Reason/Purpose for this Change Order:
The original plans did not account for the relocation of backflow preventers and removing a tree at 1539 E Plaza
Blvd. Under direction of the Engineer the Contractor is to proceed with relocating 3 backflow preventers and
removing and disposing of a cupania tree.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with relocating 3 backflow preventers and
remove and dipose of a cupania tree at 1539 E Plaza Blvd. The agreed upon price for all costs associated with
this work is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 1,894,498.10
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
1,894,498.10
5,181.84
New contract amount $
Working days added: 0 Working days subtracted: 0
Submitted by:
s/1/1t
ect ManDate
'Approved by:
id
n ineer Date ICity Manager, required for Change Orders S24999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Percent change in Contract to date 0.27%
1,899,679.94
Accepted and agreed to by Dick Miller, Inc.:
SI1c�Jt
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Tefephone(619) 336-4380
CALIFORNIA
NATIONAL TIONAL CI'!'y
INCORPORATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification # 16-01
DATE: May 10, 2016
CHANGE ORDER NO. 1
WORK PERFORMED BY: Dick Miller, Inc.
DESCRIPTION OF WORK: Relocate 3 backflow preventers and remove and dispose of a
cupania tree at 1539 E Plaza Blvd
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
2)
3)
4)
5)
Foreman
Laborer - Dig and Backfill
Laborer - Dig and Backfill
Laborer - Install Concrete Pad
Laborer - Set enclosure and
connect existing valves
Hour
Hour
Hour
Hour
Hour
8.00
8.00
8.00
4.00
6.00
80.20
55.52
55.52
57.63
57.63
641.60
444.16
444.16
230.52
345.78
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$ 2,106.22
$ 421.24
$ 2/527.46,,
MATERIALS
Unit
Qty
Rate
Total
1)
Pipe Materials
LS
1.00
785.33
785.33
2)
Concrete
CY
0.50
100.00
50.00
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 835.33
$ 125.30
EQUIPMENT
Unit
Qty
Rate
Total
1)
Chevy Truck with Tools
Hour
8.00
50.00
400.00
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 400.00
$ 60.00
SUB TOTAL:
$ 960.63 I
$ 460.00
$ 3,948.09
CALIFORNIA+
NATIONAL CM
INCORPORATED
SUBCONTRACTOR
Unit
Qty
Rate
Total
1)
1)
Remove and dispose Tree
Grind stump in place
LS
LS
1.00
1.00
800.00
375.00
Sub -total Subcontractor:
Prime Contractor Markup (5%):
800.00
375.00
$ 1,175.00
58.75
TOTAL SUBCONTRACTOR:
$ 1,233.75
GRAND TOTAL:
$5,181.84
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Order #1
Plaza Blvd. Widening "N" Avenue to 1-805
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Order to Dick Miller, Inc.