HomeMy WebLinkAbout2013 CON Basile Construction - 8th St Utility Undergrounding - Change Order #268TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT
Specification No. 11-04
Contractor: Basile Construction, Inc.
CHANGE ORDER NO. 26
February 13, 2013
Reason/Purpose for this Change Order:
Per request of SDG&E, Contractor did not install five (5) 3312 handholes and instead installed one (1) 3311
handhole (single) and five (4) 3311 handholes (double). This change in contract resulted in additional costs to the
Contractor as outlined on Attachment "A".
The City of National City and Contractor agree to the following change to the original Contract:
The City shall pay the Contractor for the additional work in the amount recorded and confirmed by the field
Inspector as outlined on Attachment "A", which is attached hereto and incorporated herein. The Contractor and
City agree that all costs for this work are included in the price of this Change Order.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0
Working days subtracted: 0
2,386,365.49
247,012.25
2,633,377.74
2,467.50
Percent change in Contract to date 10.45%
2,635,845.24
Submitt by:
r ' M
Date
f;f+ r
er
Date
PPr v b
City ngineer
2-28'-ems
Date
0 il
City anager, required for Change Orders >$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are inc or ted herein.
Ac eptedland agreed to by Basile Construction, Inc.:
c_r
ame:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
�-;C�1UFORNIJ -.a
X CORYORATtD V�
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 26
Specification No. 11-04
Utility Company Acceptance Declarations
Page 2of2
Accepted and agreed to by CoxCom, Inc. d/b/a Cox Communications:
Name:
Date
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Accepted and agreed to by SDG&E:
ti
Name:
Date
. By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Originals: City Clerk, Contractor, Utilities
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
(06'4,61 •'IED yam.
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 26, Attachment "A"
Specification #11-04
Itemized Breakdwon
Qty Unit Unit Cost Item Cost
1)
2)
3)
Credit for furnish and install 3312 HH
Furnish and install 3311 HH Single
Furnish and inntall 3311 HH Double
-5.00
1.00
4.00
EA
EA
EA
235.00
505.00
755.00
Subtotal:
Contractor Markup (5%):
TOTAL AMOUNT OF CHANGE ORDER:
(1,175.00)
505.00
3,020.00
2,350,00
117.50
$ 2,467.50
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
BASILE CONSTRUCTION
Change Order #26
8th Street Utility Undergrounding
Lynn Cole (Engineering) Forwarded
Copy of Amendment to Basile Construction