HomeMy WebLinkAbout2016 CON Portillo Concrete - Highland Avenue Safety Enhancements Project - Change Order #10 #11 #13 through #16CALIFORNIA NATIONAL Car C S V INCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 10 February 10, 2016 Reason/Purpose for this Change Order: The specified grates in the plans did not meet ADA standards with having greater than 1/2" inch opening for a pedestrian path. Under the direction of the Engineer the Contractor returned the original grates and replaced them with grates that meet ADA standards. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with replacing the grates to meet ADA standards. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost breakdown. Original Contract Amount $ 1,379,220.00 Net change by previously authorized Change Orders .............................. 42,341.65 Subtotal 1,421,561.65 Amount of this change order 11,521.97 New contract amount $ 1,433,083.62 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 3.91% Submitted by: /iv % 6 Date 0/.c, Date tbW1 Resident Engineer Pr ct Mana r Approved by: 2 Cit nglneer � �2.hii Date City Manager, required for Change Orderso$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price Is fair and complete and represents all costs associated with the work, induding but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Acce ted and a.ree•_o •. ,'ortitto Concrete, Inc.: Name: i achol>° ( fal fjI (o Date ,vj/o I (k Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 1 / CALIFORNIA - NATIONAL C'I INCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification #13-07 CHANGE ORDER NO. 10 DATE: February 10, 2016 WORK PERFORMED BY: T.L. Scanlan Construction DESCRIPTION OF WORK: Removing original grates and replacing with grates that meet ADA Revised Grates ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit LS Qty 1.00 Rate 9,542.00 Sub -Total: Markup (15%): Total 9,542.00 $ 9,542.00 $ 1,431.30 TOTAL: PRIME CONTRACTOR MARKUP (5%): $ 10,973.30 $ 548.67 GRAND TOTAL: $11,521.97 .\ 1 I / CALIFORNIA N I�!. ZONAL OMIT li& 3 J INConpoRATEO HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 11 February 10, 2016 Reason/Purpose for this Change Order: The revised grates that met ADA standards were only available as 17" wide trench grates. Additional form work was required to reduce the trench width from 24" to the new 17". Under the direction of the Engineer the Contractor proceeded with reducing the width of trench to accomodate the 17" grates. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with reducing the width of the trench to accomodate the 17" grates. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost breakdown. Original Contract Amount $ 1,379,220.00 Net change by previously authorized Change Orders Subtotal Amount of this change order 53,863.62 1,433,083.62 11,450.40 New contract amount $ 1,444,534.02 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 4.74% Submitted by: e Pro' t Mana - g 2/ 1 /16 Date at i Approved by: City ngineer Date City Manager, required for Change Orders>524999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and agreed to by Portillo Concrete, Inc.: Note to Contractor: If you .. not agre-r ith this Change Order you may be directed to proceed with this work under the terms of the contra Name: Dater2//l1% and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager Telephone (619) 336-4380 1243 National City Boulevard, National City, CA 91950 -* CALIFORNIA NATIONAL CI ry anv INCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification #13-07 DATE: February 10, 2016 CHANGE ORDER NO. 11 WORK PERFORMED BY: TL Scanlan Construction. DESCRIPTION OF WORK: Reduce width of Trench Drains from 24" to 17" ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) 3) 4) 5) Carpenter Carpenter Carpenter Laborer Laborer Hour Hour Hour Hour Hour 24.00 24.00 24.00 24.00 24.00 69.20 69.20 69.20 62.00 62.00 1,660.80 1,660.80 1,660.80 1,488.00 1,488.00 Sub -Total Labor: Labor Surcharge (12%): Labor Markup (20%): TOTAL LABOR: $ 955.01 $ 1,782.68 A Unit Qty Rate Total 1) N/A LS Sub -Total Materials: Subcontractor Markup (5%): TOTAL MATERIALS: $ $10,696.09 EQUIPMENT Unit Qty Rate Total 1) Crew Truck and tools Hour 24.00 