NATIONAL CITY AQUATIC CENTER CHANGE ORDER NO. 1
Specification # 13-04. January 16, 2014
Contractor: EC CONSTRUCTORS
Reason/Purpose for this Change Order:
There is currently no utility easement servicing the Aquatic Center site. An easement needs to be established for
electrical, gas and communications.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor's surveyor will provide all the services described in Exhibit
"A" and provide a meets and boundslega description of the easement to the satisfaction of the Port of San Diego
and San Diego Gas & Electric for the lump sum price of $5,087.
Original Contract Amount $ 3,524,896.00
Net change by previously authorized Change Orders
Subtotal 3,524,896.00
Amount of this change order 5,087.00
New contract amount $ 3,529,983.00
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 0.14%
Submitted by:
City Engineer
Resident Engineer Date
z-zl-/y
Date City Manager, required for Change Orders >$24 999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by EC CONSTRUCTORS, Inc.
Z f zo (i.
Name: I\ \ Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
c
CONSTR1LT4CT`ORSS Inc.
L2CtMffiSE aTO. ss64177
9834 River Street
Lakeside, CA 92040
Ph. (619) 440-7181
Fax (619) 440-7180
Project: National City Aquatics
Job No.: 209 - CP05
Date: 2/4/2014
CONTRACTOR'S CHANGE ORDER ESTIMATE
Scope of Change: Add'I Survey for SDG&E Easement
a) Material Cost (See Breakdown)
b) Labor Cost (See Breakdown)
c)Equipment Cost (See Breakdown)
d) Labor Burden
(Gen. Liability, Builders Risk, Work
Comp., Soc. Security, Unemployment)
e) Subtotal GC Work
f) GC Markup on Self Performed
labor
f) GC Markup on Self Performed
Material & Equipment
g) Subtotal
h) Subcontractor Costs
i) Subcontractor O/H & P
Included On Subs Quote Attached
i) Gen. Contractor's O/H & Profit
on subcontractors
j) Subtotal
k) Bond Premium crab at Project
Completion)
I) TOTAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$4,845.00
$0.00
$242.00
$5,087.00
$0.00
$5,087.00
In addition to the cost indicated above, the Contractor also requires 0 additional days added
to the contract completion date for implementation of this change order.
(See attached forjustificaton of time extension if required)
Kenny Kubia
209 - CP 005 Survey for SDG&E Easement
3441 Vista De La Cresta
Escondido
CA 92029
Voice: (760) 738-9636
Fax: (760) 738-8649
HOPWOOD LAND SURVEYING
SURVEYING PROPOSAL
NATIONAL CITY AQUATIC CENTER
Date: 1/28/14
SCOPE OR WORK
1. Research and calculations prior to and in preparation for field survey.
2. Establish survey control using Record of Surveys 17520, 16668 and 17055.
3. Locate SDG & E structures and lines from the intersection of West 32nd Street and
Goesno Place to the proposed National City Aquatic Center.
Location of the lines will be determined by utility mark out.
Only those structures visible and above ground will be included.
4. Tie the SDG & E structures and lines into NAD 83 first order control as shown on
Record of Surveys 16668 and 17055.
5. Attend 2 meeting to determine extent of the easement prior to the easement being
written.
6. Provide the body of the legal description for those structures and lines.
FEE:
$ 4,845
c)I NI, (I
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
EC CONSTRUCTORS
Change Order #1
National City Aquatic Center
Judy Hernandez (Engineering) Forwarded Copy
of Change Order to EC Constructors