HomeMy WebLinkAbout2016 CON Kinsman Construction - Police Department Building Improvements - Change Order #7NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
Contractor: KINSMAN CONSTRUCTION, INC.
CHANGE ORDER NO. 7
April 25, 2016
Reason/Purpose for this Change Order:
The City requested additional waterproofing per David Reed's recommendations, added concrete bottoms to the
planters currently not in the contract with additional waterproofing and drainage.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will provide all the services described in Attachment A for
the price of $127,007.00 and as further described in change order request 10r.2 and 11 r.1, attached.
Original Contract Amount ... $ 768,463.00
26,115.82
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
794,578.82
127,007.00
New contract amount $
Working days added: 0 Working days subtracted: 0
Percent change in Contract to date 19.93%
921,585.82
,
d b�
` /2-gie
5/3/16
Mayor, Ron orrison
Date
Project Ma = • er
Date
Approved by:
City ngineer
Date
Date
Cit�er,requiredfor Change Orders >$24,999
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
Name:
}tot
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA -�
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
NATIONAL Ci
d 3``31
INCORPORATED
CHANGE ORDER NO. 7, Attachment "A"
DATE: April 25, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: New doors, electrical panel
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Provide additional waterproofing
$ 40,825.00
2
Provide concrete bottoms to planters, inlcuding waterproofing and drain
$ 86,182.00
TOTAL
$ 127,007.00
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
10r.2
PHONE:
858-634-8180
DATE:
04/25/16
JOB NAME:
National City Police Department
LOCATION..
1200 National City Blvd
JOB NUMBER:
S5-029
PAX
858-634-8184
CONTRACT NUMBER:
Change Order Request #010r.2
Item No. Description Amount
1. Add concrete slab at bottom of planters currently NOT in our contract
Discovery of bottomless planters after removal of soils per additional request $6,850.00
2. Additional waterproofing requirements per waterproofing consultant at new
Concrete bottoms/pads $61,000.00
3. Add drainage to planters $7,091.00
4. OH&P $11,241.00
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$86,182.00
DATE
04/25/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
INCREASE CONTRACT AMOUNT BY:
$86,182.00
�� ---' ,
AUTHORIZED SIGNATURE (CONTRACTOR)
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-
CONTRACTORS LICENSE: CA #955119
UMW cabfermia oal.nt WO.
PROJECT
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 1 Fax: 619-596-5867
469 Vernon Way, Et Cajon, CA 92020
www.calsealants.com
NATIONAL POLICE STATION EVIDENCE Room
CONTRACTOR KINNSMAN CONSTRUCTION
ARCHITECT
DAVID REED CONSULTING
PROJECT No. 15-053
ATTENTION GERARD SHULTZ
DATE 3/21/16
CONTRACT CHANGE ORDER REQUEST NO. 05R2
No.
Description
Extra
Credit
Days
Ext.
c
Z
la
Parking deck planters: Remove all (E) Bituthene membrane,
prep and install 120 mils of CIM 1000 waterproofing. 710 SF
$14,500.00
5
1b
Labor = $35.15 x 200 hrs
$ 7,030.00
lc
Materials (CIM Primer, CIM 1000, scrim, bonding agent)
$ 5,580.00
ld
OH&P (15%)
$ 1,890.00
r,
z
-o
a
2a
Parking deck planters, over new 120 mil waterproofing: Install
J-Drain drainage panel. 710 SF
$ 2,000.00
2
2b
Labor = $35.15 x 30 hrs
$ 1,054.50
2c
Materials (J-Drain drainage panel and 3M glue)
$ 685.00
2d
OH&P (15%)
$ 260.50
No. 2
3a
Building perimeter planters: Remove all (E) Bituthene
membrane (1,500 SF) and install term bar at concrete height,
prep and install 120 mils of CIM 1000 waterproofing. 1,975 SF
$39,500.00
12
3b
Labor = $35.15 x 500 hrs
$17,575.00
3c
Materials (CIM Primer, CIM 1000, scrim, bonding agent)
$16,773.00
3d
OH&P (15%)
$ 5,152.00
Add No. 2
4a
Parking deck planters, over new 120 mil waterproofing: Install
J-Drain drainage panel. 1,975 SF
$ 5,000.00
4
4b
Labor = $35.15 x 70 hrs
$ 2,460.50
4c
Materials (J-Drain drainage panel and 3M glue)
$ 1,888.00
4d
OH&P (15%)
$ 651.50
TOTAL CONTRACT CHANGE
$54,000.00
23
Execution of this change order represents a lump sum cost for the scope of services identified hereon unless noted otherwise.
