HomeMy WebLinkAbout2015 CON California Department of Transportation Calrtans - Safe Routes to Schools Ped EnhancementsAccounting Officer
Chapter
utes
PROGRAM SUPPLEMENT NO. N010
to
ADMINISTERING AGENCY -STATE AGREEMENT
FOR FEDERAL -AID PROJECTS NO 11-5066R
Adv Project ID Date: September 4, 2015
1115000089 Location: 11-SD-0-NATC
Project Number: ATPL-5066(025)
E.A. Number: .
Locode: 5066
This Program Supplement hereby adopts and incorporates the Administering Agency -State Agreement for Federal Aid
which was entered into between the Administering Agency and the State on 05/02/07 and is subject to all the terms and
conditions thereof. This Program Supplement is executed in accordance with Article I of the aforementioned Master
Agreement under authority of Resolution No. ,2Ql5-Ito approved by the Administering Agency onOC .69 acts
(See copy attached).
The Administering Agency further stipulates that as a condition to the payment by the State of any funds derived from
sources noted below obligated to this PROJECT, the Administering Agency accepts and will comply with the special
covenants or remarks set forth on the following pages.
PROJECT LOCATION:
National City at various locations.
TYPE OF WORK: National City SRTS Ped Enhancements LENGTH: 0.0(MILES)
Estimated Cost Federal Funds
Matching Funds
M3E2 $50,000.00
$50,000.00
LOCAL
$0.0
OTHER
$0.00
CITY OF NAT _ .c/ L CITY
By
Title
Date
Attest
Ron Morrison, Mayor
October 6, 2015
STATE OF CALIFORNIA
Department ofT�/rt 'or
.�l �1G�
Chief, Office of Project Implementation
Division of Local Assistance
Date /0
47
I hereby certify upon my pers. - .l knowle
AreViA
Item
Yea
t budgeted funds are available for this encumbrance:
Program
BC
Date
Category
r $50,000.00
Fund Source
AMOUNT
Program Supplement 11-5066R-N010- ISTEA Page 1 of 5
STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION
PROGRAM SUPPLMENT AND CERTIFICATION FORM
PSCF (REV. 01/2010)
TO: STATE CONTROLLER'S OFFICE
Claims Audits
3301 "C" Street, Rm 404
Sacramento, CA 95816
Page 1 of 1
DATE PREPARED:
9/8/2015
PROJECT NUMBER:
11115000089
REQUISITION NUMBER / CONTRACT NUMBER:
FROM
Department of Transportation
SUBJECT.
Encumbrance Document
VENDOR / LOCAL AGENCY.
CITY OF NATIONAL CITY
CONTRACT AMOUNT:
$50,000.00
PROCUREMENT TYPE:
Local Assistance
CHAPTER
25
STATUTES
'014
ITEM
2550-108-0890
YEAR
2014/2015
PEC / PECT
2030720100
COE/Category
2620/0000
AMOUNT
50,000.00
ADA NOtll For individuals with sensory disabilities, this document is available in alternate formats. For information, call (915) 654-6410 of TDD (916) -3880 or write
Records and Forms Management, 1120 N. Street, MS-89, Sacramento, CA 95814.
11 -SD-0-NATC
ATPL-5066(025)
09/04/2015
SPECIAL COVENANTS OR REMARKS
1.
A. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
B. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
C. Award information shall be submitted by the ADMINISTERING AGENCY to the
District Local Assistance Engineer immediately after project contract award and prior to
the submittal of the ADMINISTERING AGENCY'S first invoice for the construction
contract.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Attention is directed to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual.
D. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once
every six months commencing after the funds are encumbered for each phase by the
execution of this Project Program Supplement Agreement, or by STATE's approval of an
applicable Finance Letter. STATE reserves the right to suspend future
authorizations/obligations for Federal aid projects, or encumbrances for State funded
projects, as well as to suspend invoice payments for any on -going or future project by
ADMINISTERING AGENCY if PROJECT costs have not been invoiced by
ADMINISTERING AGENCY for a six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING AGENCY in accordance with the current Local
Assistance Procedures Manual.
E. Administering Agency shall not discriminate on the basis of race, religion, age,
disability, color, national origin, or sex in the award and performance of any Federal -
assisted contract or in the administration of its DBE Program Implementation Agreement.
