HIGHLAND AVENUE SAFETY ENHANCEMENTS
Specification No. 13-07
Contractor: Portillo Concrete, Inc.
CHANGE ORDER NO. 2
April 8, 2014
Reason/Purpose for this Change Order:
Southbound Highland approaching 8th Street had to be restriped to one lane to accommodate the turning radius
of the MTS buses turning right onto 8th Street. Under the direction of the Engineer the Contractor proceeded with
the work.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall restripe Southbound Highland approaching 8th Street
to one lane to accomodate the turning radius of the MTS Buses. The lump sum change order price includes all
labor, materials, and equipment required to complete this work. The agreed upon price for all costs associated
with this work is as stated on this Change Order.
Original Contract Amount $ 1,379,220.00
2,297.02
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0 Working days subtracted: 0
1, 381, 517.02
3,197.25
Percent change in Contract to date 0.40%
1,384,714.27
Submitted by:
Pr c1M---'1V
t Man
er
Date
P '
Resi ent Engineer
412-lb r
Date
Approved by:
2.....
City ngineer
•
�
�-i t it
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and reto by Portillo Concrete, Inc.:
Name:
V.1-1s
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Telephone (619) 336-4380
1243 National City Boulevard, National City, CA 91950
\'I
CALIFORNIA
&1T9Lcfl'v
INCORPORATED /1
HIGHLAND AVENUE SAFETY ENHANCEMENTS
Specification #13-07
CHANGE ORDER NO. 2
DATE: April 8, 2015
WORK PERFORMED BY: Portillo Concrete, Inc.
DESCRIPTION OF WORK: Restripe of Southbound Highland approaching 8th to one lane
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Rate
Total
1)
2)
Remove D-9 Skip Stripe by
Waterblasting
LF
550.00
3.00
1,650.00
3)
4)
Detail 27B 4" Right Edgeline
Type VI Lane Drop Arrow
T-Stalls
LF
EA
EA
250.00
3.00
5.00
1.00
100.00
10.00
250.00
300.00
50.00
5)
Roadside Sign (Various Designations)
EA
3.00
265.00
795.00
Sub -Total:
Prime Contractor Markup (5%):
TOTAL COST:
$ 152.25
$ 3,197.25
$ 3,045.00
c' s;
y.i sA=
£
RATED A
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
PORTILLO CONCRETE
Change Order #2
Highland Avenue Safety Enhancements Project
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Order to Portillo Concrete