8TH STREET SAFETY ENHANCEMENTS PROJECT
Specification #12-15
Contractor: Ramona Paving and Construction Corp.
Reason/Purpose for this Change Order
Punchlist items were requested from Stack Traffic for the Traffic Signals at 8th Street and M Avenue and 8th
Street and Palm Avenue.
CHANGE ORDER NO. 27
February 4, 2015
The City of National City and Contractor agree to the following change to the original Contract:
From the working day statements it was calculated the punchlist items caused the contractor 31 working days
delay. The Contractor and the City agree that the Contractor shall recieve an additional 31 working days to the
contract.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 31 Working days subtracted: 0
$ 1,199,139.75
93,695.45
1,292,835.20
Percent change in Contract to date 7.81 %
1,292,835.20
Submitted by:
--.....
P Ma
7-1..1LIs............
Date
, 1
Resident Engineer
z-1 ./..15........
Date
>�
Approved by:
Ci ngineer
Zitrk
Date
City Manager, requreabrChange Orders >s24.ssa
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions Additionally, Contractor confirms that the price and time stated herein represents all costs associated with the
work, including but not fimited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, contract time, etc. and
that there will be no further compensation. All of the terms and conditions of the original Contract Documents are incorporated herein.
Contractor further releases the City and its consultants and each of their elected officials, officers, agents, employees, volunteers, heirs and
assigns from any claim whatsoever that relates in any way 10 the matters addressed herein whether known or unknown at the time of the
Change Order and specifically waives any claims under Section 1542 of the California Civil Code which states: "A general release does not
extend to claims which the creditor does not know or suspect to exist in his or her favor at the time of executing the release, which if known by
him or her must have materially affected his or her settlement with the debtor."
Ramona Paving and Construction Corp.:
1_ • \.
Date
Note b It you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
RAMONA PAVING AND CONSTRUCTION
Change Order #27
8th Street Safety Enhancements Project
Judy Hernandez (Engineering) Forwarded Copy of
Change Order to Ramona Paving and Construction