October 28, 2015
Reason/Purpose for this Change Order:
The original war memorial design did not account for refurbishing existing flag poles and large offsets and
fabricating new small offsets. With redoing the entire memorial wall the City did not want to place old products
onto a new wall. The limits of the tile were also extended to the walls adjacent to the war memorial. The
Contractor shall proceed with refurbishing (3) flag poles and (3) large offsets, fabricate (12) small offsets and
extend the limits of the tile to the wall adjacent of the war memorial.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the above mentioned work. The agreed
upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost
breakdown.
Original Contract Amount $ 1,495,889.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
18,107.34
1,513,996.34
20,448.75
Percent change in Contract to date 2.58%
1,534,445.09
Submitted by:
/;
•Proect Ma
10/emirs
er Date
Approved by:
ity Engin er
112
a
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Not Century Construction, Inc.:
ZF
Name: f Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Telephone (619) 336-4380
1243 National City Boulevard, National City, CA 91950
CALIFORNIA
NATIONAL C.137
�ye o t/
INC,ORpORATE])
D AVENUE AND E 12TH STREET ROUND -A -BOUT CHANGE ORDER NO. 5
Specification #15-02
DATE: August 7, 2015
WORK PERFORMED BY: Restoration Artechs
DESCRIPTION OF WORK: Refurbish large offsets and flag poles, fabricate small offsets
extend limits of tile to adjacent walls
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LUMP SUM
Unit
Qty
Rate
Total
1)
2)
3)
4)
Refurbish (3) large offsets
Refurbish (3) Flag Poles
Fabricate (12) small offsets
Extend limits of tile to walls
adjacent to war memorial
LS
LS
LS
LS
1.00
1.00
1.00
1.00
1,500.00
5,775.00
7,620.00
4,580.00
1,500.00
5,775.00
7,620.00
4,580.00
$ 19,475.00
Sub -Total:
Prime Contractor Markup (5%):
GRAND TOTAL:
$ 973.75
$ 20,448.75
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: City of National City
Project Name: D Avenue and E 12' Street Roundabout Improvements
Spec No 15-02
ITEMS DELIVERED:
Change Order #5.
Delivered by:941-1Project Professionals Corporation
Received by:
Date: 1vMdc
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
NEW CENTURY CONSTRUCTION
Change Order #5
"D" Avenue & East 12th Street Roundabout
Judy Hernandez (Engineering/Public Works) Forwarded