CHANGE ORDER AGREEMENT
The undersigned hereby agrees to the above -described amendment of the contract.
David A. Felix
Printed Name of Authorized Representative (California Sealant Solutions, Inc. (CSSI))
Manager 3/21/16
Original Contract = $48,500.00
Approved Change Orders:
CO#01 = ($11,650.00)
Change Order Requests:
COR#01 = $2,350.00
COR#02R1— $3,568.00
COR#03 = ($11,650.00)
COR#04 = $2,500.00
COR#05R2 = $54,000.00
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 I Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
�_� �• wow, www.calsealants.com
SIGNATURE
TITLE DATE
Total Contract w/COs = $36,900.00
OTHER NOTES:
Printed Name of Authorized Representative (Contractor)
SIGNATURE TITLE DATE
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
11r.1
PHONE:
858-634-8180
DATE:
04/25/16
JOB NAME:
National City Police Department
LOCATION:
1200 National City Blvd
JOB NUMBER:
S5-029
PAX
858-634-8184
CONTRACT NUMBER:
Change Order Request #011 r.1
Item No. Description Amount
1. Added waterproofing scope per David Reed recommendations
see attached breakout
Included Item la $10,000.00
Included Item 2a $18,500.00
Included Item 3a $5,000.00
Included Item 6a $2,000.00
2. OH&P $5,325.00
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$40,825.00
DATE
04/25/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
,.Fri-. -,-� ,
-
AUTHORIZED SIGNATURE (CONTRACTOR)
INCREASE CONTRACT AMOUNT BY:
$40,825.00
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-2950
CONTRACTORS LICENSE: CA #955119
Lcssi
PROJECT
calibrnia nul,nt Wuhan
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 1 Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
www.calsealants.com
NATIONAL POLICE STATION EVIDENCE Room
CONTRACTOR KINSMAN CONSTRUCTION
ARCHITECT
DAVID REED CONSULTING
PROJECT No. 15-053
ATTENTION GERARDSHULTZ
DATE
CONTRACT CHANGE ORDER REQUEST NO. 06
3/30/16
No.
Description
Extra
Credit
Days
Ext.
c.,
o
la
Garage & Stairways: Remove efflorescence at garage walls & ceiling,
stairway CMU walls. Prosoco Light Duty Concrete Cleaner and Prosoco Vana
Trol may be utilized per Prosoco instructions. 500 SF
$10,000.00
6
1b
Labor = $35.15 x 150 hrs
$5,272.00
lc
Materials (Prosoco Vana Trol, Rags, Buckets, Etc.)
$3,425.00
ld
OH&P (15%)
$1,303.00
,,,
o
2a
Adjust grade around building perimeter & properly terminate below grade
waterproofing: Existing Bituthene Membrane and/or Miracote. Membrane C
is to be a minimum of 6 inches above grade. Lower drain board to six inches
below proper grade level. Repair & properly terminate waterproofing
membrane at grade level. Clean to remove any contamination to exposed
membrane surface. Lightly wire brush membrane, & clean with water. Apply
Miracote Universal Primer and Membrane C coating (grey) onto
waterproofing membrane to the sheet membrane extending from the
drainage board to at least six inches above grade. 990 SF
$18,500.00
12
2b
Labor = $35.15 x 120 hrs
$8,787.00
2c
Materials (J-Drain panel and 3M glue, Miracote Primer & Membrane C)
$7,300.00
2d
OH&P (15%)
$2,413.00
m
0
z
3a
Renovate pedestrian decks on East & West Second floor - Tremco
Vulkem 360NF/951NF. Waterproof under thresholds. Repair and re -coat
pedestrian deck coating and remove and replace adjacent urethane
sealant. 700 SF
$5,000.00
5
3b
Labor = $35.15 x 70 hrs
$2,460.00
3c
Materials (191 Primer, Vulkem 360/951NF)
$1,889.00
3d
OH&P (15%)
$651.00
a
0
z
4a
Parking deck coating renovation - Tremco Vulkem 360NF/951NF. Repair and
re -coat parking deck coating and remove and replace adjacent urethane
sealant. A test patch/mock-up to check for adhesion is required. Cut out all
caulking and re -caulk with Tremco Dymonic 100, 1,500 LF. Degrease entire
deck with Simple Green mixture and pressure washer. 3 mobilizations.
