HomeMy WebLinkAbout2014 CON PAL General Engineering - 8th Street Smart Growth Revitalization - Change Order #26 #27N 8TH STREET SMART GROWTH REVITALIZATION Specification #12-13 Contractor: PAL General Engineering Inc. Reason/Purpose for this Change Order: !Unforeseen conditions have been discovered throughout the project for which change orders have been''. previously issued to account the differences in costs and some changes have not required change orders. Many; of these changes have increased the number working days required to complete the project. The City has alsol =allowed street closures in both a singular and dual directions and allowed certain street sections to remain to! reduce contract time. This change order addresses all contract time issues up to the date of its execution. All of adjustments to line items the cost issues have been addressed in previous change orders and in The City of National City and Contractor agree to the following change to the original Contract: ,The City and the Contractor agree that all the the additive and deductive work, change conditions and unforseen conditions up to the date this change order is executed have totalled to add 35 working days to the contract. The City and the Contractor further agree that the project shall be substantially complete with all surface' :improvements between Highland and National City Blvd. (NCB) by the end of that contract time. If the Contractor 'is not substantially complete with all those surface improvements within that contract time liquidated damages, ;shall be assessed in accordance with the Contract Documents until they are complete. The Contractor shall' :have an additional 4 weeks to complete all landscaping, improvements West of NCB and punchlist items from( the end of the new contract completion date. If the project is not wholly complete within 4 weeks (20 working', 'days) from the new completion date liquidated damages shall be assessed in accordance with the Contract, Documents. CHANGE ORDER NO. 26 September 23, 2014 Original Contract Amount $ 3,709,079.35 Net change by previously authorized Change Orders 909,840.13 Subtotal Amount of this change order 4,618, 919.48 New contract amount $ 4,618,919.48 Working days added: 35 Submitted by: Approved by: Working days subtracted: 0 opmq Date (i(6/ f CityrEngineer / Date ;Cif Manager, required for Change Orders>$24,999 Date £ Bysigning ChangeContractor this Order the confirms that it is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions Additionally, Contractor confirms that the price and time stated herein represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, contract time, etc. and that there will be no further compensation. All of the terms and conditions of the original Contract Documents are incorporated herein. Contractor further releases the City and its consultants and each of their elected officials, officers, agents, employees, volunteers, heirs and assigns from any claim whatsoever that relates in any way to the matters addressed herein whether known or unknown at the time of the Change Order and specifically waives any claims under Section 1542 of the California Civil Code which states: "A general release does not extend to claims which the creditor does not know or suspect to exist in his or her favor at the time of executing the release, which if known by him or her must have materially affected his or her settlement with the debtor." ted and agreed to PAL General Engineering, Inc.: Percent change in Contract to date 24.53% City Project Manager ame: Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA - NATI®1 11L C Ty - I=VCOR.OR1T1O 8TH STREET SMART GROWTH REVITALIZATION Specification #12-13 Contractor: PAL General Engineering, Inc. CHANGE ORDER NO. 27 September 24, 2014 Reason/Purpose for this Change Order: The Strongbox backflow enclosures SBBC-30SS did not fit over the backflow devices as designed and had to be upgraded to the larger enclosures SBBC-45SS. The SBBC-30SS was specifically called out in the plans and was an approved submittal. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall install the SBBC-45SS Strongbox Backflow Enclosures. The agreed upon price for all costs associated with this work is as stated on this Change order. See Attachment "A" for cost breakdown. Original Contract Amount $ 3,709,079.35 Net change by previously authorized Change Orders Subtotal Amount of this change order New contract amount Working days added: 0 Working days subtracted: 0ercent change in Contract to date 24.56% Submitted by: 909,840.13 4,618,919.48 1,174.82 $ 4,620,094.30 Date Cit Project Mana er Date Cit En.ineer Date Cit Manager, required for Change orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. PAL General Engineering, Inc.: 7/26 /// Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CALIFORXM NATIONAL CITE atty Ipcox...AT n 8TH STREET SMART GROWTH REVITALIZATION CHANGE ORDER NO. 27, Attachment "A" Specification #12-13 DATE: September 24, 2014 WORK PERFORMED BY: PAL General Engineering, Inc. DESCRIPTION OF WORK: Install SBBC-45SS StrongBox Backflow Enclosures MATERIALS Unit QtY Rate Total Install SBBC-45SS StrongBox Backflow Enclosures EA 2.00 1,498.75 2,997.50 Credit for SBBC-305S StrongBox Backflow Enclosures EA 2.00 (987.96) (1,975.92) Subtotal: Materials Markup (150/0): TOTAL COST: $ 1,021.58 153.24 $ 1,174.82 PROJECT PROFESSIONALS CORPORATION' TRANSMITTAL COVER To: City of National City Project Name: 8th Street Smart Growth Spec No 12-13 ITEMS DELIVERED: Change Orders #26,27. Delivered by: ' Project Professionals Corporation Received by: Date: 1 0/� i 4k1 {qio G� kss gam _. 'RAd [II ?° CITY OF NATIONAL CITY Office of the City Clerk 1243 National City Blvd., National City, California 91950 619-336-4228 phone / 619-336-4229 fax Michael R. Dalla, CMC - City Clerk PAL GENERAL ENGINEERING Change Order #26 and #27 8th Street Smart Growth Revitalization Judy Hernandez (Engineering / Public Works) Forwarded Copy of Change Orders to PAL General Engineering