 11, 2012
The City of National City and Contractor agree to the following change to the original Contract:
;See "Attachment 5A" for a complete reconciliation of all items of work and change orders performed and
;delivered to the project by the Contractor and is an agreed upon final contract balance for the project.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
187,212.90
7,029.84
194,242.74
(14,307.53)
New contract amount $
Working days added: 5 Working days subtracted: 0
Submitted by
ved
ineer
Date
Percent change in Contract to date -3.89%
7,6 it? Nei
Date City M nager, required for Change Orders>$24 999 Date
179, 935.21
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
d agrr d d2 try Palm Engineering and Construction, Inc.:
:Name: Da
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
Telephone (619) 336-4380
CITY OF NATIONAL CITY
National City Drainage Improvements
Specification No. 11-07
FINAL PROJECT ACCOUNTING
November 11, 2012
Original Contract
To Date
Delta
No.
Item
Unit
Quantity
Unit Price
Amount
Final Quantities
Amount
Base Bid for 5th & D Streets:
1
Mobilization/Demobilization
LS
1
2,000.00
2,000.00
1.00
2,000.00
-
2
Traffic Control
LS
1
2,500.00
2,500.00
1.00
2,500.00
-
3
Demolition, Excavation, and Disposal
LS
1
2,000.00
2,000.00
1.00
2,000.00
-
4
Excavation & Disposal of Unsuitable
Subgrade and Replacement with CAB
TON
50
60.00
3,000.00
180.00
10,800.00
7,800.00
5
Curb & Gutter (Modified G-2 including
Transitions)
LF
204
30.00
6,120.00
351.00
10,530.00
4,410.00
6
Pedestrian Ramp (G-28)
EA
4
2,000.00
8,000.00
4.00
8,000.00
-
7
Cross Gutter (G-12 modified with #4
rebar 24" O.C. each way)
EA
2
4,500.00
9,000.00
2.00
9,000.00
-
8
PCC Sidewalk (G-7)
SF
300
8.00
2,400.00
351.00
2,808.00
408.00
9
1.5"Asphalt Grind
SF
97
2.00
194.00
97.00
194.00
-
10
3" Asphalt Grind
SF
2,453
2.30
5.641.90
4,906.00
11,283.80
5,641.90
11
Crushed Aggregate Base
TON
455
40.00
18,200.00
455.00
18,200.00
-
12
Asphalt Concrete
TON
253
137.00
34,661.00
344.01
47,129.37
12,468.37
13
Sign Relocation
EA
2
563.00
1,126.00
2.00
1,126.00
-
14
Replacement of Striping and Pavement
Markings
LS
1
1,250.00
1,250.00
1.00
1,250.00
-
15
Street Survey Monument (M-10)
EA
1
200.00
200.00
1.00
200.00
-
16
Bonds
LS
1
1,000.00
1,000.00
1.00
1,000.00
Additive Bid "A" for 5th & C Streets:
-
1
Mobilization/Demobilization
LS
1
1,000.00
1,000.00
1.00
1,000.00
-
2
Traffic Control
LS
1
1,500.00
1,500.00
1.00
1,500.00
-
3
Demolition, Excavation, and Disposal
LS
1
1,500.00
1,500.00
1.00
1,500.00
-
4
Excavation & Disposal of Unsuitable
Subgrade and Replacement with CAB
TON
50
60.00
3,000.00
55.47
3,328.20
328.20
5
Curb & Gutter (Modified G-2 including
Transitions)
LF
64
30.00
1,920.00
96.50
2,895.00
975.00
6
Pedestrian Ramp (G-28)
EA
2
2,000.00
4,000.00
2.00
4,000.00
-
.7
Cross Gutter (G-12 modified with #4
rebar 24" O.C. each way)
EA
1
4,500.00
4,500.00
1.00
4,500.00
-
8
PCC Sidewalk (G-7)
SF
150
8.00
1,200.00
175.00
1,400.00
200.00
9
1.5" Asphalt Grind
SF
135
2.20
297.00
135.00
297.00
-
10
Crushed Aggregate Base
TON
155
50.00
7,750.00
155.00
7,750.00
-
11
Asphalt Concrete
TON
85
165.00
14,025.00
85.00
14,025.00
-
12
Sign Relocation
EA
2
563.00
1,126.00
2.00
1,126.00
-
13
Striping and Paving Markings
LS
1
813.00
813.00
1.00
813.00
-
14
Bonds
1
750.00
750.00
1.00
750.00
-
Additive Bid 'B" for 4th & D Streets:
1
Mobilization/Demobilization
LS
1
1,500.00
1,500.00
-
-
(1,500.00)
(1,500.00)
2
Traffic Control
LS
1
1,500.00
1,500.00
-
-
3
Demolition, Excavation, and Disposal
LS
1
1,500.00
1,500.00
-
(1,500.00)
4
Excavation & Disposal of Unsuitable
Subgrade and Replacement with CAB
TON
50
60.00
3,000.00
-
-
(3,000.00)
5
Pedestrian Ramp (G-28)
EA
4
2,000.00
8,000.00
-
-
(8,000.00)
6
Cross Gutter (G-12 modified with #4 reba
EA
2
4,500.00
9,000.00
-
-
(9,000.00)
(2,400.00)
7
PCC Sidewalk (G-7)
SF
300
8.00
2,400.00
-
-
8
1" - 2" Asphalt Grind
SF
937
3.00
2,811.00
-
-
(2,811.00)
9
Crushed Aggregate Base
TON
50
60.00
3,000.00
-
-
(3,000.00)
(9,500.00)
10
Asphalt Concrete
TON
50
190.00
9,500.00
-
-
11
Sign Relocation
EA
4
410.00
1,640.00
-
-
(1,640.00)
12
Striping and Paving Markings
LS
1
1,688.00
1,688.00
-
-
(1,688.00)
13
Bonds
LS
1
1,000.00
1,000.00
-
-
(1,000.00)
Original Contract Total
187,212.90
Change Orders
1
Install 60 LF of Concrete Cover
LS
1
1,800.00
1,800.00
1.00
1,800.00
-
2
Install 40 LF of Concrete Cover
LS
1
1,200.00
1,200.00
1.00
1,200.00
-
3
Remove and dispose ofACP
LS
1
1,081.31
1,081.31
1.00
1,081.31
-
4
Potholing at 4th/D
LS
1
2,948.53
2,948.53
1.00
2,948.53
-
FINAL ADD/DEDUCT
(14,307.53)
TOTALS:
194,242.74
179,935.21
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
PALM ENGINEERING
Change Order #3, #4 and #5
Drainage Improvements Project
Judy Hernandez (Engineering) Forwarded
Copy of Change Orders to Palm Engineering