HomeMy WebLinkAbout2013 CON Project Professionals - Project Management Services Capital Improvement Projects - Amendment #5FIFTH AMENDMENT TO AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
PROJECT PROFESSIONALS CORPORATION
This Fifth Amendment to the Agreement is entered into this 15th day of October,
2013 by and between the City of National City, a municipal corporation ("CITY"), and
Project Professionals Corporation (the "CONSULTANT").
RECITALS
WHEREAS, The CITY and the CONSULTANT entered into an agreement on
October 5, 2010, ("the Agreement") through the adoption of City of National City Council
Resolution No. 2010-225, wherein the CONSULTANT agreed to provide on -call general
engineering services, construction inspections and project management services for
various Capital Improvement Projects.
WHEREAS, the original Agreement had a not -to -exceed amount of $300,000; and
WHEREAS, the original Agreement was set to expire on October 6, 2012, with
optional extensions when mutually agreed upon by the parties; and
WHEREAS, on July 5, 2011, the City Council adopted Resolution No. 2011-143,
approving the First Amendment to the Agreement increasing the not -to -exceed amount by
$300,000, for a total Agreement amount of $600,000; and
WHEREAS, on January 24, 2012, the City Council adopted Resolution No. 2012-
20, approving the Second Amendment to the Agreement increasing the not -to -exceed
amount by $300,000, for a total Agreement amount of $900,000; and
WHEREAS, on September 4, 2012, the City Council adopted Resolution No. 2012-
187, approving the Third Amendment to the Agreement increasing the not -to -exceed
amount by $300,000, for a total Agreement amount of $1,200,000, and extending the term
of the Agreement through October 6, 2013; and
WHEREAS, on May 7, 2013, the City Council adopted Resolution No. 2013-59,
approving the Fourth Amendment to the Agreement increasing the not -to -exceed amount
by $430,000, for a total Agreement amount of $1,630,000, and extending the term of the
Agreement through October 5, 2014; and
WHEREAS, to continue timely completion of Capital Improvement Projects, the
parties desire to increase the not -to -exceed amount by $300,000, for a total Agreement
amount of $1,930,000.
AGREEMENT
NOW, THEREFORE, the parties agree to amend the Agreement entered into on
October 5, 2010 to increase the not -to -exceed amount by $300,000, for a total Agreement
amount of $1,930,000.
The parties further agree that with the foregoing exception, each and every term
and provision of the Agreement dated October 5, 2010, shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the
date and year first above written.
CITY OF NATIONAL CITY
By:
C
City A
n Morrison, ayor
PROVED AS TO FORM:
a Silva
PROJECT PROFESSIONALS CORPORATION
(Signatures of two corporate officers required)
By:
By:
(Name)
f z_ i► 1e c)
(Title)
(Signature) Lean IY ( .O.
IiacdG�-
RESOLUTION NO. 2013 — 155
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE A FIFTH AMENDMENT
TO THE AGREEMENT WITH PROJECT PROFESSIONALS CORPORATION
TO INCREASE THE NOT -TO -EXCEED AMOUNT OF THE AGREEMENT
BY $300,000 FOR ON -CALL GENERAL ENGINEERING SERVICES,
CONSTRUCTION INSPECTIONS AND PROJECT MANAGEMENT
SERVICES FOR VARIOUS CAPITAL IMPROVEMENT PROJECTS
WHEREAS, on October 5, 2010, the City Council adopted Resolution No. 2010-
225, approving a two-year Agreement with Project Professionals Corporation to provide on -call
general engineering, construction inspections, and project management services for various
Capital Improvement Projects for a not to exceed amount of $300,000; and
WHEREAS, on July 5, 2011, the City Council adopted Resolution No. 2011-143,
approving the First Amendment to the Agreement increasing the not to exceed amount an
additional $300,000, for a total Agreement amount of $600,000; and
WHEREAS, on January 24, 2012, the City Council adopted Resolution No. 2012-
20, approving the Second Amendment to the Agreement, increasing the not to exceed amount
an additional $300,000, for a total Agreement amount of $900,000; and
WHEREAS, on September 4, 2012, the City Council adopted Resolution No.
2012-187, approving the Third Amendment to the Agreement, extending the term of the
Agreement for one additional year for the not to exceed amount of $300,000, for a total
Agreement amount of $1,200,000; and
WHEREAS, on May 7, 2013, the City Council adopted Resolution No. 2013-59,
approving the Fourth Amendment to the Agreement, extending the term of the Agreement until
completion of on -going Capital Improvement Projects, but no later than October 5, 2014, for the
not to exceed amount of $430,000, for a total Agreement amount of $1,630,000; and
WHEREAS, to continue timely completion of Capital Improvement Projects, a
Fifth Amendment to the Agreement is necessary to increase the not to exceed amount of the
Agreement by $300,000, for a total Agreement amount of $1,930,000.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute the Fifth Amendment to the Agreement
with Project Professionals Corporation for the not to exceed amount of $300,000, for a total
Agreement amount of $1,930,000. Said Fifth Amendment to the Agreement in on file in the
office of the City Clerk.
