Citywide Pedestrian Crossings CHANGE ORDER NO. 3
Specification No. 12-12 April 10, 2013
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order.
Contractor was directed to repair pothole due to a failed abandon utility abandonment as directed by National
City at NC Blvd. and 7th.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor will grind the additional area to a depth of approximately 8" to 12" and patch back with asphalt
to fill the existing pothole and repair to a smooth compacted uniform finish.
Original Contract Amount $ 813,949.15
Net change by previously authorized Change Orders
Subtotal 808, 752.15
Amount of this change order 217.92
New contract amount . . . . $ 808,970.07
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date -0.61 %
Submitted by:
5 -1 V-13
'ect Manager Date
pproved by:
Cingineer Date City Manager, required for Change Orders >ssasae Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
(5,197.00)
Date
— eo r A rAts 1-r4-5-- 11 --13
Name: Date
Note to contractor: It you ao not agree witn mis unange uraer you may alrectea to proceed wan this worK unaer me terms or me
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
vour claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
NATI
(rcaaros
Citywide Pedestrian Crossings CHANGE ORDER NO. 6
Specification No. 12-12 May 10, 2013
Contractor: Koch -Armstrong
:Reason/Purpose for this Change Order:
Deletion of the bio-barrier at National City Blvd. and 14th St. as they were no longer needed with the deletion
of the 36" box trees by the designer.
The City of National City and Contractor agree to the following change to the original Contract:
Delete bio-barrier at National City Blvd. and 14th St. as they were no longer needed with the deletion of the
36" box trees by the designer.
Original Contract Amount $ 813,949.15
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
2,792.36
816,741.51
(3,230.00)
New contract amount $ 813,511.51
Working days added: 0
Sub ; ted by:
Working days subtracted: 0
t/‘ /
CitrEngineer Date City Manager, required for Change Orders >s2ass9 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein, Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Percent change in Contract to date -0.05%
Accepted and agreed to by (Contractor's name):
J4
Narr{e: Date 1
mate s COrkfaCtar rryou do not agree ci n-tnit mange-ura r ymr may e-rn ecterMartreeed WO this wor1runaertne refrffertfle
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
ATION lL CHT
ZNCORPORA.rEr?
Citywide Pedestrian Crossings
Specification No. 12-12
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order:
Excavate wet subgrade under existing cross gutter on southwest side of 30th St. and F Ave. as directed.
CHANGE ORDER NO. 7
May 10, 2013
The City of National City and Contractor agree to the following change to the original Contract:
Contractor encountered wet and yielding material at 30th St. and F Ave. at the southwest corner of 30th St.
and F Ave. and was directed to proceed with excavating and processing this material on a T&M basis.
Original Contract Amount $ 813,949.15
Net change by previously authorized Change Orders (437.64)
Subtotal
Amount of this change order
New contract amount $ 814,561.91
813,511.51
1,050.40
Working days added: 0
Sub ed by:
ect Manager
Approved by:
ngineer
Working
days subtracted: 0 Percent change in Contract to date 0.08%
Date
dl(/3
Date
Lbate
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Name: Date
Note to contractor. it you ao not agree wan tnis Unange uraer you may De-airectea to proceed wltninls work under tne terms or tne
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
— CALIFORNIA
NATIONAL CITY
.;..0f
lNCORPON ATV,'
Citywide Pedestrian Crossings CHANGE ORDER NO. 8
Specification No. 12-12 Mav 10. 2013
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order:
Contractor was directed by the city to excavate and grade 5'x50' of subgrade for sidewalk, remove and
replace 66 If of curb and gutter and repair the slot patch as needed at 21 st. And I Ave.
The City of National City and Contractor agree to the following change to the original Contract:
Contractor will excavate 5'x50' of subgrade, place sidewalk at same location, remove and replace 66 If of curb
and gutter and repair the slot patch as needed at 21st. And I Ave. All work includes necessary clean-up traffic
control, posting etc.
