HomeMy WebLinkAbout2016 CON Dick Miller Inc - Plaza Blvd and 14th Street Improvements Project CIP 15-10 - Change Order #2CALIFORNIA ---
NATIONAL CITY
rlvcoaPoR x10
Plaza Blvd. and 14th St. Improvements
CIP No: 15-10
Contractor: Dick Miller Inc.
CHANGE ORDER NO. 2
June 7, 2016
Reason/Purpose for this Change Order:
The city has directed the contractor to install eight additional Solar Powered LED Enhanced School Warning
Sign Systems.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor shall provide and install eight additional Solar Powered LED Enhanced School Warning Sign
Systems inclusive of all work as itemized in pay items 51-53. The locations for each are as follows: E. 16th
Street & "B" Ave, E. 18th Street & "F" Ave, E. 8th Street & "K" Ave, E. 8th Street and Olive Ave, Granger Jr.
High Speed Table, E. 16th Street & Grove Street, E. 8th St. and "E" Ave, and Plaza Blvd. and A Ave.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
$ 1,276,903.10
49,815.00
1,326,718.10
170,800.00
New contract amount $ 1,497,518.10
Wodays added: 0 Wprking days subtracted: 0
Percent change in Contract to date 17.28%
SumitIJ°d by:
Date
App oved by:
Cit ngineer
Date
/
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Narfie �Av U.rrua, S, P(tn-W'cr P't AAfiat. , t..Ikt
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
RESOLUTION NO. 2016 — 100
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
INCREASING THE CONTRACT WITH DICK MILLER, INC., IN THE NOT TO
EXCEED AMOUNT OF $170,800 FOR THE PLAZA BOULEVARD AND
14' STREET IMPROVEMENTS PROJECT, AND AUTHORIZING THE MAYOR
TO EXECUTE CHANGE ORDER NO. 2 IN THE AMOUNT OF $170,800
TO PROVIDE AND INSTALL EIGHT SOLAR POWERED, LED -ENHANCED
PEDESTRIAN CROSSING SIGN SYSTEMS AT EXISTING CROSSWALKS
WHEREAS, on March 1, 2016, City Council adopted Resolution No. 2016-27
awarding a contract in the amount of $1,276,903.10 to Dick Miller, Inc., for the Plaza Boulevard
and 14th Street Improvements Project (CIP No. 15-10) (the "Project"); and
WHEREAS, the contract includes purchase and installation of two solar powered,
LED -enhanced pedestrian crossing sign systems for both midblock crosswalks on the 1300
block of Highland Avenue; and
WHEREAS, Dick Miller, Inc., is willing to charge the same unit price per system
for an additional eight (8) systems to be installed at other crosswalks located within the Project
area for a total change order amount of $170,800; and
WHEREAS, Section 3-2.2 of the Standard Specifications for Public Works
Construction (the "Greenbook") permits for change orders of this nature that do not result in a
substantial change in character of the work as provided in the contract plans and specifications;
and
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute Change Order No. 2 to the Plaza
Boulevard and 14th Street Improvements Project contract (CIP No. 15-10) with Dick Miller, Inc.,
for the not to exceed amount of $170,800, above and beyond the original 15% contingency of
$191,535.47, for the purchase and installation of an additional eight (8) solar powered, LED -
enhanced pedestrian crossing sign systems, which includes procurement of equipment,
mobilization, system installation and crosswalk repair and re -striping, at various crosswalks
citywide.
ATTEST:
e>e
PASSED and ADOPTED this 21st day of June, 2016.
Afsva
Michael R. Dalla, ity Clerk
Morrison- Mayor
OVED A TO FOR
Claudia Gacit
City Attorn
Passed and adopted by the Council of the City of National City, California, on June 21,
2016 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
l.a.
City Clerk of the City o National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2016-100 of the City of National City, California, passed and
adopted by the Council of said City on June 21, 2016.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA , a o ‘ c
COUNCIL AGENDA STATEMENT
MEETING DATE: June 21, 2016
AGENDA ITEM NO. 28
ITEM TITLE:
Resolution of the City Council of the City of National City, 1) increasing the contract with Dick Miller, Inc. in
the not to exceed amount of $170,800 for the Plaza Boulevard & 14 h Street Improvements Project, CIP
No. 15-10; and 2) authorizing the Mayor to execute Change Order No. 2 in the amount of $170,800 to
provide and install eight solar powered, LED -enhanced pedestrian crossing sign systems at existing
crosswalks.
PREPARED BY: Jose Lopez, Junior Engineer -Civil
PHONE: 336-4312
EXPLANATION:
See attached.
DEPARTMENT: Engineering & Public Works
APPROVED BY:
FINANCIAL STATEMENT:
ACCOUNT NO.
APPROVED:
APPROVED:
Expenditure Account: 307-409-500-598-6166 (Prop A TransNet - Citywide Safe Routes to School)
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
Finance
MIS
STAFF RECOMMENDATION:
Adopt the Resolution.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Change Order No. 2
3. Resolution
REso�v��o�1 No. ,C\C-\Cd
EXPLANATON
On March 1, 2016, City Council adopted Resolution No. 2016-27 awarding a
contract in the amount of $1,276,903.10 to Dick Miller, Inc. for the Plaza
Boulevard and 14th Street Improvements Project, CIP No. 15-10 ("Project"). The
contract includes purchase and installation of two solar powered, LED -enhanced
pedestrian crossing sign systems ("Crossing Signs") for both midblock
crosswalks on the 1300 block of Highland Avenue. The unit price of $21,350 per
system, which includes procurement of equipment, mobilization, system
installation and crosswalk re -striping, is the lowest the City has received through
competitive bidding over the past four years. As such, staff approached Dick
Miller, Inc. to see if they would honor the same unit prices to provide an
additional eight systems at other crosswalks located within the Projeclt area. Dick
Miller, Inc. agreed to charge the same unit price of $21,350 per system for a
total change order amount of $170,800.