The Administering Agency shall take all necessary and reasonable steps under 49 CFR
Part 26 to ensure nondiscrimination in the award and administration of Federal -assisted
contracts. The Administering Agency's DBE Implementation Agreement is incorporated
by reference in this Agreement. Implementation of the DBE Implementation Agreement,
including but not limited to timely reporting of DBE commitments and utilization, is a legal
Program Supplement 11-5066R-N010- ISTEA Page 2 of 5
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
obligation and failure to carry out its terms shall be treated as a violation of this
Agreement. Upon notification to the Administering Agency of its failure to carry out its
DBE Implementation Agreement, the State may impose sanctions as provided for under
49 CFR Part 26 and may, in appropriate cases, refer the matter for enforcement under 18
U.S.C. 1001 and/or the Program Fraud Civil Remedies Act of 1986 (31 U.S.C. 3801 et
seq.).
F. Any State and Federal funds that may have been encumbered for this project are
available for disbursement for limited periods of time. For each fund encumbrance the
limited period is from the start of the fiscal year that the specific fund was appropriated
within the State Budget Act to the applicable fund Reversion Date shown on the State
approved project finance letter. Per Government Code Section 16304, all project funds
not liquidated within these periods will revert unless an executed Cooperative Work
Agreement extending these dates is requested by the ADMINISTERING AGENCY and
approved by the California Department of Finance.
ADMINISTERING AGENCY should ensure that invoices are submitted to the District
Local Assistance Engineer at least 75 days prior to the applicable fund Reversion Date to
avoid the lapse of applicable funds. Pursuant to a directive from the State Controller's
Office and the Department of Finance; in order for payment to be made, the last date the
District Local Assistance Engineer can forward an invoice for payment to the
Department's Local Programs Accounting Office for reimbursable work for funds that are
going to revert at the end of a particular fiscal year is May 15th of the particular fiscal
year. Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement involving
applicable funds that is not received by the Department's Local Programs Accounting
Office at least 45 days prior to the applicable fixed fund Reversion Date will not be paid.
These unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on the applicable fund Reversion Date.
G. As a condition for receiving federal -aid highway funds for the PROJECT, the
Administering Agency certifies that NO members of the elected board, council, or other
key decision makers are on the Federal Government Exclusion List. Exclusions can be
found at www.sam.gov.
H. This PROJECT is programmed to receive Federal funding from the Active
Transportation Program (ATP). Funding may be provided under one or more
components. A component(s) specific fund allocation is required, in addition to other
requirements, before reimbursable work can occur for the component(s) identified. Each
allocation will be assigned an effective date and identify the amount of funds allocated per
component(s).
This PROGRAM SUPPLEMENT has been prepared to allow reimbursement of eligible
PROJECT expenditures for the component(s) allocated. The start of reimbursable
expenditures is restricted to the later of either 1) the effective date of the component
specific allocation or the effective date of the federal obligation of funds.
Program Supplement 11-5066R-N010- ISTEA Page 3 of 5
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
I. STATE and ADMINISTERING AGENCY agree that any additional funds made
available for new phase(s) of work by future Federal obligations will be encumbered on
this PROJECT by use of a Federal Highway Administration -approved "Authorization to
Proceed" notification and State Finance Letter. ADMINISTERING AGENCY also agrees
that Federal funds available for reimbursement will be limited to the amounts obligated by
the Federal Highway Administration and that STATE funds available for reimbursement
will be limited to the amounts allocated by the California Transportation Commission
and/or STATE.
J. Upon ADMINISTERING AGENCY request, the CTC and/or STATE may approve
supplementary allocations, time extensions, and fund transfers between components.
Funds transferred between allocated project components retain their original timely use of
funds deadlines, but an approved time extension will revise the timely use of funds criteria
for the component(s) and allocation(s) requested. Approved supplementary allocations,
time extensions, and fund transfers between components made after the execution of this
PROGRAM SUPPLEMENT will be documented and considered subject to the terms and
conditions thereof. Documentation will consist of a Federal Highway Administration -
approved "Authorization to Proceed" notification, a STATE approved Allocation Letter,
Fund Transfer Letter, Time Extension Letter, and Finance Letter, as appropriate.
K. This PROJECT will be administered in accordance with the applicable CTC STIP
guidelines and the Active Transportation Program guidelines as adopted or amended, the
Local Assistance Procedures Manual (LAPM), the Local Assistance Program Guidelines
(LAPG), and this PROGRAM SUPPLEMENT.