Restripe all parking stalls and lines. 33,500 SF
$167,500.00
20
4b
Labor = $35.15 x 1,500 hrs
$52,725.00
4c
Materials (Vulkem 191 primer, Vulkem 360/951NF, Squeegees, Rollers,
Consumables)
$93,000.00
4d
OH&P (15%)
$21,775.00
`^
o
z
5a
Parking deck coating renovation - Tremco Vulkem 360NF/951NF. Repair and
re -coat center concrete walkway island on parking deck. 1,000 SF
$5,000.00
3
5b
Labor = $35.15 x 70 hrs
$2,460.00
Sc
Materials (Vulkem 191 primer, Vulkem 360/951NF, Squeegees, Rollers,
Consumables)
$1,888.00
5d
OH&P (15%)
$652.00
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 I Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
•+_•••••••••••••+•• www.calsealants.com
d
z
6a
Mock up - Window system repair: Window wet seal & urethane sealant
replacement around window at break room window on South elevation
$2,000.00
2
6b
Labor = $35.15 x 16 hrs
$562.00
6c
Materials (GE 2000, backer rod, primer, tape, etc.)
$1,178.00
6d
OH&P (15%)
$260.00
TOTAL CONTRACT CHANGE
$208,000.00
48
Execution of this change order represents a lump sum cost for the scope of services identified hereon unless noted otherwise.
CHANGE ORDER AGREEMENT
The undersigned hereby agrees to the above -described amendment of the contract.
Original Contract = $48,500.00
Approved Change Orders:
CO#01= ($11,650.00)
Change Order Requests:
David A. Felix
Printed Name of Authorized Representative (California Sealant Solutions, Inc. (CSSI))
Manager 3/30/16
COR#01 = $2,350.00
CORIt02R1- $3,568.00
COR#03 = ($11,650.00)
COR#04 = $2,500.00
COR#05R2 = $54,000.00
COR#06 = $208,000.00
Total Contract w/COs = $36,900.00
SIGNATURE TITLE DATE
OTHER NOTES:
Printed Name of Authorized Representative (Contractor)
SIGNATURE TITLE DATE
RESOLUTION NO. 2016 — 59
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
INCREASING THE CONTRACT WITH KINSMAN CONSTRUCTION, INC.,
FOR THE NOT TO EXCEED AMOUNT OF $127,007.15 FOR THE POLICE
DEPARTMENT BUILDING IMPROVEMENTS PROJECT, AND AUTHORIZING
THE MAYOR TO EXECUTE CHANGE ORDER NO. 7 IN THE AMOUNT
OF $127,007.15 TO PROVIDE WATERPROOFING AROUND THE ENTIRE
GROUND FLOOR PERIMETER OF THE POLICE DEPARTMENT BUILDING,
PLANTER BOXES, AND TWO PEDESTRIAN DECKS ON THE SECOND FLOOR
WHEREAS, on September 15, 2015, City Council adopted Resolution No. 2015-
139 awarding a contract in the amount of $768,463 to Kinsman Construction, Inc., for the Police
Department Building Improvements Project, CIP No. 15-06; and
WHEREAS, the original contract in the not to exceed amount of $768,463
included electrical and mechanical upgrades to support expansion of the Police Department
Property and Evidence Room, Americans with Disabilities Act upgrades, fire suppression
system upgrades to both the Police Department server room and City Hall server room, heating,
ventilating and air conditioning upgrades to the Police Department sever room, and
waterproofing; and
WHEREAS, during the design phase, a waterproofing specialist was hired to
analyze the waterproofing requirements for the Property and Evidence room, as well as analyze
the remainder of the Police Department building; and
WHEREAS, given the extensive nature of the "building -wide" analysis, only the
recommendations associated with the Property and Evidence room were included in the original
contract, which included waterproofing specific walls, ceilings, cracks, and the planters directly
associated with water intrusion issues for the basement; and
WHEREAS, after contract award, staff continued working with the waterproofing
specialist to complete the analysis for the entire building perimeter where soil is in contact with
walls, the remaining planters surrounding the building, and the two pedestrian decks on the
second floor; and
WHEREAS, the project is currently on schedule with construction completion
estimated for the end of June 2016; and
WHEREAS, six change orders totaling $46,432.71 have been processed, which
is approximately 6% of the contract amount; and
WHEREAS, Kinsman Construction, Inc., has provided a change order proposal
in the not to exceed amount of $127,007, exceeding the original 25% contingency of
$192,115.75.15 to procure and install the waterproofing improvements for the remaining high
priority areas of the building per the waterproofing analysis.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby approves an increase to the contract with Kinsman Construction, Inc., in a
not to exceed amount of $127,007.15.
