Kimball, El Toyon and Kimball Skate Park Improvements CHANGE ORDER NO. 7
CIP No: 15-04
Contractor: Westem Rim Constructors, Inc.
Reason/Purpose for this Change Order:
The city has determined asbestos materials were located in the El Toyon Restroom facility prior to demolition
and directed the contractor to properly remove and dispose the material.
April 26, 2016
The City of National City and Contractor agree to the following change to the original Contract:
The city determined the El Toyon Restroom may contain asbestos materials. After undergoing a testing
procedure the results came back positive. The contractor has been directed to obtain a contractor licensed
and registered to properly remove and dispose of the asbestos material identified in the El Toyon Restroom
roof mastic. This work shall include all labor, materials and equipment and related cost necessary to
complete the asbestos removal and disposal at the El Toyon Restroom facility. All work described above shall
be completed for the lump sum price stated below.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 5 Working days subtracted: 0
iSu t'ted by:
, /0.11
roject Manager Date ity Project AAanager - Date
103, 942.80
3,556,285.78
1,155.00
$ 3,557,440.78
Percent change in Contract to date 3.04%
Aproved by:
!CityvEngineer O Date
City Manager, required for Change Orders >$24.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the origi - ontract .. ments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accept: d a • ag to by (Contractor's name):
v vv /��
Name: Date
Note to Contractor: tf you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
— CALIFORNIA
NATIONAL ClIfir
INCORPORATEO
Kimball, El Toyon and Kimball Skate Park Improvements CHANGE ORDER NO. 8
CIP No: 15-04 April 26, 2016
Contractor: Westem Rim Constructors, Inc.
Reason/Purpose for this Change Order:
The City has directed the Contractor to delete a portion of electrical work related to camera installation for
security coordination with the City's IT Department.
The City of National City and Contractor agree to the following change to the original Contract:
The Contractor shall eliminate installation of 37 cameras and mounts, and associated system testing. This
change order deletes Bid Item #36 for $11,270.60 at Kimball Park; Bid Item #87 for $7,889.42 at El Toyon
Park; and Bid Item #145 for $1,690.59 and Bid Item #148 for $4,007.36 at Kimball Skate Park. This deduction
includes all associated labor and equipment related to installation, system testing and verification. All work
described above shall be completed for the lump sum price stated below.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
105, 097.80
3,557,440.78
(24,857.97)
New contract amount $ 3,532,582.81
Working days added: 0 Workin • ays subtracted: 0 Percent change in Contract to date 2.32%
Sub d by:
s/io. Lh t
Manager " Date Project lylanager
roved by:
City Engineer / Date
City Manager, required for Change Orders >$24.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead ees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the o : in . contra cuments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Ate• -d a • a• j� �► to by (Contractor's name):
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
,... CALIFORNIA
Percent change in Contract to date 2.48%
NATIONAL er'Z"i v
rvcoRpoRATED
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
Reason/Purpose for this Change Order
The city has determined two existing light towers at Las Palmas Park should be removed immediately due to
public safety.
CHANGE ORDER NO. 9
May 5, 2016
The City of National City and Contractor agree to the following change to the original Contract:
The city determined that two existing light towers at Las Palmas Park had corrosion to the existing pole baes
that could fail without warning. The contractor has been directed to bring down two poles identified at Las
Palmas and completely remove them from the site. This work shall include all labor, materials and equipment
and related cost necessary to complete the removal and secure the existing electrical wires so the additional
remaining lights and electrical system is safe to the public. All work described above shall be completed for
the lump sum price stated below.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
80,239.83
3, 532, 582.81
5,250.00
New contract amount $ 3,537,832.81
Working days added: 0 Workin.days subtracted: 0
Su. i -d by:
-roj= Manage Date (pity ProjectNlanager
Cityngineer
Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and comp -te and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supe overhe •es, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the . rigin: l contr. .. uments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
to by (Contractor's name):
Name:
s"-kiL
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
NATIONAL CITY.
sly
INCOR FORATFD
Kimball, El Toyon and Kimball Skate Park Improvements CHANGE ORDER NO. 10
CIP No: 15-04 May 27, 2016
Contractor: Western Rim Constructors, Inc.
Reason/Purpose for this Change Order:
The city has determined temporary restroom are needed during the construction of the two El Toyon
Restrooms since there are no other facilities in place.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been requested to supply temporary restrooms during the construction of the two El Toyon
Restrooms since there are no other facilities in place during construction. The contractor supplied two
standard and two ADA restrooms with sinks. The restrooms are to be serviced twice a week for a three
month period. All delivery and services are included for the lump sum price indicated below.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders 85,489.83
Subtotal 3,537,832.81
Amount of this change order 4,510.94
New contract amount $ 3,542,343.75
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 2.61%
Subrfndted by:
Date jjj 'City Project Manager Date
•
df/x( I
OG /aelib
Engineer Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
ed to by (Contractor's name):
h.
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA -_=
NATJ®N L CiTy
=NCORPORATEP
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Westem Rim Constructors, Inc.
CHANGE ORDER NO. 11
June 1,2016
Reason/Purpose for this Change Order.
The contractor encountered an existing mainline during excavation of the Skate Park. The mainline was in
conflict with the construction of the new Skate Park and required relocation.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor was required to relocate an existing 4" PVC mainline and irrigation wire outside the
construction limits of the Skate Park. All work was completed on a T&M basis.
Original Contract Amount ......................................................
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
$ 3,452,342.98
90,000.77
3,542, 343.75
17,750.69
New contract amount $ 3,560,094.44
Working days added: 10 Working d- s subtracted: 0
Sub -d by:
Percent change in Contract to date 3.12%
Manager Date City Project Ma r Date
ed by:
gineer Date ' City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor wit provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete a epresents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fe • . ds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the • igi .I contract do ` - is are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
nd agree • ► y (Contractor's name): f
t4f.1311b
ame: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA —'
NATIONAL MI
rNcOnpon AT ED
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
CHANGE ORDER NO. 12
June 1, 2016
Reason/Purpose for this Change Order.
The contractor encountered several locations of unmarked existing irrigation wire. The wire had been
previously spliced and buried below grade without proper identification or splicing methods and needed to be
repaired or replaced.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to trace, identify and repair as needed multiple locations of existing
irrigation wire. This included repairing existing faulting connections and marking all wire to three separate
controllers and installing splice boxes as needed. All work was completed on a T&M basis.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal ........... ........ ....... ...................................... .......... ......... ......... ......
..,
Amount of this change order
New contract amount
Working days added: 5
d by:
Working days subtracted: 0
$ 3,452,342.98
107, 751.46
3, 560, 094.44
16,551.97
$ 3,576,646.41
Percent change in Contract to date 3.60%
063
Date City Project Manage Date
dpj6b
City Engineer / Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, f
of the on r na ontract
Name:
s, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
ments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
o by (Contractor's name):
k47\.b‘NO
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
WESTERN RIM CONSTRUCTORS
Change Order #7 - #12
Kimball Park, El Toyon Park and Kimball Skate Park Improvements
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Orders to Western Rim Constructors