L. The submittal of invoices for PROJECT costs shall be in accordance with the above -
referenced publications and the following. The ADMINISTERING AGENCY shall invoice
STATE for environmental & permits, plans specifications & estimate, and right-of-way
costs no later than 180 days after the end of last eligible fiscal year of expenditure. For
construction costs, the ADMINISTERING AGENCY has 180 days after project completion
or contract acceptance, whichever occurs first, to make the final payment to the
contractor and prepare the final Report of Expenditures and final invoice, and submit to
STATE for verification and payment.
M. All obligations of STATE under the terms of this Agreement are subject to the
appropriation of resources by the Legislature and the encumbrance of funds under this
Agreement. Funding and reimbursement are available only upon the passage of the
State Budget Act containing these Federal funds.
N. This PROJECT is subject to the timely use of funds provisions enacted by the ATP
Guidelines, as adopted or amended, and by approved CTC and State procedures as
outlined below.
Funds allocated for the environmental & permits (E&P), plan specifications & estimate
(PS&E), and right-of-way components are available for expenditure until the end of the
second fiscal year following the year in which the funds were allocated.
Program Supplement 11-5066R-N010- ISTEA Page 4 of 5
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
Funds allocated for the construction component are subject to an award deadline and
contract completion deadline. ADMINISTERING AGENCY agrees to award the contract
within 6 months of the construction fund allocation and to complete and accept the
construction within 36 months of award.
O. By executing this PROGRAM SUPPLEMENT, ADMINISTERING AGENCY agrees to
comply with all reporting requirements in accordance with the Active Transportation
Program Guidelines, as adopted or amended.
Program Supplement 11-5066R-N010- ISTEA Page 5 of 5
RESOLUTION 2015 — 148
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE PROGRAM SUPPLEMENT
AGREEMENT NO. N010 WITH THE STATE OF CALIFORNIA DEPARTMENT OF
TRANSPORTATION FOR THE NATIONAL CITY SRTS PED ENHANCEMENTS
PROJECT TO ALLOW FOR REIMBURSEMENT OF UP TO $50,000 IN ELIGIBLE
PROJECT EXPENDITURES THROUGH THE FEDERAL ACTIVE
TRANSPORTATION PROGRAM, AND AUTHORIZING THE ESTABLISHMENT
OF FUND APPROPRIATIONS AND A CORRESPONDING REVENUE
BUDGET IN THE AMOUNT OF $50,000
WHEREAS, on September 27, 2014, the California Department of Transportation
(Caltrans) awarded a $350,000 Federal Active Transportation Program ("ATP") grant to the City
of National City for the National City SRTS Ped Enhancements Project; and
WHEREAS, the State allocated $50,000 for the Project Approval and
Environmental Documents ("PA&ED") phase, with the remaining balance for final design and
engineering, available pending completion of the PA&ED phase; and
WHEREAS, the project will address potential pedestrian barriers previously
identified during a walk audit by providing the following enhancements: high visibility
crosswalks, ADA accessible ramps with truncated domes, pedestrian crosswalk signs, and
sidewalk enhancements at key locations.
NOW, THEREFORE, BE IT RESOLED that the City Council of the City of
National City hereby authorizes the Mayor to execute Program Supplement Agreement No.
N010 to Administering Agency -State Master Agreement No. 11-5066R, as required, to allow for
reimbursement of eligible project expenditures through the Federal Active Transportation
Program.
BE IT FURTHER RESOLVED that the City Council authorizes the establishment
of appropriations and the corresponding revenue budget in the amount of $50,000.
ATTEST:
PASSED and ADOPTED this 6th day of October,
on Morrison, Mayor
PPROVED S TO FORM:
Micha-I R. Dalla, Cit Clerk
laudia Gac r ua ilva
City Attori\ey
Passed and adopted by the Council of the City of National City, California, on October
6, 2015 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
MICHAEL R. DALLA
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2015-148 of the City of National City, California, passed and
adopted by the Council of said City on October 6, 2015.
i/ a.