Resolution No. 2016 — 59
Page Two
BE IT FURTHER RESOLVED that the Mayor is authorized to execute
Change Order No. 7 in the amount of $127,007.15 to provide waterproofing around the entire
ground floor perimeter of the police department building, planter boxes, and two pedestrian
decks on the second floor.
PASSED and ADOPTED this 3rd day of May, 2016.
Ron Morrison, Mayor
ATTEST:
it N Gt-c�c-w
Micha R. Dalla, ity Jerk
PPROVED AS TO FM:
udia Ga itua Sil a
City Attrne,
Passed and adopted by the Council of the City of National City, California, on May 3,
2016 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY:
RON MORRISON
Mayor of the City of National City, California
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2016-59 of the City of National City, California, passed and adopted
by the Council of said City on May 3, 2016.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
MEETING DATE: May 3, 2016
AGENDA ITEM NO. 9
ITEM TITLE:
Resolution of the City Council of the City of National City, 1) increasing the contract with Kinsman
Construction, Inc. in the not to exceed amount of $127,007.15 for the Police Department Building
Improvements Project, CIP No. 15-06; and 2) authorizing the Mayor to execute Change Order No. 7 in the
amount of $127,007.15 to provide waterproofing around the entire ground floor perimeter of the Police
Department Building, planter boxes and the two pedestrian decks on the second floor.
PREPARED BY: Stephen Manganiello
PHONE: 336-4382
EXPLANATION:
See attached.
FINANCIAL STATEMENT:
ACCOUNT NO.
DEPARTMENT: Engineering & Public Works
APPROVED BY:
APPROVED:
APPROVED:
Expenditure Account: 001-409-500-598-1182 (Police Department Building Improvements) - $127,007.15
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
Finance
MIS
STAFF RECOMMENDATION:
Adopt the Resolution.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Change Order No. 7
3. Resolution
9,V3otA.)-1cN tso. (-4,0+G •5°I
EXPLANATON
On September 15, 2015, City Council adopted Resolution No. 2015-139
awarding a contract in the amount of $768,463 to Kinsman Construction, Inc. for
the Police Department Building Improvements Project, CIP No. 15-06. The
original contract amount included electrical and mechanical upgrades to support
expansion of the Police Department Property and Evidence Room, Americans
with Disabilities Act upgrades, fire suppression system upgrades to both the
Police Department server room and City Hall server room, heating, ventilating
and air conditioning upgrades to the Police Department sever room, and
waterproofing.
During the design phase, staff hired a waterproofing specialist to analyze the
waterproofing requirements for the Property and Evidence room, as well as
analyze the remainder of the Police Department Building. Given the extensive
nature of the "building -wide" analysis, only the recommendations associated with
the Property and Evidence room were included in the original contract. These
improvements include waterproofing specific walls, ceilings, cracks, and the
planters directly associated with water intrusion issues for the basement. After
contract award, staff continued working with the waterproofing specialist to
complete the analysis for the entire building perimeter where soil is in contact
with walls, the remaining planters surrounding the building, and the two
pedestrian decks on the second floor.