Original Contract Amount $ 813,949.1E
Net change by previously authorized Change Orders
612.76
Subtotal 814,561.91
Amount of this change order 5,777.20
New contract amount
Working days added: 0
Sub $y- d by::
Working days subtracted: 0
s -ILf-I�
Date
7� i/(//-
City'Engineer Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price slated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
$ 820,339.11
Percent change in Contract to date 0.79%
Date
or' - `4 S= / Y-13
Name: Date
Note to contractor: it you ao not agree witn tms unange Uraer you may be airectea to proceea witn this wort unaer the terms oT the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
4— CALIFORNIA -4
NATIONAL Cfl'V
y e s
-r�NCOR3O RA ED��
Citywide Pedestrian Crossings CHANGE ORDER NO. 9
Specification No. 12-12 May 10, 2013
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order:
Revised ADA standard to include 3 additional ADA Pedestrian Passageways on 8th St. in lieu of striped
crosswalks currently shown on plans.
The City of National City and Contractor agree to the following change to the original Contract:
Contractor will excavate and remove three 11' x 11' areas in the proposed center median locations for the
addition of ADA Pedestrian Passageways as directed by Nation City. Work includes necessary removals,
traffic control, concrete flatwork, curb and tactile domes required to construct per ADA Standard.
Original Contract Amount $ 813,949.15
Net change by previously authorized Change Orders 6,389.96
Subtotal
Amount of this change order
New contract amount $ 828,166.93
Working days added: 2
820,339.11
7,827.82
CitTi Engineer
Working days subtracted: 0
I1(-)3
Date
Date
Percent change in Contract to date 1.75%
City Manager, required for change orders 424,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Cleerk,1 for Contractor)
Accepted and agreed to by (Contractor's name):
S"—>c1 I3
Name: Date
Note to contractor: n you ao not agree wim mis mange uraer you may De airectea to proceed with tms work under the terms OT the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
Citywide Pedestrian Crossings
Specification No. 12-12
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order:
Deletion of planted median on 8th St. Original design called for drought tolerant material with no irrigation.
Current design requirements could pose added maintenance cost issues for the city with a low survivability
rate of plant material. City will review adding this island at a later date with an automatic irrigation system.
CHANGE ORDER NO. 10
May 10, 2013
The City of National City and Contractor agree to the following change to the original Contract:
Delete survey, unclassified excavation, portion of median curb, vegetation median, and a portion of the misc.
signage and striping with the deletion of the planted median on 8th St.
Original Contract Amount $ 813,949.15
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $ 822,124.16
Working days added: 0 Working days subtracted: 2 Percent change in Contract to dale 1.00%
S . ' tted by:
14,217.78
828,166.93
(6,042.77)
t Manager
roved by:
City,Enjineer Date City Manager, required for change orders 424,996 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confimis that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name)._
Name: Date
t OW161.: lrratt6f' III you da not agreewlm nir?;"Gnaive'U7eter Air r'iaq t56'clfrateoT5ptoteed with gig WM under the' rerfProt tne.
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
4.- CALIFORNIA 4-44
NATIONAL CITY
d,3J 1 —�
INCORPORATED
Citywide Pedestrian Crossings
Specification No. 12-12
Contractor: Koch -Armstrong
Reason/Purpose for this Change Order:
Additional striping at 7th St. and NC Blvd. as directed by National City.
CHANGE ORDER NO. 11
May 10, 2013
The City of National City and Contractor agree to the following change to the original Contract:
Contractor will add the additional detail 26 around new median, water blast and remove the existing
thermoplastic left turn arrow and replace with new thermoplastic left turn arrow as directed.
Original Contract Amount $ 813,949.15
8,175.01
Net change by previously authorized Change Orders
Subtotal
822,124.16
Amount of this change order 963.00
New contract amount $ 823,087.16
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 1.12%
Submi -d by:
City ngineer Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
14 all -1/ ,. 5 ' Cf )3
Name: Date
Note to contractor: ir you ao not agree wim tnis Gnange uraer you may De arrectea to proceed witn tnis work under the terms or the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
KOCH ARMSTRONG GENERAL ENGINEERING
Citywide Pedestrian Crossings Project
Change Order #3, #6, #7, #8, #9, #10 and #11
Judy Hernandez (Engineering) Forwarded Copy of
Change Orders to Koch Armstrong General Armstrong