HomeMy WebLinkAbout2015 CON LB Civil Construction - "A" Avenue Green Street Improvements SP 14-05 - Change Orders #20+}- CALIFORNIA —,,
NATIONAL CITY
aacw
1VCORPORATED
A Avenue Green Street improvements
CIP No. 14-05
Contractor: L.B. Civil Construction
Reason/Purpose for this Change Order:
Paint existing bollards and lights to match existing per specifications.
CHANGE ORDER NO. 20
September 15, 2015
The City of National City and Contractor agree to the following change to the original Contract:
City directed the contractor to prepare and refinish 37 existing bollards and one existing light base to match
the new lights being installed in a two-part black epoxy paint per the contract specifications from 7th St. to
11th St. on A Ave. or as directed. Bollards will be paid per the unit cost of $100 each and light poles will be
paid at the unit cost of $400 each.
Original Contract Amount $ 2,841,105.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
221, 858.88
3,062,963.88
4,100.00
New contract amount $ 3,067,063.88
Working days added: Working days subtracted: 0 Percent change in Contract to date 7.95%
Submit cI by:
roved by:
2
City Engineer
Date City Project Manager
Date
�arh-r
Date City Manager, required for Change Orders '$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
J30 NA g' /4,45
Name: Date
Note to contractor: it you ao not agree witn tms cnange urger you may oe airectea to proceea witn tnis work unaer me terms or the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
L.B. CIVIL CONSTRUCTION
Change Order #20
"A" Avenue Green Street Improvements
Tirza Gonzales (Engineering) Forwarded
Copy of Change Order to L.B. Civil Construction