City CIrk of the City of tional City, California
By:
Deputy
DEPARTMENT OF TRANSPORTATION
DIVISION OF ACCOUNTING
LOCAL PROGRAM ACCOUNTING BRANCH
Attention: City of National City
FINANCE ITEMS
FINANCE LETTER
Date: 09/14/2015
Agency: 11-SD-0-NATC
Project No: ATPL-5066(025)
EA No:
PRO RATA OR TOTAL COST OF FEDERAL PART. FED. REIMB % FEDERAL LOCAL
LUMP SUM WORK COST
M3E2
Agency Preliminary Engineering
- PA/ED
Fed. Partic: 100.00%
Totals:
Lump Sum
$50,000.00 $50,000.00 100.00%
$50,000.00 $50,000.00 0.00%
$50,000.00
$50,000.00
$0.00
$o.00
This Finance Letter was created based on specific financial information provided by the responsible local agency. The following
encumbrance history is prepared by Local Assistance Accounting Office and is provided here for local agency's information and action.
Signature:
Title:
el-i\c‘),‘apat-
HQ Sr. Area Engineer
Remarks: Toll credit is used in lieu of local match.
ACCOUNTING INFORMATION
For questions regarding finance letter, contact:
Printed Name : Richard Ke
Telephone No: (916) 653-4797
ATPL-5066(025)
APPROP. ENCUMBRANCE APPROP EXPENDITURE ENCUMBRANCE REVERSION
ADV. PROJ. ID UNIT STATE PROG. FED/STATE AMOUNT YEAR AMOUNT BALANCE DATE
1115000089 15108F 2030720100 F $50,000.00 1415 $0.00 $50,000.00 06/30/20
Cooperative Work Agreement
APPROVED EXPIRATION
AMOUNT DATE
Page 1 of 1
ATTEST:
Michabl R. Dalla, Cit Clerk
RESOLUTION 2015 — 148
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE PROGRAM SUPPLEMENT
AGREEMENT NO. N010 WITH THE STATE OF CALIFORNIA DEPARTMENT OF
TRANSPORTATION FOR THE NATIONAL CITY SRTS PED ENHANCEMENTS
PROJECT TO ALLOW FOR REIMBURSEMENT OF UP TO $50,000 IN ELIGIBLE
PROJECT EXPENDITURES THROUGH THE FEDERAL ACTIVE
TRANSPORTATION PROGRAM, AND AUTHORIZING THE ESTABLISHMENT
OF FUND APPROPRIATIONS AND A CORRESPONDING REVENUE
BUDGET IN THE AMOUNT OF $50,000
WHEREAS, on September 27, 2014, the California Department of Transportation
(Caltrans) awarded a $350,000 Federal Active Transportation Program ("ATP") grant to the City
of National City for the National City SRTS Ped Enhancements Project; and
WHEREAS, the State allocated $50,000 for the Project Approval and
Environmental Documents ("PA&ED") phase, with the remaining balance for final design and
engineering, available pending completion of the PA&ED phase; and
WHEREAS, the project will address potential pedestrian barriers previously
identified during a walk audit by providing the following enhancements: high visibility
crosswalks, ADA accessible ramps with truncated domes, pedestrian crosswalk signs, and
sidewalk enhancements at key locations.
NOW, THEREFORE, BE IT RESOLED that the City Council of the City of
National City hereby authorizes the Mayor to execute Program Supplement Agreement No.
N010 to Administering Agency -State Master Agreement No. 11-5066R, as required, to allow for
reimbursement of eligible project expenditures through the Federal Active Transportation
Program.
BE IT FURTHER RESOLVED that the City Council authorizes the establishment
of appropriations and the corresponding revenue budget in the amount of $50,000.
PASSED and ADOPTED this 6th day of October,
on Morrison, Mayor
PPROVED S TO FORM:
laudia Gac ua ilva
City Attor'ey
Passed and adopted by the Council of the City of National City, California, on October
6, 2015 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
I AY .A
City Jerk of the City of ational City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2015-148 of the City of National City, California, passed and
adopted by the Council of said City on October 6, 2015.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA a 0%
COUNCIL AGENDA STATEMENT
MEETING DATE: October 6, 2015
AGENDA ITEM NO. 12
ITEM TITLE:
Resolution of the City Council of the City of National City authorizing, 1) the Mayor to execute Program
Supplement Agreement No. NO10 with the State of California Department of Transportation for the National City
SRTS Ped Enhancements Project to allow for reimbursement of up to $50,000 in eligible project expenditures
through the Federal Active Transportation Program (ATP), and; 2) the appropriation of $50,000 for the project
PREPARED BY: Stephen Manganiello
PHONE: (619) 336-4382
EXPLANATION:
See attached.