The project is currently on schedule with construction completion estimated for
the end of June 2016. To date, staff has executed six change orders totaling
$46,432.71, which is approximately 6% of the contract amount. Staff requested a
quote from the contractor to procure and install the waterproofing improvements
for the remaining high priority areas of the building per the waterproofing
analysis. The contractor's change order proposal is for $127,007.15. Staff has
reviewed the proposal and recommends executing the change order with
Kinsman Construction, Inc. as the amount is fair and reasonable, work can be
performed in a timely manner, and there is no competitive advantage to bidding
out this work.
Therefore, staff requests that City Council approve an increase to the contract
with Kinsman Construction, Inc. in a not to exceed amount of $127,007.15,
above and beyond the original 25% contingency of $192,115.75. Funds are
available in the Police Department Building Improvements expenditure account
number 001-409-500-598-1182 through previous City Council appropriations.
C, R Oi TV>
r
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
Contractor: KINSMAN CONSTRUCTION, INC.
CHANGE ORDER NO. 7
April 25, 2016
Reason/Purpose for this Change Order:
The City requested additional waterproofing per David Reed's recommendations, added concrete bottoms to the
planters currently not in the contract with additional waterproofing and drainage.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor will provide all the services described in Attachment A for
the price of $127,007.00 and as further described in change order request 10r.2 and 11 r.1, attached.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
768,463.00
26,115.82
794,578.82
127,007.00
Working days added: 0
Working days subtracted: 0
Percent change in Contract to date 19.93%
921, 585.82
S ► d
Project Ma
er
`1/24/6
Mayor, Ron Morrison Date
Date
Approved by:
City nglneer
Date
4
111*
Date
City anager, required for Change Orders >$24,999
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by KINSMAN CONSTRUCTION, Inc.
Name:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
-1-
Telephone (619) 336-4380
NATIONAL CITY POLICE DEPARTMENT UPGRADES
Specification #15-06
CHANGE ORDER NO. 7, Attachment "A"
DATE: April 25, 2016
WORK PERFORMED BY: KINSMAN CONSTRUCTION, INC
DESCRIPTION OF WORK: New doors, electrical panel
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1
Provide additional waterproofing
$ 40,825.00
2
Provide concrete bottoms to planters, inlcuding waterproofing and drain
$ 86,182.00
TOTAL
$ 127,007.00
-2-
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
10r.2`
PHONE:
858-634-8180
DATE:
04/25/16
JOB NAME:
National City Police Department
LOCATION:
1200 National City Blvd
JOB NUMBER:
S5-029
FAX.
858-634-8184
CONTRACT NUMBER:
Change Order Request #010r.2
Item No. Description Amount
1. Add concrete slab at bottom of planters currently NOT in our contract
Discovery of bottomless planters after removal of soils per additional request $6,850.00
2. Additional waterproofing requirements per waterproofing consultant at new
Concrete bottoms/pads $61,000.00
3. Add drainage to planters $7,091.00
4. OH&P $11,241.00
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$86,182.00
DATE
04/25/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
•
INCREASE CONTRACT AMOUNT BY:
$86,182.00
-�
AUTHORIZED SIGNATURE (CONTRACTOR)
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-2950
CONTRACTORS LICENSE: CA #955119
-3-
IJcssI
PROJECT
..lilw.ia 'taint ..l.l,....ise
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 I Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
www.calsealants.com
NATIONAL POLICE STATION EVIDENCE Room
CONTRACTOR KINNSMAN CONSTRUCTION
ARCHITECT
DAVID REED CONSULTING
PROJECT No. 15-053
ATTENTION GERARD SHULTZ
DATE
CONTRACT CHANGE ORDER REQUEST NO. 05R2
3/21/16
No.