PASSED and ADOPTED this 15th day of October 013.
ATTEST:
/ityMichael R. Dalla,lerk
or
rn Morrison, Y ayor
PROVED AS TO FORM:
audi
City A
Gaci
rney
a Silva
Passed and adopted by the Council of the City of National City, California, on October
15, 2013 by the following vote, to -wit:
Ayes: Councilmembers Cano, Morrison, Natividad, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2013-155 of the City of National City, California, passed and
adopted by the Council of said City on October 15, 2013.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
EETING DATE: October 15, 2013
AGENDA ITEM NO. 12
EM TITLE:
Resolution of the City Council of the City of National City authorizing the Mayor to execute a Fifth Amendment
to the Agreement with Project Professionals Corporation to increase the not -to -exceed amount of the Agreement
by $300,000 for on -call general engineering services, construction inspections and project management services
for various Capital Improvement Projects (funded by various CIP projects)
PREPARED BY: Stephen Manganiello
PHONE: 336-4382
EXPLANATION:
See attached
•
DEPARTMENT: Engineering
APPROVED BY:
FINANCIAL STATEMENT:
ACCOUNT NO.
There is no financial impact at this time. Funds will be encumbered on an as -needed basis from previously
approved CIP project appropriations.
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED:
APPROVED:
Finance
MIS
STAFF RECOMMENDATION:
Adopt resolution
BOARD / COMMISSION RECOMMENDATION:
N/A
ATACHMENTS:
1. Explanation
2. Fifth Amendment — Project Professionals Corporation
3. Resolution
�\ L.\ \_,c.
Explanation:
On October 5, 2010, per City Council Resolution No. 2010-225, the City of National City
entered into an agreement with Project Professionals Corporation to provide on -call
general engineering services, construction inspections and project management
services for various Capital Improvement Projects. The Agreement was for a not -to -
exceed amount of $300,000 and a term of two years, with the option to extend.
On July 5, 2011, the City Council adopted Resolution No. 2011-143, approving the First
Amendment to the Agreement increasing the not -to -exceed amount by $300,000.
On January 24, 2012, the City Council adopted Resolution No. 2012-20, approving the
Second Amendment to the Agreement increasing the not -to -exceed amount by
$300,000.
On September 4, 2012, the City Council adopted Resolution No. 2012-187, approving
the Third Amendment to the Agreement increasing the not -to -exceed amount by
$300,000 and extending the term of the Agreement through October 6, 2013.
On May 7, 2013, the City Council adopted Resolution No. 2013-59, approving the
Fourth Amendment to the Agreement increasing the not -to -exceed amount by $430,000
and extending the term of the Agreement through October 5, 2014.
Project Professionals Corporation is currently performing construction management and
inspection services for the following "active" CIP projects:
• National City Aquatic Center
• 8th Street Smart Growth Revitalization (Trolley Station to Highland Ave)
• 8th Street Safety Enhancements (Highland Ave to Palm Ave)
• Community Corridor Improvements (4th St, "D" Ave, Coolidge Ave & 18th St)
• WI-TOD / PW Relocation
• Police Department Electrical Upgrades
• Police Department Property & Evidence Room Upgrades
• Civic Center Chiller (Airside) Upgrades
• Kimball Tower Boiler Replacement
In order to keep these projects on schedule to meet various funding expenditure
requirements and commitments to the residents of National City, staff is requesting a
Fifth Amendment to the Agreement to add an additional $300,000.
National City's 5-Year CIP is estimated to deliver over $53 million in capital projects for
residents of National City. In order to successfully deliver these projects, staff will be
administering a competitive Request for Qualifications (RFQ) for various engineering
and construction support services. This process is estimated to take approximately four
months. In the interim, staff will need to rely on existing "On -call" service contracts for
assistance with project delivery. Therefore, staff recommends execution of a Fifth
Amendment to the Agreement with Project Professionals Corporation.
FIFTH AMENDMENT TO AGREEMENT
BY AND BETWEEN
THE CITY OF NATIONAL CITY
AND
PROJECT PROFESSIONALS CORPORATION
This Fifth Amendment to the Agreement is entered into this 15th day of October,
2013 by and between the City of National City, a municipal corporation ("CITY"), and
Project Professionals Corporation (the "CONSULTANT").
RECITALS
WHEREAS, The CITY and the CONSULTANT entered into an agreement on
October 5, 2010, ("the Agreement") through the adoption of City of National City Council
Resolution No. 2010-225, wherein the CONSULTANT agreed to provide on -call general
engineering services, construction inspections and project management services for
various Capital Improvement Projects.