DEPARTME Engineering & Public Works
APPROVED BY:
FINANCIAL STATEMENT:
ACCOUNT
Revenue Account No. 323-00000-3498
Expenditure Account No. 323-409-500-598-6166 (Safe Routes to School)
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED: /r Finance
APPROVED: MIS
STAFF RECOMMENDATION:
Adopt the Resolution
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Program Supplemental Agreement
3. Resolution
��C.sU1,Vt10t, !30• got5 -\`k%
Explanation
On September 27, 2014, the California Department of Transportation (Caltrans)
awarded a $350,000 Federal Active Transportation Program (ATP) grant for the
National City SRTS Ped Enhancements Project. The State has allocated $50,000 for
the Project Approval and Environmental Documents (PA&ED) phase. On August 21,
2015, Caltrans issued an Authorization to Proceed to the City for the PA&ED phase,
establishing the date for eligible reimbursement. The remaining balance, which will be
used for final design / engineering, will be available pending completion of the PA&ED
phase. Staff is pursuing grant opportunities to fund project construction. There is no
local match requirement.
The potential improvements will be based on barriers identified during a series of
comprehensive Walk Audits as part of the City's SMART Foundation Plan. Pedestrian
barriers identified during the walk audit include: lifted sidewalks, utility poles within
sidewalks/pedestrian curb ramps, substandard pedestrian curb ramps, and a lack of
crosswalks, pedestrian ramps, signage and signals. The project will address these
barriers by providing the following enhancements: high visibility crosswalks, ADA
accessible ramps with truncated domes, pedestrian crosswalk signs and sidewalk
enhancements at key locations.
Staff recommends authorizing the Mayor to execute Program Supplement Agreement
No. N010 to Administering Agency -State Master Agreement No. 11-5066R, as required
to allow for reimbursement of eligible project expenditures through the Federal ATP.
Staff also recommends appropriation of $50,000 to corresponding expenditure account
for Safe Routes to School.
PROGRAM SUPPLEMENT NO. N010
to
ADMINISTERING AGENCY -STATE AGREEMENT
FOR FEDERAL -AID PROJECTS NO 11-5066R
Adv Project ID Date:
1115000089 Location:
Project Number:
E.A. Number:
Locode:
September 4, 2015
11-SD-0-NATC
ATPL-5066(025)
5066
This Program Supplement hereby adopts and incorporates the Administering Agency -State Agreement for Federal Aid
which was entered into between the Administering Agency and the State on 05/02/07 and is subject to all the terms and
conditions thereof. This Program Supplement is executed in accordance with Article I of the aforementioned Master
Agreement under authority of Resolution No. approved by the Administering Agency on
(See copy attached).
The Administering Agency further stipulates that as a condition to the payment by the State of any funds derived from
sources noted below obligated to this PROJECT, the Administering Agency accepts and will comply with the special
covenants or remarks set forth on the following pages.
PROJECT LOCATION:
National City at various locations.
TYPE OF WORK: National City SRTS Ped Enhancements
LENGTH: 0.0(MILES)
Estimated Cost
Federal Funds
Matching Funds
M3E2 $50,000.00
$50,000.00
LOCAL
$0.00
OTHER
$0.00
CITY OF NATIONAL CITY J
By
Title
Date
Attest
Ron Morrison, Mayor
October 6, 2015
I hereby certify upon my pe ,. - -1 knowle,
Accounting Officer
Chapter
utes
Item
Yea
STATE OF CALIFORNIA
Department of Transportation
By
Chief, Office of Project Implementation
Division of Local Assistance
Date
t budgeted funds are available for this encumbrance:
Program
BC
Date
Category
Fund Source
$50,000.00
AMOUNT
Program Supplement 11-5066R-N010- ISTEA Page 1 of 5
-2-
STATE OF CALIFORNIA. DEPARTMENT OF TRANSPORTATION
PROGRAM SUPPLMENT AND CERTIFICATION FORM
PSCF (REV. 01/2010)
TO: STATE CONTROLLER'S OFFICE
Claims Audits
3301 "C" Street, Rm 404
Sacramento, CA 95816
FROM:
Department of Transportation
Page 1 of 1
DATE PREPARED:
9/8/2015
PROJECT NUMBER:
11115000089
REQUISITION NUMBER / CONTRACT NUMBER:
RQS 111600000093
SUBJECT:
Encumbrance Document
VENDOR/LOCAL AGENCY:
CITY OF NATIONAL CITY
CONTRACT AMOUNT:
$50,000.00
PROCUREMENT TYPE:
Local Assistance
CHAPTER STATUTES ITEM YEAR PEC / PECT COE/Category AMOUNT
2"5 2014 2660-108-0890 2014/2015 2030720100 2620/0000 50,000.00
ADA Notil For individuals with sensory disabilities, this documen is available in alternate formats. For information, call (915) 654-6410 of TDD (916) -3880 or write
Records and Forms Management, 1120 N. Street, MS-89, Sacramento, CA 95814.