Description
Extra
Credit
Days
Ext.
i
0
z
la
Parking deck planters: Remove all (E) Bituthene membrane,
prep and install 120 mils of CIM 1000 waterproofing. 710 SF
$14,500.00
5
1b
Labor = $35.15 x 200 hrs
$ 7,030.00
lc
Materials (CIM Primer, CIM 1000, scrim, bonding agent)
$ 5,580.00
id
OH&P (15%)
$ 1,890.00
,i
z
-d
13
2a
Parking deck planters, over new 120 mil waterproofing: Install
J-Drain drainage panel. 710 SF
$ 2,000.00
2
2b
Labor = $35.15 x 30 hrs
$ 1,054.50
2c
Materials (J-Drain drainage panel and 3M glue)
$ 685.00
2d
OH&P (15%)
$ 260.50
ev
z
3a
Building perimeter planters: Remove all (E) Bituthene
membrane (1,500 SF) and install term bar at concrete height,
prep and install 120 mils of CIM 1000 waterproofing. 1,975 SF
$39,500.00
12
3b
Labor = $35.15 x 500 hrs
$17,575.00
3c
Materials (CIM Primer, CIM 1000, scrim, bonding agent)
$16,773.00
3d
OH&P (15%)
$ 5,152.00
es.]J-Drain
0
z
-o
a
4a
Parking deck planters, over new 120 mil waterproofing: Install
drainage panel. 1,975 SF
$ 5,000.00
4
4b
Labor = $35.15 x 70 hrs
$ 2,460.50
4c
Materials (J-Drain drainage panel and 3M glue)
$ 1,888.00
4d
OH&P (15%)
$ 651.50
TOTAL CONTRACT CHANGE
$54,000.00
23
Execution of this change order represents a lump sum cost for the scope of services identified hereon unless noted otherwise.
CHANGE ORDER AGREEMENT
The undersigned hereby agrees to the above -described amendment of the contract.
David A. Felix
Printed Name of Authorized Representative (California Sealant Solutions, Inc. (CSSI))
Manager 3/21/16
Original Contract = $48,500.00
Approved Change Orders:
CO#01 = ($11,650.00)
Change Order Requests:
COR#01 = $2,350.00
CORt102R1 - $3,568.00
COR#03 = ($11,650.00)
COR#04 = $2,500.00
COR#05R2 = $54,000.00
-4-
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-5863 I Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
atlfrr.is sealant „1..n. la. www.calsealants.com
SIGNATURE
TITLE DATE
Total Contract w/COs = $36,900.00
OTHER NOTES:
Printed Name of Authorized Representative (Contractor)
SIGNATURE TITLE DATE
-5-
KINSMAN CONSTRUCTION, INC
TO: Derrick Anderson
PPC
4499 Ruffin Road, Suite 250
San Diego CA 92123
Change Order Request #
11r.1
PHONE
858-634-8180
DATE
04/25/16
JOB NAME
National City Police Department
LOCATION
1200 National City Blvd
JOB NUMBER
S5-029
FAX.
858-634-8184
CONTRACT NUMBER:
Change Order Request #011 r.1
Item No. Description Amount
1 Added waterproofing scope per David Reed recommendations
see attached breakout
Included Item la $10,000.00
Included Item 2a $18,500.00
Included Item 3a $5,000.00
Included Item 6a $2,000.00
2. OH&P $5,325.00
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby to make the change(s) specified above at THIS price
$40,825.00
DATE
04/25/16
BASE CONTRACT AMOUNT:
(original contract amount)
$0.00
. „ .
INCREASE CONTRACT AMOUNT BY:
$40,825.00
AUTHORIZED SIGNATURE (CONTRACTOR)
ACCEPTED - The above prices and specifications of the
Change Order are satisfactory and are hereby accepted.
All work to be performed under same terms and conditions
as specified in original contract unless otherwise
stipulated.
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
Corporate Office: 6711 Nancy Ridge Dr., San Diego, CA 92121 (858)875-2950
CONTRACTORS LICENSE: CA #955119
-6-
1111111...
enlilenb sealant %Callen, ,eo
PROJECT
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-58631 Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
www.calsealants.com
NATIONAL POLICE STATION EVIDENCE ROOM
CONTRACTOR KINSMAN CONSTRUCTION
ARCHITECT
DAVID REED CONSULTING
PROJECT No. 15-053
ATTENTION GERARD SHULTZ
DATE 3/30/16
CONTRACT CHANGE ORDER REQUEST NO. 06
No.