Section 3-2.2 of the Standard Specifications for Public Works Construction
(Greenbook) allows for an increase in quantity for bid items of work covered by
contract unit pricing through execution of a construction change order if the
change order "does not result in a substantial change in character of the work" as
provided in the contract plans and specifications. Staff contends that installation
of the additional solar powered, LED -enhanced pedestrian crossing sign systems
falls within the same character of work contemplated in Resolution No. 2016-27
because the intent of the Project is to enhance pedestrian safety and access at
existing crosswalks through traffic calming, lighting, and enhanced signing and
striping. Section 3-2.2 of the Greenbook permits this type of change order
because the cost of the eight Crossing Signs does not increase the contract price
by more than 25 percent.
The project is currently on schedule with construction completion estimated for
September 2016. Execution of this Change Order No. 2 would require the
contractor to complete this additional work within the existing project schedule.
To date, staff has executed one change order totaling $49,815. Staff
recommends execution of this Change Order No. 2 in a not to exceed amount of
$170,800, above and beyond the original 15% contingency of $191,535.47,
which should be retained to address unforeseen conditions. Funds are available
in the Prop A TransNet Citywide Safe Routes to School expenditure account no.
307-409-500-598-6166 through previous City Council appropriations.
Plaza Blvd. and 14th St. Improvements
CIP No: 15-10
Contractor: Dick Miller Inc.
CHANGE ORDER NO. 2
June 7, 2016
Reason/Purpose for this Change Order:
The city has directed the contractor to install eight additional Solar Powered LED Enhanced School Warning
Sign Systems.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor shall provide and install eight additional Solar Powered LED Enhanced School Warning Sign
Systems inclusive of all work as itemized in pay items 51-53. The locations for each are as follows: E. 16th
Street & "B" Ave, E. 18th Street & "F" Ave, E. 8th Street & "K" Ave, E. 8th Street and Olive Ave, Granger Jr.
High Speed Table, E. 16th Street & Grove Street, E. 8th St. and "E" Ave, and Plaza Blvd. and A Ave.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Woy hvg days added: 0
Wprking days subtracted: 0
$ 1,276,903.10
49,815.00
1,326,718.10
170,800.00
$ 1,497,518.10
Percent change in Contract to date 17.28%
Submitted
by:
Proj
Manag Date
'MAYOR Date
App oved by:
Cit ngineer
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
N e: PAv i._rr-tAe, S P(ZB-rrcr r.tiaaCTi M
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
RESOLUTION NO. 2016 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
INCREASING THE CONTRACT WITH DICK MILLER, INC., IN THE NOT TO
EXCEED AMOUNT OF $170,800 FOR THE PLAZA BOULEVARD AND
14T" STREET IMPROVEMENTS PROJECT, AND AUTHORIZING THE MAYOR
TO EXECUTE CHANGE ORDER NO. 2 IN THE AMOUNT OF $170,800
TO PROVIDE AND INSTALL EIGHT SOLAR POWERED, LED -ENHANCED
PEDESTRIAN CROSSING SIGN SYSTEMS AT EXISTING CROSSWALKS
WHEREAS, on March 1, 2016, City Council adopted Resolution No. 2016-27
awarding a contract in the amount of $1,276,903.10 to Dick Miller, Inc., for the Plaza Boulevard
and 14th Street Improvements Project (CIP No. 15-10) (the "Project"); and
WHEREAS, the contract includes purchase and installation of two solar powered,
LED -enhanced pedestrian crossing sign systems for both midblock crosswalks on the 1300
block of Highland Avenue; and
WHEREAS, Dick Miller, Inc., is willing to charge the same unit price per system
for an additional eight (8) systems to be installed at other crosswalks located within the Project
area for a total change order amount of $170,800; and
WHEREAS, Section 3-2.2 of the Standard Specifications for Public Works
Construction (the "Greenbook") permits for change orders of this nature that do not result in a
substantial change in character of the work as provided in the contract plans and specifications;
and
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby authorizes the Mayor to execute Change Order No. 2 to the Plaza
Boulevard and 14th Street Improvements Project contract (CIP No. 15-10) with Dick Miller, Inc.,
for the not to exceed amount of $170,800, above and beyond the original 15% contingency of
$191,535.47, for the purchase and installation of an additional eight (8) solar powered, LED -
enhanced pedestrian crossing sign systems, which includes procurement of equipment,
mobilization, system installation and crosswalk repair and re -striping, at various crosswalks
citywide.
PASSED and ADOPTED this 21st day of June, 2016.
Ron Morrison, Mayor
ATTEST: APPROVED AS TO FORM:
Michael R. Dalla, City Clerk Claudia Gacitua Silva
City Attorney
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Order #2
Plaza Blvd. and 14th Street Improvements
Judy Hernandez (Engineering/PW) Forwarded
Copy of Changer Order to Dick Miller, Inc.