-3-
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
1. A. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
B. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
C. Award information shall be submitted by the ADMINISTERING AGENCY to the
District Local Assistance Engineer immediately after project contract award and prior to
the submittal of the ADMINISTERING AGENCY'S first invoice for the construction
contract.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Attention is directed to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual.
D. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once
every six months commencing after the funds are encumbered for each phase by the
execution of this Project Program Supplement Agreement, or by STATE's approval of an
applicable Finance Letter. STATE reserves the right to suspend future
authorizations/obligations for Federal aid projects, or encumbrances for State funded
projects, as well as to suspend invoice payments for any on -going or future project by
ADMINISTERING AGENCY if PROJECT costs have not been invoiced by
ADMINISTERING AGENCY for a six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING' AGENCY in accordance with the current Local
Assistance Procedures Manual.
E. Administering Agency shall not discriminate on the basis of race, religion, age,
disability, color, national origin, or sex in the award and performance of any Federal -
assisted contract or in the administration of its DBE Program Implementation Agreement.
The Administering Agency shall take all necessary and reasonable steps under 49 CFR -
Part 26 to ensure nondiscrimination in the award and administration of Federal -assisted
contracts. The Administering Agency's DBE Implementation Agreement is incorporated
by reference in this Agreement. Implementation of the DBE Implementation Agreement,
including but not limited to timely reporting of DBE commitments and utilization, is a legal
Program Supplement 11-5066R-N010- ISTEA
Page 2 of 5
-4-
11-SD-O-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
obligation and failure to carry out its terms shall be treated as a violation of this
Agreement. Upon notification to the Administering Agency of its failure to carry out its
DBE Implementation Agreement, the State may impose sanctions as provided for under
49 CFR Part 26 and may, in appropriate cases, refer the matter for enforcement under 18
U.S.C. 1001 and/or the Program Fraud Civil Remedies Act of 1986 (31 U.S.C. 3801 et
seq.).
F. Any State and Federal funds that may have been encumbered for this project are
available for disbursement for limited periods of time. For each fund encumbrance the
limited period is from the start of the fiscal year that the specific fund was appropriated
within the State Budget Act to the applicable fund Reversion Date shown on the State
approved project finance letter. Per Government Code Section 16304, all project funds
not liquidated within these periods will revert unless an executed Cooperative Work
Agreement extending these dates is requested by the ADMINISTERING AGENCY and
approved by the California Department of Finance.
ADMINISTERING AGENCY should ensure that invoices are submitted to the District
Local Assistance Engineer at least 75 days prior to the applicable fund Reversion Date to
avoid the lapse of applicable funds. Pursuant to a directive from the State Controller's
Office and the Department of Finance; in order for payment to be made, the last date the
District Local Assistance Engineer can forward an invoice - for payment to the
Department's Local Programs Accounting Office for reimbursable work for funds that are
going to revert at the end of a particular fiscal year is May 15th of the particular fiscal
year. Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement involving
applicable funds that is not received by the Department's Local Programs Accounting
Office at least 45 days prior to the applicable fixed fund Reversion Date will not be paid.
These unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on the applicable fund Reversion Date.
G. As a condition for receiving federal -aid highway funds for the PROJECT, the
Administering Agency certifies that NO members of the elected board, council, or other
key decision makers are on the Federal Government Exclusion List. Exclusions can be
found at www.sam.gov.
H. This PROJECT is programmed to receive Federal funding from the Active
Transportation Program (ATP). Funding may be provided under one or more
components. A component(s) specific fund allocation is required, in addition to other
requirements, before reimbursable work can occur for the component(s) identified. Each
allocation will be assigned an effective date and identify the amount of funds allocated per
component(s).
