CHANGE ORDER NO. 1
February 3, 2016
Reason/Purpose for this Change Order.
The owner asked Kinsman Construction to remove dirt from additional planter boxes around the building. The
owner also requested the use of a special inspector to witnes and certify the anchor bolts being installed for the
shelving system.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will provide all the services described in Exhibit "A" for the
lump sum price of $7,148.
Original Contract Amount $ 768,463.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
768,463.00
7,148.00
Percent change in Contract to date 0.93%
775,611.00
itte
2/311
'0
Resident En ineeV6� r 1 Date
r Date
Project Project Manager
Approved by: i
2 71r11/4
Cit nqineer Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
Name:
co
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #12-13
NATI
Il y1
ZNCORPORAT$D
CHANGE ORDER NO. 1, Attachment "A"
DATE: February 3, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: Excavate planter boxes, special inspector
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Remove soil from additional planters
$ 6,550.00
2
Provide special inspector for anchor bolts
$ 598.00
TOTAL
$ 7,148.00
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
Contractor: KINSMAN CONSTRUCTION, INC.
CHANGE ORDER NO. 2
February 23, 2016
Reason/Purpose for this Change Order:
Due to a lack of space available to temporarily store evidence, the City approved the use of a 40 foot shipping
container to accommodate additional storage. Additionally, the City requested a proposal to reconfigure office
partitions on the third floor and to provide additional partitions.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will provide all the services described in Exhibit "A" for the
lump sum price of $14,367.20
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
768,463.00
7,148.00
775,611.00
14,367.20
Percent change in Contract to date 2.80%
789,978.20
s3ulr itt y:
Project Manager
Date
Resident Engineer
Date
Approved by:
�, ....
Cit ngineer
til!�
t fig
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
teAttg,j
Da
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
CALIFORNIA
NATIONAL Cjitiv
a nnl
INCORPORATES
CHANGE ORDER NO. 2, Attachment "A"
DATE: February 23, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: Storage Container, Office Partitions
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Storage container
$ 754.20
2
3rd Floor Office Partitions
$ 13,613.00
TOTAL
$ 14,367.20
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
003
PHONE:
858-634-8180
DATE:
02/14/16
JOB NAME:
National City Police Department
LOCATION:
1200 National City Blvd
JOB NUMBER:
S5-029
FAX.
858-634-8184
CONTRACT NUMBER:
Change Order Request #003
Item No. Description Amount
1. Systems furniture restructure on 3rd floor to include new system
at office and new panels in open area $7,854.00
2. Supply plastic moving bins $445.00
3. Moving of office furniture and equipment $3,038.00
4. Relocate power circuit through new furniture chase $500.00
5. OH&P @ 15% $1,776.00
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$13,613.00
DATE
02/14/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
--�:.._ _� _ _
.,-2
AUTHORIZED SIGNATURE (CONTRACTOR)
INCREASE CONTRACT AMOUNT BY:
$13,613.00
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-2950
CONTRACTORS LICENSE: CA #955119
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
004
PHONE:
858-634-8180
DATE.:
02/11/16
JOB NAME:
National City Police Department
LOCATION
1200 National City Blud
JOB NUMBER:
S5-029
FAX.
858-634-8184
CONTRACT NUMBER.:
Change Order Request #004
Item No. Description Amount
1. Steel storage container to hold overflow of evidence from Homicide area.
for the term of 2 months $198.00
2. Delivery and return trucking onetime fee $198.00
3. Lighted barracades rental $234.00
4. OH&P @ 15% $124.20
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$754.20
DATE
02/11/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
. _ __
INCREASE CONTRACT AMOUNT BY:
$754.20
AUTHORIZED SIGNATURE (CONTRACTOR)
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-2950
CONTRACTORS LICENSE: CA #955119
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
Contractor: KINSMAN CONSTRUCTION, INC.
CHANGE ORDER NO. 3
March 1, 2016
Reason/Purpose for this Change Order:
As a result of further investigations by the waterproofing consultant, David Reed, the curtain wall injection called
out as Additive Bid item 4 is not deemed necessary and is deleted by this change order.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will delete all the services described in Additive Bid Item 4
for the reduction in contract price of $22,471.00
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
768,463.00
21,515.20
789,978.20
(22,471.00)
New contract amount $
Working days added: 0
Working days subtracted: 0
Percent change in Contract to date -0.12%
767,507.20
r
Project anager
•
•3/Z140
Date
Resident Engineer
Date
Approved by:
bo` N. ,
ty Engin er
3'/2/I .o
Dat
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
Name:
201,
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
- CALIFORNIA —
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
NATIONAL Glory
vim
`NCORPORATE
CHANGE ORDER NO. 3, Attachment "A"
DATE: March 1, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: Storage Container, Office Partitions
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Delete Additive Bid Item 4
$ (22,471.00)
TOTAL
$ (22,471.00)
�-^ CALIFORNIA
NATIONAL M
INCORPORATED
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
Contractor: KINSMAN CONSTRUCTION, INC.
Reason/Purpose for this Change Order:
It was determined that the proposed 6'6" doors will not work. New doors will need to be 7' tall. The City directed
the contractor to install 7' doors. Also, it was determined that an existing electrical panel did not have the proper
cover. A new panel will be required to meet code.
CHANGE ORDER NO. 4
March 9, 2016
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will provide all the services described in Attachment A for
the price of $8,060.55
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
$
768,463.00
(955.80)
767, 507.20
8,060.55
Percent change in Contract to date 0.92%
775,567.75
ubnlitted • ,.
rjI
j
ect annaa er
sf�//�
Date
Resident Engineer
Date
Approved by:
Cit n ineer
Date
City Manager, required for Change Orders >$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
z
Name:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA —0
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
NATIONAL CITY
`NCORPORATE
CHANGE ORDER NO. 4, Attachment "A"
DATE: March 9, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: New doors, electrical panel
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Provide 7' doors
$ 6,538.40
2
Provide new electrical panel
$ 1,522.15
TOTAL
$ 8,060.55
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
KINSMAN CONSTRUCTION
Change Orders #1, #2, #3, #4
Police Department Building Improvements
Judy Hernandez (Engineering/Public Works) Forwarded Copy of
Change Orders to Kinsman Construction