HomeMy WebLinkAbout2014 CON PAL General Engineering - 8th Street Smart Growth Revitalization - Change Order #26 #27N
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering Inc.
Reason/Purpose for this Change Order:
!Unforeseen conditions have been discovered throughout the project for which change orders have been''.
previously issued to account the differences in costs and some changes have not required change orders. Many;
of these changes have increased the number working days required to complete the project. The City has alsol
=allowed street closures in both a singular and dual directions and allowed certain street sections to remain to!
reduce contract time. This change order addresses all contract time issues up to the date of its execution. All of
adjustments to line items
the cost issues have been addressed in previous change orders and in
The City of National City and Contractor agree to the following change to the original Contract:
,The City and the Contractor agree that all the the additive and deductive work, change conditions and unforseen
conditions up to the date this change order is executed have totalled to add 35 working days to the contract. The
City and the Contractor further agree that the project shall be substantially complete with all surface'
:improvements between Highland and National City Blvd. (NCB) by the end of that contract time. If the Contractor
'is not substantially complete with all those surface improvements within that contract time liquidated damages,
;shall be assessed in accordance with the Contract Documents until they are complete. The Contractor shall'
:have an additional 4 weeks to complete all landscaping, improvements West of NCB and punchlist items from(
the end of the new contract completion date. If the project is not wholly complete within 4 weeks (20 working',
'days) from the new completion date liquidated damages shall be assessed in accordance with the Contract,
Documents.
CHANGE ORDER NO. 26
September 23, 2014
Original Contract Amount $ 3,709,079.35
Net change by previously authorized Change Orders 909,840.13
Subtotal
Amount of this change order
4,618, 919.48
New contract amount $ 4,618,919.48
Working days added: 35
Submitted by:
Approved by:
Working days subtracted: 0
opmq
Date
(i(6/ f
CityrEngineer / Date ;Cif Manager, required for Change Orders>$24,999 Date £
Bysigning ChangeContractor this Order the confirms that it is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions Additionally, Contractor confirms that the price and time stated herein represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, contract time, etc. and that there will be no further compensation. All of the terms and conditions of
the original Contract Documents are incorporated herein. Contractor further releases the City and its consultants and each
of their elected officials, officers, agents, employees, volunteers, heirs and assigns from any claim whatsoever that relates in
any way to the matters addressed herein whether known or unknown at the time of the Change Order and specifically waives
any claims under Section 1542 of the California Civil Code which states: "A general release does not extend to claims which
the creditor does not know or suspect to exist in his or her favor at the time of executing the release, which if known by him
or her must have materially affected his or her settlement with the debtor."
ted and agreed to PAL General Engineering, Inc.:
Percent change in Contract to date 24.53%
City Project Manager
ame: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA -
NATI®1 11L C Ty
- I=VCOR.OR1T1O
8TH STREET SMART GROWTH REVITALIZATION
Specification #12-13
Contractor: PAL General Engineering, Inc.
CHANGE ORDER NO. 27
September 24, 2014
Reason/Purpose for this Change Order:
The Strongbox backflow enclosures SBBC-30SS did not fit over the backflow devices as designed and had to be
upgraded to the larger enclosures SBBC-45SS. The SBBC-30SS was specifically called out in the plans and was
an approved submittal.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall install the SBBC-45SS Strongbox Backflow
Enclosures. The agreed upon price for all costs associated with this work is as stated on this Change order. See
Attachment "A" for cost breakdown.
Original Contract Amount $ 3,709,079.35
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0ercent change in Contract to date 24.56%
Submitted by:
909,840.13
4,618,919.48
1,174.82
$ 4,620,094.30
Date Cit Project Mana er Date
Cit En.ineer Date
Cit Manager, required for Change orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
PAL General Engineering, Inc.:
7/26 ///
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORXM
NATIONAL CITE
atty
Ipcox...AT n
8TH STREET SMART GROWTH REVITALIZATION CHANGE ORDER NO. 27, Attachment "A"
Specification #12-13
DATE: September 24, 2014
WORK PERFORMED BY: PAL General Engineering, Inc.
DESCRIPTION OF WORK: Install SBBC-45SS StrongBox Backflow Enclosures
MATERIALS
Unit
QtY
Rate
Total
Install SBBC-45SS StrongBox Backflow Enclosures
EA
2.00
1,498.75
2,997.50
Credit for SBBC-305S StrongBox Backflow Enclosures
EA
2.00
(987.96)
(1,975.92)
Subtotal:
Materials Markup (150/0):
TOTAL COST:
$ 1,021.58
153.24
$ 1,174.82
PROJECT PROFESSIONALS CORPORATION'
TRANSMITTAL COVER
To: City of National City
Project Name: 8th Street Smart Growth
Spec No 12-13
ITEMS DELIVERED:
Change Orders #26,27.
Delivered by: ' Project Professionals Corporation
Received by:
Date: 1 0/� i 4k1
{qio G� kss gam _.
'RAd [II ?°
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
PAL GENERAL ENGINEERING
Change Order #26 and #27
8th Street Smart Growth Revitalization
Judy Hernandez (Engineering / Public Works) Forwarded
Copy of Change Orders to PAL General Engineering