Description
Extra
Credit
Days
Ext.
r,
z
la
Garage & Stairways: Remove efflorescence at garage walls & ceiling,
stairway CMU walls. Prosoco Light Duty Concrete Cleaner and Prosoco Vana
Trol may be utilized per Prosoco instructions. 500 SF
$10,000.00
6
lb
Labor = $35.15 x 150 hrs
$5,272.00
lc
Materials (Prosoco Vana Trol, Rags, Buckets, Etc.)
$3,425.00
ld
OH&P (15%)
$1,303.00
,.i
oo
2a
Adjust grade around building perimeter & properly terminate below grade
waterproofing: Existing Bituthene Membrane and/or Miracote. Membrane C
is to be a minimum of 6 inches above grade. Lower drain board to six inches
below proper grade level. Repair & properly terminate waterproofing
membrane at grade level. Clean to remove any contamination to exposed
membrane surface. Lightly wire brush membrane, & clean with water. Apply
Miracote Universal Primer and Membrane C coating (grey) onto
waterproofing membrane to the sheet membrane extending from the
drainage board to at least six inches above grade. 990 SF
$18,500.00
12
2b
Labor = $35.15 x 120 hrs
$8,787.00
2c
Materials (J-Drain panel and 3M glue, Miracote Primer & Membrane C)
$7,300.00
2d
OH&P (15%)
$2,413.00
`n
0
z
3a
Renovate pedestrian decks on East & West Second floor - Tremco
Vulkem 360NF/951NF. Waterproof under thresholds. Repair and re -coat
pedestrian deck coating and remove and replace adjacent urethane
sealant. 700 SF
�. 5,000.00
5
3b
Labor = $35.15 x 70 hrs
$2,460.00
3c
Materials (191 Primer, Vulkem 360/951NF)
$1,889.00
3d
OH&P (15%)
$651.00
a
o
z
4a
Parking deck coating renovation - Tremco Vulkem 360NF/951NF. Repair and
re -coat parking deck coating and remove and replace adjacent urethane
sealant. A test patch/mock-up to check for adhesion is required. Cut out all
caulking and re -caulk with Tremco Dymonic 100, 1,500 LF. Degrease entire
deck with Simple Green mixture and pressure washer. 3 mobilizations.
Restripe all parking stalls and lines. 33,500 SF
$167,500.00
20
4b
Labor = $35.15 x 1,500 hrs
$52,725.00
4c
Materials (Vulkem 191 primer, Vulkem 360/951NF, Squeegees, Rollers,
Consumables)
$93,000.00
4d
OH&P (15%)
$21,775.00
u'
z°
5a
Parking deck coating renovation - Tremco Vulkem 360NF/951NF. Repair and
re -coat center concrete walkway island on parking deck. 1,000 SF
$5,000.00
3
5b
Labor = $35.15 x 70 hrs
$2,460.00
5c
Materials (Vulkem 191 primer, Vulkem 360/951NF, Squeegees, Rollers,
Consumables)
$1,888.00
5d
OH&P (15%)
$652.00
-7-
C S
CALIFORNIA SEALANT SOLUTIONS, INC.
Office: 619-596-58631 Fax: 619-596-5867
469 Vernon Way, El Cajon, CA 92020
www.calsealants.com
to
®
Z
6a
Mock up - Window system repair: Window wet seal & urethane sealant
replacement around window at break room window on South elevation
$2,000.00
2
6b
Labor = $35.15 x 16 hrs
$562.00
6c
Materials (GE 2000, backer rod, primer, tape, etc.)
$1,178.00
6d
OH&P (15%)
$260.00
TOTAL CONTRACT CHANGE
$208,000.00
48
Execution of this change order represents a lump sum cost for the scope of services identified hereon unless noted otherwise.
CHANGE ORDER AGREEMENT
The undersigned hereby agrees to the above -described amendment of the contract.
