8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering, Inc.
CHANGE ORDER NO. 8
February 11, 2014
Reason/Purpose for this Change Order:
There are 3 Mexican Fan Palms at the Northwest corner of 8th Street and F Avenue that are in conflict with the
new improvements. The Engineer recommends that they be removed for the new planter area to be properly
installed.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall remove, stump and dispose of the 3 Mexican Fan
Palms at the Northwest corner of 8th street and F Avenue. The agreed upon lump sum price for all costs
associated with this work is $1,144.50, see Attachment "A" for cost breakdown.
Original Contract Amount ... $ 3,709,079.35
Net change by previously authorized Change Orders 707,555.87
Subtotal
4,416,635.22
Amount of this change order 1,144.50
New contract amount . $ 4,417,779.72
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 19.11%
Submitted by:
Pr ect Marla
Approved by:
Date
ipt
City_ Project Manager
Date
Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by PAL General Engineering, Inc.:
/.49.441hYna l _..
Name:
(tots
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA -
NATIONAL CITY
tNco po ATED
8TH STREET SMART GROWTH REVITALIZATION CHANGE ORDER NO. 8, Attachment "A"
Specification #12-13
DATE: February 11, 2014
WORK PERFORMED BY: PAL General Engineering, Inc.
DESCRIPTION OF WORK: Remove 3 Mexican Fan Palms
LABOR, MATERIALS AND EQUIPMENT
Unit
Qty
Rate
Total
Removal of 3 Mexican Fan Palms at the Northwest corner of 8th Street and F Ave.
LS
1.00
1,090.00
1,090.00
Markup (5%):
TOTAL COST:
$ 54.50
$ 1,144.50
-0- CALIFORNIA
NATIONAL CITY
INCORPORATED
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering, Inc.
CHANGE ORDER NO. 9
February 28, 2014
Reason/Purpose for this Change Order:
The Engineer found a grade conflict with the sidewalk layout of the new improvements at Station 47+50. To fix
make the grades ADA compliant.. The work proceeded by time and materials under the direction of the
Engineer.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall remove and dispose of the improvements to the curb,
gutter and flatwork at Station 47+50 as directed by the Engineer to accomodate ADA compliance. The total
time, equipment and materials including all assiciated costs for this work is the amount as stated on this Change
Order. See Attachment "A" for cost breakdown.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
3,709,079.35
708, 700.37
4,417,779.72
655.92
New contract amount $ 4,418,435.64
Working days added: 0 Working days subtracted: 0
Submitted by:
Approved by:
MP/
Date
Date
Percent change in Contract to date 19.12%
Project Manager
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confines that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by PAL General Engineering, Inc.:
Name:
hz//y
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA -
NATIONAL CITY
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
INCORPORATED `
CHANGE ORDER NO. 9, Attachment "A"
DATE: February 18, 2014
WORK PERFORMED BY: PAL General Engineering, Inc.
DESCRIPTION OF WORK: Ped Ramp and curb Gutter Removal
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Laborer
Hour
1.00
53.15
53.15
2)
Laborer
Hour
1.00
53.15
53.15
3)
Operator
Hour
0.50
72.00
36.00
Sub -Total Labor:
Labor Burden (13%):
Labor Markup (20%):
TOTAL LABOR:
$ 142.30
$ 18.50
$ 28.46
$ 189.26
MATERIALS
Unit
Qty
Rate
Total
1)
Dump Fees
EA
1.00
150.00
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
150.00
$ 163.13
$ 24.47
$ 187.60
EQUIPMENT
Unit
Qty
Rate
Total
1)
Backhoe 430F
Hour
0.50
65.31
$ 32.66
2)
10 Wheeler (w/Driver)
Hour
1.50
110.00
$ 165.00
3)
Demo Saw
Hour
0.50
50.00
$ 25.00
4)
Breaker Attachment
Hour
0.50
40.00
$ 20.00
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL MATERIALS:
$ 242.66
$ 36.40
$ 279.06
Total Labor: $ 189.26
Total Materials: $ 187.60
Total Equipment: $ 279.06
TOTAL: $ 655.92
�^ CALIFORNIA -�
NATIONAI inr
flo
INCORPORATED
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering, Inc.
CHANGE ORDER NO. 10
February 28, 2014
Reason/Purpose for this Change Order:
The City Engineer requests additional striping, and markings on 16th Street and Highland Avenue and behind
City Hall at the handicap stall that are not included in the orginal contract.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall remove and install new striping, and markings, along
16th Street at Highland Avenue and behind City Hall. The agreed upon lump sum price for all costs associated
with this work is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount
...........
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0 Working days subtracted: 0
Submitted by:
Approved by:
ngineer
Date
Date
3,709,079.35
709,356.29
4,418,435.64
4,189.50
Percent change in Contract to date 19.24%
4,422,625.14
City Project Manager Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by PAL General Engineering, Inc.:
Name:
311z1/�
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
-t- CALIFORNIA
NATIONAL cir
ztv
INCORPORATED -
8TH STREET SMART GROWTH REVITALIZATION CHANGE ORDER NO. 10, Attachment "A"
Specification #12-13
DATE: Feburary 26, 2014
WORK PERFORMED BY: PAL General Engineering, Inc.
DESCRIPTION OF WORK: Remove and install striping along 16th St at Highland Ave.
LABOR, MATERIALS AND EQUIPMENT
Unit
Qty
Rate
Total
Remove and install striping along 16th St at Highland Ave
LS
1.00
3,440.00
3,440.00
Remove and install handicap stall behind City Hall
LS
1.00
550.00
550.00
SUB TOTAL:
Markup (5%):
TOTAL COST:
3,990.00
$ 199.50
$ 4,169.50
CALIFORNIA -K
NoIONAL CITY
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering, Inc.
CHANGE ORDER NO. 11
March 3, 2014
Reason/Purpose for this Change Order:
The Engineer directed the contractor to remove the driveway at 333 8th Street because the grades were in
conflict with the new sidewalk, curb and gutter improvements.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall remove the existing driveway at 333 8th Street at a
lump sum price of $277.20 and the installation of the new driveway will be charged to bid item no.10 "Construct
PCC Driveways". The lump sum change order price includes all labor, materials, and equipment required to
complete this work. The agreed upon lump sum price for all costs associated with this work is as stated on this
Change order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 3,709,079.35
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
713, 545.79
4,422,625.14
277.20
New contract amount $ 4,422,902.34
Working days added: 0
Submitted by:
Working days subtracted: 0
Percent change in Contract to date 19.25%
Cif Project Manager Date
Date Cit Manager, required for Change Orders 424,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Acce.ted and agreed to by PAL General Engineering, Inc.:
Name:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
4 CALIFORNIA -4,
NATIONAL CITY
' --tmcoaroaessD
8TH STREET SMART GROWTH REVITALIZATION CHANGE ORDER NO. 11, Attachment "A"
Specification #12-13
DATE: March 3, 2014
WORK PERFORMED BY: PAL General Engineering, Inc.
DESCRIPTION OF WORK: Remove driveway at 333 8th St.
LABOR, MATERIALS AND EQUIPMENT
Unit
Qty
Rate
Total
Remove driveway at 333 8th St.
LS
132.00
2.00
264.00
Markup (50/0):
TOTAL COST:
13.20
$ 277.20
twL et
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
PAL GENERAL ENGINEERING
Change Orders #8, #9, #10, #11
8th Street Smart Growth Revitalization
Spec. No. 12-13
Judy Hernandez (Engineering) Forwarded Copy of
Change Orders to PAL General Engineering