Paradise Creek Restoration CHANGE ORDER NO. 2
CIP No: 15-05 May 19, 2016
Contractor: West -Tech Contracting, Inc. rReason/Purpose for this Change Order:
The city has directed the contractor to remove asbestos pipe from the creek channel.
The City of National City and Contractor agree to the following change to the original Contract:
During excavation of line 1 on sheet 23 of 41 the contractor encountered approximately 40 If of asbestos
transite pipe. The city directed the contractor to remove and dispose of this pipe per local, State and Federal
regulations including filing all necessary manifests. All work shall be performed at the agreed lump sum
price below.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders
Subtotal
(55,226.00)
1,605,696.33
Amount of this change order 2,100.00
New contract amount $ 1,607,796.33
Working days added: 0 Workin• days subtracted: 0 Percent change in Contract to date -3.20%
—1—lb
Date
Af
City Project Manag
Date
ngineer Date City Manager, required for Change Orders>i24.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Acce•ted and agreed to b Contractor's name): jl✓oS�- 1 C'/ co.," I'YIetc iN G, ',v c
Name iCK tie RAr.S,EA-1 /0723r6Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
WEST -TECH CONTRACTING
Change Order #2
Paradise Creek Restoration Project
Judy Hernandez (Engineering/PW) Forwarded