WHEREAS, the original Agreement had a not -to -exceed amount of $300,000; and
WHEREAS, the original Agreement was set to expire on October 6, 2012, with
optional extensions when mutually agreed upon by the parties; and
WHEREAS, on July 5, 2011, the City Council adopted Resolution No. 2011-143,
approving the First Amendment to the Agreement increasing the not -to -exceed amount by
$300,000, for a total Agreement amount of $600,000; and
WHEREAS, on January 24, 2012, the City Council adopted Resolution No. 2012-
20, approving the Second Amendment to the Agreement increasing the not -to -exceed
amount by $300,000, for a total Agreement amount of $900,000; and
WHEREAS, on September 4, 2012, the City Council adopted Resolution No. 2012-
187, approving the Third Amendment to the Agreement increasing the not -to -exceed
amount by $300,000, for a total Agreement amount of $1,200,000, and extending the term
of the Agreement through October 6, 2013; and
WHEREAS, on May 7, 2013, the City Council adopted Resolution No. 2013-59,
approving the Fourth Amendment to the Agreement increasing the not -to -exceed amount
by $430,000, for a total Agreement amount of $1,630,000, and extending the term of the
Agreement through October 5, 2014; and
WHEREAS, to continue timely completion of Capital Improvement Projects, the
parties desire to increase the not -to -exceed amount by $300,000, for a total Agreement
amount of $1,930,000.
AGREEMENT
NOW, THEREFORE, the parties agree to amend the Agreement entered into on
October 5, 2010 to increase the not -to -exceed amount by $300,000, for a total Agreement
amount of $1,930,000.
The parties further agree that with the foregoing exception, each and every term
and provision of the Agreement dated October 5, 2010, shall remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the
date and year first above written.
CITY OF NATIONAL CITY PROJECT PROFESSIONALS CORPORATION
(Signatures of two corporate officers required)
By: By:
Ron Morrison, Mayor (Signature)
(Name)
APPROVED AS TO FORM:
(Title)
Claudia Gacitua Silva
City Attorney By:
(Signature)
(Name)
(Title)
RESOLUTION NO. 2013 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE A FIFTH AMENDMENT
TO THE AGREEMENT WITH PROJECT PROFESSIONALS CORPORATION
TO INCREASE THE NOT -TO -EXCEED AMOUNT OF THE AGREEMENT
BY $300,000 FOR ON -CALL GENERAL ENGINEERING SERVICES,
CONSTRUCTION INSPECTIONS AND PROJECT MANAGEMENT
SERVICES FOR VARIOUS CAPITAL IMPROVEMENT PROJECTS
WHEREAS, on October 5, 2010, the City Council adopted Resolution No. 2010-
225, approving a two-year Agreement with Project Professionals Corporation to provide on -call
general engineering, construction inspections, and project management services for various
Capital Improvement Projects for a not to exceed amount of $300,000; and
WHEREAS, on July 5, 2011, the City Council adopted Resolution No. 2011-143,
approving the First Amendment to the Agreement increasing the not to exceed amount an
additional $300,000, for a total Agreement amount of $600,000; and
WHEREAS, on January 24, 2012, the City Council adopted Resolution No. 2012-
20, approving the Second Amendment to the Agreement, increasing the not to exceed amount
an additional $300,000, for a total Agreement amount of $900,000; and
WHEREAS, on September 4, 2012, the City Council adopted Resolution No.
2012-187, approving the Third Amendment to the Agreement, extending the term of the
Agreement for one additional year for the not to exceed amount of $300,000, for a total
Agreement amount of $1,200,000; and
WHEREAS, on May 7, 2013, the City Council adopted Resolution No. 2013-59,
approving the Fourth Amendment to the Agreement, extending the term of the Agreement until
completion of on -going Capital Improvement Projects, but no later than October 5, 2014, for the
not to exceed amount of $430,000, for a total Agreement amount of $1,630,000; and
WHEREAS, to continue timely completion of Capital Improvement Projects, a
Fifth Amendment to the Agreement is necessary to increase the not to exceed amount of the
Agreement by $300,000, for a total Agreement amount of $1,930,000.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute the Fifth Amendment to the Agreement
with Project Professionals Corporation for the not to exceed amount of $300,000, for a total
Agreement amount of $1,930,000. Said Fifth Amendment to the Agreement in on file in the
office of the City Clerk.
PASSED and ADOPTED this 15th day of October, 2013.
Ron Morrison, Mayor
ATTEST: APPROVED AS TO FORM:
Michael R. Dalla, City Clerk Claudia Gacitua Silva
City Attorney
81PL r:l.
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
October 21, 2013
Mr. Byron Wade
Project Professionals Corporation
656 Fifth Avenue, Suite W
San Diego, CA 92101
Dear Mr. Wade,
On October 15th, 2013, Resolution No. 2013-155 was passed and adopted by the City
Council of the City of National City, authorizing execution of Amendment #5 to an
Agreement with Project Professionals Corporation.
We are enclosing for your records a certified copy of the above Resolution and a fully
executed original Amendment.
Michael R. Dalla, CMC
City Clerk
Enclosures
cc: Engineering Dept.