This PROGRAM SUPPLEMENT has been prepared to allow reimbursement of eligible
PROJECT expenditures for the component(s) allocated. The start of reimbursable
expenditures is restricted to the later of either 1) the effective date of the component
specific allocation or the effective date of the federal obligation of funds.
Program Supplement 11-5066R-N010- ISTEA Page 3 of 5
-5-
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
I. STATE and ADMINISTERING AGENCY agree that any additional funds made
available for new phase(s) of work by future Federal obligations will be encumbered on
this PROJECT by use of a Federal Highway Administration -approved "Authorization to
Proceed" notification and State Finance Letter. ADMINISTERING AGENCY also agrees
that Federal funds available for reimbursement will be limited to the amounts obligated by
the Federal Highway Administration and that STATE funds available for reimbursement
will be limited to the amounts allocated by the California Transportation Commission
and/or STATE.
J. Upon ADMINISTERING AGENCY request, the CTC and/or STATE may approve
supplementary allocations, time extensions, and fund transfers between components.
Funds transferred between allocated project components retain their original timely use of
funds deadlines, but an approved time extension will revise the timely use of funds criteria
for the component(s) and allocation(s) requested. Approved supplementary allocations,
time extensions, and fund transfers between components made after the execution of this
PROGRAM SUPPLEMENT will be documented and considered subject to the terms and
conditions thereof. Documentation will consist of a Federal Highway Administration -
approved "Authorization to Proceed" notification, a STATE approved Allocation Letter,
Fund Transfer Letter, Time Extension Letter, and Finance Letter, as appropriate.
K. This PROJECT will be administered in accordance with the applicable CTC STIP
guidelines and the Active Transportation Program guidelines as adopted or amended, the
Local Assistance Procedures Manual (LAPM), the Local Assistance Program Guidelines
(LAPG),- and this PROGRAM SUPPLEMENT.
L. The submittal of invoices for PROJECT costs shall be in accordance with the above -
referenced publications and the following. The ADMINISTERING AGENCY shall invoice
STATE for environmental & permits, plans specifications & estimate, and right-of-way
costs no later than 180 days after the end of last eligible fiscal year of expenditure. For
construction costs, the ADMINISTERING AGENCY has 180 days after project completion
or contract acceptance, whichever occurs first, to make the final payment to the
contractor and prepare the final Report of Expenditures and final invoice, and submit to
STATE for verification and payment.
M. All obligations of STATE under the terms of this Agreement are subject to the.
appropriation of resources by the Legislature and the encumbrance of funds under this
Agreement. Funding and reimbursement are available only upon the passage of the
State Budget Act containing these Federal funds.
N. This PROJECT is subject to the timely use of funds provisions enacted by the ATP
Guidelines, as adopted or amended, and by approved CTC and State procedures as
outlined below.
Funds allocated for the environmental. & permits (E&P), plan specifications & estimate
(PS&E), and right-of-way components are available for expenditure until the end of the
second fiscal year following the year in which the funds were allocated.
Program Supplement 11-5066R-N010- ISTEA Page 4 of 5
-6-
11-SD-0-NATC
ATPL-5066(025)
SPECIAL COVENANTS OR REMARKS
09/04/2015
Funds allocated for the construction component are subject to an award deadline and
contract completion deadline. ADMINISTERING AGENCY agrees to award the contract
within 6 months of the construction fund allocation and to complete and accept the
construction within 36 months of award.
O. By executing this PROGRAM SUPPLEMENT, ADMINISTERING AGENCY agrees to
comply with all reporting requirements in accordance with the Active Transportation
Program Guidelines, as adopted or amended.
Program Supplement 11-5066R-N010- ISTEA Page 5 of 5
-7-
DEPARTMENT OF TRANSPORTATION
DIVISION OF ACCOUNTING
LOCAL PROGRAM ACCOUNTING BRANCH
Attention: City of National City
FINANCE LETTER
Date: 09/14/2015
Agency: 11-SD-0-NATC
Project No: ATPL-5066(025)
EA No:
FINANCE ITEMS
Agency Preliminary Engineering
- PA/ED
Fed. Partic: 100.00%
Totals:
PRO RATA OR TOTAL COST OF FEDERAL PART. FED. REIMB % FEDERAL LOCAL
LUMP SUM WORK COST
Lump Sum
$50,000.00
$50,000.00
100.00%
M3E2
$50,000.00
$0.00
550,000.00 $50,000.00 0.00% $50,000.0 mod
This Finance Letter was created based on specific financial information provided by the responsible local agency. The following
encumbrance history is prepared by Local Assistance Accounting Office and is provided here for local agency's information and action.