27.33 655.92 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 98.39 $ 754.31 GRAND TOTAL: $11,450.40 $ 655.92 $ 7,958.40 4 CALIFORNIA �INCORPORATED _J HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 13 March 23, 2016 Reason/Purpose for this Change Order: The median layouts were adjusted to accommodate the entrances of businesses. With the new layouts the overall square feet of line item 10, Stamped & Colored PCC Median (4" Thick), was decreased more than 25%. The bid quantity being 5,650 SF and the final measured quanity of 2,978 SF created a 47% reduction. Per section 3-2.2.3 the Contractor requested an adjustment in payment because of the reduction of quantity and loss of continunuity of work. The work was stopped and redesigned with the new layout. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall be compensated for the reduced quantity of line item 10, Stamped & Colored PCC Median (4" Thick). The agreed upon lump sum price for all additional costs associated with this line item is as stated on this Change Order. Original Contract Amount $ 1,379,220.00 Net change by previously authorized Change Orders Subtotal Amount of this change order New contract amount Working days added: 0 Working days subtracted: 0 69,780.23 1,449,000.23 3,206.40 Percent change in Contract to date 5.29% 1,452,206.63 Submitted by: !. ect Ma ger Date Date .. �� es dent Enginee Approved by: City ngineer Date City Manager, required for Change Orders>$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and agreed toffy Portillo Concrete, Inc.: Name: Rh2e,1 t`Ut--7/LL Q Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 D40,6 ate Telephone (619) 336-4380 ii. - CALIFORNIA ,-e- NATIONAL lorry i;3v1 INCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 14 March 23, 2016 Reason/Purpose for this Change Order: The bulbout graded were redesigned to greatly reduce the amount of asphalt street section being removed and replaced. With the new design the overall tons of line item 20, Construct 5" asphalt concrete, was decreased more than 25%. The bid quantity being 148 tons and the final measured tons of 67.66 created a 54% reduction. Per section 3-2.2.3 the Contractor requested an adjustment in payment because of the loss of production and creating small patches at 6 different locations. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall be compensated for the reduced quantity of line item 20, Construct 5" asphalt concrete. The agreed upon lump sum price for all additional costs associated with this line item is as stated on this Change Order. Original Contract Amount.. $ 1,379,220.00 Net change by previously authorized Change Orders 72,986.63 Subtotal... Amount of this change order New contract amount $ Working days added: 0 Working days subtracted: 0 1,452,206.63 2,229.44 Percent change in Contract to date 5 45° 1,454,436.07 Submitted by: Pr ct Mana r Date esident Enginee ate Approved by: City ngineer Date City Manager, required for Change Orders>$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accept-d an. -ate Portillo Concrete, Inc.: 3/9[3aV/& Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 >rLL. CALIFORNIA .-c« NOIO.lAvIr.. Cf 'i IlP° '— } INCORRPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 15 March 28, 2016 Reason/Purpose for this Change Order: The green bike boxes at Highland Avenue and 4th Street were damaged during installation of pedestrian ramps and needed to be repaired. The Contract for Highland Avenue was accepted before the installation of the green bike boxes for the Community Corridors Project. Under the direction of the Engineer the Contractor proceeded with repairing the green bike boxes. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall repair the green bike boxes at Highland Ave and 4th Street. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost breakdown. Original Contract Amount $ 1,379,220.00 Net change by previously authorized Change Orders Subtotal Amount of this change order New contract amount $ Working days added: 0 Working days subtracted: 0 75,216.07 1,454,436.07 787.50 Percent change in Contract to date 5.51% 1,455,223.57 Submitted by: Pr•'-ct Manage Date .......... sldent Engineer ate Approved by: 2. iY gineer y y/d Date City Manager, required for Change Orders>$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and a reed t by Portillo Concrete, Inc.: Date 3%. Note to ContracIor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager Telephone (619) 336-4380 1243 National City Boulevard, National City, CA 91950 CALIFORNIA . NATAL Cir 'y i ac o 7 NCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification #13-07 DATE: March 28, 2016 CHANGE ORDER NO. 15 WORK PERFORMED BY: Shariden Design Asphalt Inc. DESCRIPTION OF WORK: Green Bike Box repairs ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Green Bike Box Repairs Unit LS Qty 1.00 Rate 750.00 Sub -Total: Total 750.00 $ 750.00 TOTAL: PRIME CONTRACTOR MARKUP (5%): 750.00 $ 37.50 GRAND TOTAL: $ 787.50 SHARIDEN DESIGN ASPHALT INC. P.O. Box 285 Alpine, CA 91903 Phone: 619-445-3611 Fax: 619-445-3642 E Mail: sharie@sharidendesignasphalt.com Contractors License Number: 760168 Portillo 3527 Citrus St Lemon Grove, Ca 91945 Rachael Portillo Customer E-mail iportillo a portilloconcreteinc.com Item Description Date Estimate # 3/11/2016 1 0296 REV Customer Phone 619 466-4685 Customer Fax Project Qty Rate Total MOBILIZATION PRE MARK MOBILIZATION Highland And 4th Breakdowm / Revised Labor One Man 5 Hours Pre Mark Thermoplastic Green Bike Panels Approximately 3 to 5 Panels / Sealer Dodge Ram 5500 Truck & Equipment : Hand Held Street Heat Propane Torch. Poroane. lnfared Thermometer. 290.00 210.00 250.00 290.00 210.00 250.00 Shariden Design Asphalt is a Certified Level III StreetPrint Applicator Date: L Total $750.00 Signature: Subtotal Amount of this change order New contract amount Working days added: 0 CALIFORNIA NATIONAL City (^�- INCCRPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification No. 13-07 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 16 April 1, 2016 Reason/Purpose for this Change Order: New wire had to be pulled to repair the safety light above the traffic signal at the SW corner of Highland Avenue and 8th Street. Under the direction of the Engineer the Contractor proceeded with repairing the safety light. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall repair the safety Tight at the SW corner of Highland Avenue and 8th Street. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost breakdown. Original Contract Amount $ 1,379,220.00 Net change by previously authorized Change Orders 76,003.57 Working days subtracted: 0 1,455,223.57 1,079.12 $ 1,456,302.69 Percent change in Contract to date 5.59° Submitted by: P ject Man er C1A1//./ Date ':_tiairA/ ate Resident Engineer Approved by: 1 Cif. ngineer J. te r Date City Manager, required for Change orders>$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Acce.ted and agree.. by Portillo Concrete, Inc.: Name: 4-7 pa272444 Date ///i Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the ontract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA NATIONAL CITY a �`, M. INCORPORATED HIGHLAND AVENUE SAFETY ENHANCEMENTS Specification #13-07 DATE: April 1, 2016 CHANGE ORDER NO. 16 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Repairing Safety Light on the SW corner of Highland and 8th. ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) Tech 1 - Tim Peterson Tech 2 - Dan Flores Hour Hour 6.00 4.00 41.12 26.37 246.72 105.48 Sub -Total Labor: Labor Surcharge (12%): Labor Markup (20%): TOTAL LABOR: $ 352.20 42.26 $ 70.44 $ 464.90 MATERIALS Unit Qty Rate Total 1) N/A Sub -Total Materials: Materials Markup (15%): TOTAL MATERIALS: $ UIPMENT Unit Qty Rate Total 1) 2) 3) 4) Bucket Truck Boom Lift Air Compressor Utility Truck Hour Hour Hour Hour 4.00 4.00 4.00 6.00 28.17 34.60 17.33 28.17 112.68 138.40 69.32 169.02 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: PRIME CONTRACTOR MARKUP (5%): $ 489.42 $ 73.41 $ 562.83 $ 51.39 GRAND TOTAL: $1,079.12 CITY OF NATIONAL CITY Office of the City Clerk 1243 National City Blvd., National City, California 91950-4397 619-336-4228 phone / 619-336-4229 fax Michael R. Dalla, CMC - City Clerk PORTILLO CONCRETE Change Order #10 - #11, #13 - #16 Highland Avenue Safety Enhancements Project Judy Hernandez (Engineering/PW) Forwarded Copy of Change Orders to Portillo Concrete