Original Contract = $48,500.00
Approved Change Orders:
CO#01= ($11,650.00)
Change Order Requests:
David A. Felix
Printed Name of Authorized Representative (California Sealant Solutions, Inc. (CSSI))
Manager 3/30/16
COR#01 = $2,350.00
COR#02R1— $3,568.00
COR#03 = ($11,650.00)
COR#04 = $2,500.00
COR#05R2 = $54,000.00
COR#06 = $208,000.00
Total Contract w/COs = $36,900.00
SIGNATURE TITLE DATE
OTHER NOTES:
Printed Name of Authorized Representative (Contractor)
SIGNATURE TITLE DATE
-8-
RESOLUTION NO. 2016 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
INCREASING THE CONTRACT WITH KINSMAN CONSTRUCTION, INC.,
FOR THE NOT TO EXCEED AMOUNT OF $127,007.15 FOR THE POLICE
DEPARTMENT BUILDING IMPROVEMENTS PROJECT, AND AUTHORIZING
THE MAYOR -TO EXECUTE CHANGE ORDER NO. 7 IN THE AMOUNT
OF $127,007.15 TO PROVIDE WATERPROOFING AROUND THE ENTIRE
GROUND FLOOR PERIMETER OF THE POLICE DEPARTMENT BUILDING,
PLANTER BOXES, AND TWO PEDESTRIAN DECKS ON THE SECOND FLOOR
WHEREAS, on September 15, 2015, City Council adopted Resolution No. 2015-
139 awarding a contract in the amount of $768,463 to Kinsman Construction, Inc., for the Police
Department Building Improvements Project, CIP No. 15-06; and
WHEREAS, the original contract in the not to exceed amount of $768,463
included electrical and mechanical upgrades to support expansion of the Police Department
Property and Evidence Room, Americans with Disabilities Act upgrades, fire suppression
system upgrades to both the Police Department server room and City Hall server room, heating,
ventilating and air conditioning upgrades to the Police Department sever room, and
waterproofing; and
WHEREAS, during the design phase, a waterproofing specialist was hired to
analyze the waterproofing requirements for the Property and Evidence room, as well as analyze
the remainder of the Police Department building; and
WHEREAS, given the extensive nature of the "building -wide" analysis, only the
recommendations associated with the Property and Evidence room were included in the original
contract, which included waterproofing specific walls, ceilings, cracks, and the planters directly
associated with water intrusion issues for the basement; and
WHEREAS, after contract award, staff continued working with the waterproofing
specialist to complete the analysis for the entire building perimeter where soil is in contact with
walls, the remaining planters surrounding the building, and the two pedestrian decks on the
second floor; and
WHEREAS, the project is currently on schedule with construction completion
estimated for the end of June 2016; and
WHEREAS, six change orders totaling $46,432.71 have been processed, which
is approximately 6% of the contract amount; and
WHEREAS, Kinsman Construction, Inc., has provided a change order proposal
in the not to exceed amount of $127,007, exceeding the original 25% contingency of
$192,115.75.15 to procure and install the waterproofing improvements for the remaining high
priority areas of the building per the waterproofing analysis.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby approves an increase to the contract with Kinsman Construction, Inc., in a
not to exceed amount of $127,007.15.
Resolution No. 2016 —
Page Two
BE IT FURTHER RESOLVED that the Mayor is authorized to execute
Change Order No. 7 in the amount of $127,007.15 to provide waterproofing around the entire
ground floor perimeter of the police department building, planter boxes, and two pedestrian
decks on the second floor.
PASSED and ADOPTED this 3rd day of May, 2016.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Claudia Gacitua Silva
City Attorney
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Aito Ate
Michael R. Dalla, CMC - City Clerk
May 5, 2016
Mr. Craig Kinsman
Kinsman Construction, Inc.
6711 Nancy Ridge Drive
San Diego, CA 92121
Dear Mr Kinsman,
On May 3rd, 2016, Resolution No. 2016-59 was passed and adopted by the City Council
of the City of National City, increasing the Contract amount and authorizing execution of
Change Order #7 to a Contract with Kinsman Construction, Inc.
We are enclosing for your records a certified copy of the above Resolution and a fully
executed copy of the Change Order.
Michael R. Dalla, CMC
City Clerk