Signature: c"),,k4a7421/___,,
Title: HQ Sr. Area Engineer
Remarks: Toll credit is used in lieu of local match.
For questions regarding finance letter, contact:
Printed Name : Richard Ke
Telephone No: (916) 653-4797
ACCOUNTING INFORMATION
ATPL-5066(025)
APPROP. ENCUMBRANCE APPROP EXPENDITURE ENCUMBRANCE REVERSION
ADV. PROJ. ID UNIT STATE PROG. FED/STATE AMOUNT YEAR AMOUNT BALANCE DATE
Cooperative Work Agreement
APPROVED EXPIRATION I
AMOUNT DATE
1115000089 15108F 2030720100 F $50,000.00 1415 $0.00 650,000.00 06/30/20
Page 1 of 1
RESOLUTION 2015 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
AUTHORIZING THE MAYOR TO EXECUTE PROGRAM SUPPLEMENT
AGREEMENT NO. N010 WITH THE STATE OF CALIFORNIA DEPARTMENT OF
TRANSPORTATION FOR THE NATIONAL CITY SRTS PED ENHANCEMENTS
PROJECT TO ALLOW FOR REIMBURSEMENT OF UP TO $50,000 IN ELIGIBLE
PROJECT EXPENDITURES THROUGH THE FEDERAL ACTIVE
TRANSPORTATION PROGRAM, AND AUTHORIZING THE ESTABLISHMENT
OF FUND APPROPRIATIONS AND A CORRESPONDING REVENUE
BUDGET IN THE AMOUNT OF $50,000
WHEREAS, on September 27, 2014, the California Department of Transportation
(Caltrans) awarded a $350,000 Federal Active Transportation Program ("ATP") grant to the City
of National City for the National City SRTS Ped Enhancements Project; and
WHEREAS, the State allocated $50,000 for the Project Approval and
Environmental Documents ("PA&ED") phase, with the remaining balance for final design and
engineering, available pending completion of the PA&ED phase; and
WHEREAS, the project will address potential pedestrian barriers previously
identified during a walk audit by providing the following enhancements: high visibility
crosswalks, ADA accessible ramps with truncated domes, pedestrian crosswalk signs, and
sidewalk enhancements at key locations.
NOW, THEREFORE, BE IT RESOLED that the City Council of the City of
National City hereby authorizes the Mayor to execute Program Supplement Agreement No.
N010 to Administering Agency -State Master Agreement No. 11-5066R, as required, to allow for
reimbursement of eligible project expenditures through the Federal Active Transportation
Program.
BE IT FURTHER RESOLVED that the City Council authorizes the establishment
of appropriations and the corresponding revenue budget in the amount of $50,000.
PASSED and ADOPTED this 6th day of October, 2015.
Ron Morrison, Mayor
ATTEST: APPROVED AS TO FORM:
Michael R. Dalla, City Clerk Claudia Gacitua Silva
City Attorney
STATE OF CALIFORNIA - CALIFORNIA STATE TRANSPORTATION AGENCY EDMUND G. BROWN Jr., Governor
DEPARTMENT OF TRANSPORTATION
Division of Local Assistance
1120 N STREET
P.O. BOX 942874, MS# 1
Sacramento, CA 94274-0001
TTY 711
(916) 654-3883
Fax (916) 654-2408
November 3, 2015
Mr. Stephen Manganiello
Director of Public Works
City of National City
1243 National City Boulevard
National City, CA 91950-4301
Attn: Kuna Muthusamy
Dear Mr. Manganiello:
File : 11-SD-O-NATC
ATPL-5066(025)
National City at various locations.
Enclosed is your fully executed copy of Program Supplement Agreement No. 010-N to Administering Agency -State
Agreement No. 11-5066R.
Sincerely,
JOHN HOOLE, Chief
Office of Project Implementation - South
Division of Local Assistance
Enclosure
c: DLA AE Project Files
(11) DLAE - Erwin Gojuangco