HomeMy WebLinkAbout2013 CON Basile Construction - 8th St Utility Undergrounding - Change Order #27+h-- CALIFORNIA
NATIONAL CI
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT
Specification No. 11-04
Contractor: Basile Construction, Inc.
CHANGE ORDER NO. 27
February 13, 2013
Reason/Purpose for this Change Order.
After the DBLs were approved, AT&T requested that 3' x 5' pull boxes be installed at 2 locations on 8th Street
instead of the 2' x 3' pull boxes that were scheduled to be installed.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor shall install two 3' x 5' pull boxes on 8th Street between E Street and Highland Ave in place of the
2' x 3' pull boxes that were scheduled to be installed. The calculation for compensation under this change order
is found on Attachment "A", attached hereto and incorporated herein. The Contractor and City agree that an
costs for the work described above are included in the price of this Change Order.
Original Contract Amount $ 2,386,385.49
Net change by previously authorized Change Orders
Subtotal
249,479.75
2,635,845.24
Amount of this change order 4,032.00
New contract amount $
Working days added: 0 Working days subtracted: 0 Percent change in Contract to data 10.62%
Subm = d by:
City ngineer Date City Manager, required for Change Orders 404,sas Date
er
z- 27-/3
Date
2,639,877.24
er Date
By signing this Change Order the Contractor conlrma that he/she is completely familiar with its terms and conditions and has fairly negotiated Its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment. materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance ,.,_ , etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are
in
ed to by Basile Construction, Inc.:
Name:
Date
r3
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Utility Company Acceptance of and Agreement to this Change Order found on Page 2
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
+- CALIFORNIA •-►
NATIONAL cnrit
8TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 27
Specification No. 11-04 Page 2 of 2
Utility Company Acceptance Declarations
Accepted and agreed to by CoxCom, Inc. d/b/a Cox Communications:
Name: Date
By signing this Change Order the Utility Company confirms that it is familiar with the terms and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Accepted and agreed to by SDG&E:
Name:
Date
By signing this Change Order the Utility Company confirms that it is familiar with the terns and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Accepted and agreed to, as to the work only, by AT&T
Name: Date
By suing this Change Order the Utility Company confirms that it is familiar with the temps and conditions of the Change Order and that it
accepts and agrees to the fairly negotiated terms, conditions, and price for this Change Order.
Originals: City Clerk, Contractor, Utilities cc: Engineering project fie, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA r .
NATIONAL Car
opaQ
5TH STREET UTILITY UNDERGROUNDING AND SEWER REPLACEMENT CHANGE ORDER NO. 27, Attachment "A"
Specification #11-04
Itemized 6nakdwon Qty Unit Unit Cost Item Cost
1)
Install 3 x 5 AT&T Pull Box
2.00 1 EA I 1,920.00
Subtotal:
Contractor Markup (5%):
TOTAL AMOUNT OF CHANGE ORDER:
3,840.00
3,840.00
192.00
$ 4,032.00
OFFICE OF THE CITY CLERK
1243 National City Blvd.
National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
BASILE CONSTRUCTION
Change Order #27
8th Street Utility Undergrounding
Judy Hernandez (Engineering) Forwarded
Copy of Change Order to Basile Construction