HomeMy WebLinkAbout2016 CON Western Rim Constructors - Parks Improvements Project - Change Order #13 #14CALIFORNIA
--
NATIONAL CITY
»
INCORPORATED
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
CHANGE ORDER NO. 13
June 29, 2016
Reason/Purpose for this Change Order:
To replace the existing, deteriorated transformer with a new transformer that meets current electrical code
and energy efficiency requirements.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to furnish and install a new 15 KVA transformer with wire at El Toyon Park.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders... .................................... 124,303.43
Subtotal
3,576,646.41
Amount of this change order 3,182.55
New contract amount $ 3,579,828.96
Working days added: 3
ed by: /7
Working days subtracted: 0
ate
74.//‘
Cit ngineer 0 Date
Percent change in Contract to date 3.69%
roject Manager
qkte
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, b..ds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the origin ontract docu &are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Contractor's name):
(62L )b
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
WESTERN RIM CONSTRUCTORS, INC.
921 S. Andreasen Drive, Suite B, Escondido, CA. 92029
Phone: 760-489-4328 Fax: 760-489-4304
REQUEST FOR CONTRACT CHANGE ORDER
DATE: 6/2/2016
PROJECT: Kimball, El Toyon and Kimball Skate Park Improvements
CIP NO: 15-04
WRC PCO NO: 023
WRC JOB NO:
202
Description of Change Order Request:
Install new electrical transformer at El Toyon Park as requested by the City of National City
Item
1 Ace Electric
2
3
4
Description
Sub Total
Mark Up
Total this Request
Quantity Unit
1 LS
WRC requires a 3 work day time extension to perform this additional work
Unit Price
$ 3,031.00 $
Total Price
3,031.00
$ 3,031.00
$ 151.55
$ 3,182.55
By:
Title:
Date:
Western Rim Costructors, Inc. City of National City
Mike Domanski
Project Superintendent
2/11/2016
By:
Title:
Date:
0
ACE ELECTRIC
June 1, 2016
Western Rim Constructors
912 S. Andreasen Dr., Ste. 108
Escondido, CA 92029
Attention Mike Domanski
Subject: Kimball & El Toyon Park
Change Order #13 — New Transformer
Mike,
Please issue a change order for $3,031.00 to install a new 15KVA transformer with wire as per RFI
responses 29 and 31. See the attached breakdown for details.
Please call if you have any questions or if you need additional information.
Sincerely,
Ryan Swenson
P.O. Box 601071
San Diego, CA 92160-1071
tic. No. 835109 A,C10 Tel (619) 521-9740 ext. 102
www.AceElectriclnc.com Fax (619) 521-9742
6/1/2016 2:47:29 PM
Ace Electric, Inc.
Kimball and El 'rayon Change Orders
Totals (Summary) - Bid Summary: Default
Page 1
51,912.78
1'7215
5551.28
.... 0.00
5551.28
50.00
0.00
52,6401
395.43
$3,031.64
.031,64
5/31/2016 1:59:24 PM
Item #
Description
Ace Electric, Inc.
Kimball and El Yoyon Change Orders
Job Number: 1778-CO
Extension By Section
Quantity
Price U
Ext Price Labor Hr U
Page 1
Ext Lab Hr
2797
3616
#1 THHN CU Stranded Wire
15 KVA 1PHTiansfonner 240V X 480V
PrI 2915KVA Transformer Total —
Job Total
2915KVA.Tiansfomier- ; .i
50 1,374.46 M
68.72
13.20 M
0.66
1,912.78 7.37
1,912.78
7.37
* Target, Labor column 2
CALIFORNIA —
NATIONAL CITY
1:3 3'/
INCORPORATED
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
CHANGE ORDER NO. 14
June 29, 2016
Reason/Purpose for this Change Order:
To more effectively communicate the rules and guidelines of the Kimball Skate Park to park users, the City
requested one additional sign to be furnished and installed at the Skate Park, for a total of three (3) signs.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to furnish and install one additional sign frame at Kimball Skate Park at the
location determined in the field.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders 127,485.98
Subtotal
3,579,828.96
Amount of this change order 1,989.55
New contract amount...
Working days added: 0
FSub, ed by:
Ci/irq
Working days subtracted: 0
$ 3,581,818.51
Percent change in Contract to date 3.75%
Date
1"
roject Manager / Date
ngineer Date City Manager, required for Change Orders 424,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision verhead, fees, bon j, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the on.;. ntract docume , e incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
e • t, • G ► • *reed to r ontractor's name):
Name:
(oI�Q �Ilo
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
WESTERN RIM CONSTRUCTORS, INC.
621 S. Andreasen Drive, Suite B, Escondido, CA. 92029
Phone: 760-489-4328 Fax: 760-489-4304
REQUEST FOR CONTRACT CHANGE ORDER
DATE: 6/6/2016
PROJECT: Kimball, El Toyon and Kimball Skate Park Improvements
CIP NO: 15-04
WRC PCO NO:
WRC JOB NO:
24
202
Description of Change Order Request:
Provide & install one additional Skate Park sign frame as directed by City of National City
Item
1 Install Sign Frame
2
3
4
Description
Sub Total
Mark Up
Total this Request
Quantity Unit
1 LS
WRC requires a 0 work day time extension to perform this additional work
Unit Price
$ 1,989.55 $
$
$
$
Total Price
1,989.55
1,989.55
$ 1,989.55
By:
Title:
Date:
Western Rim Costructors, Inc. City of National City
Mike Domanski
Project Superintendent
6/6/2016
By:
Title:
Date:
Material
Unit
Unit Cost
Total
LABOR
HOURS
HOURLY
RATES
EXTENDED
AMOUNTS
EZ Sign
1
$ 971.63
$ 971.63
Laborer 1
OT
$ -
REG
6
$ 48.66
$ 291.96
$ -
$
Laborer 1
OT
$ -
REG
6
$ 48.66
$ 291.96
$ -
$ -
OT
$ -
REG
0
$ -
$ -
$ -
OT
$ -
REG
0
$ -
$ -
$ -
OT
$ -
REG
0
$ -
$ -
$ -
OT
$ -
REG
0
$ -
$ 971.63
OT
$ -
REG
0
$ -
APPROVED WORK DONE BY SPECIALISTS
$ 583.92
Payroll Burden 22% $126.48
DESCRIPTION
NO. UNIT
UNIT COST
`HOURLY RATES - PER SECTION 3-3.2.2
TOTAL LABOR
A
$710.40
TOTAL COST OF EQUIPMENT, MATERIALS AND WORK
$ -
$ -
B
TOTAL EQUIPMENT & MATERIALS
C
$ 971.63
20 % MARKUP ON LABOR COST ( A)
$ 142.08
$ 145.74
1 b % MARKUP ON EQUIPMENT, MATERIAL AND WORK COST ( B)
$ -
CONTRACTOR'S REPRESENTATIVE
5 % MARKUP ON SUBCONTRACTED WORK c C)
$ 1,969.85
SUBTOTAL
( D)
$ 19.70
RESIDENT ENGINEER 1 % BOND AND LIABLILITY INSURANCE
$ 1,989.55
TOTAL
!z FINE SIGNS OF ALL KINDS
BIBNE
QUALITY, ANY QUANTITY tisA
INVOICE #1040 - Customer PO# 202-060 5/12/2016
Prepared For: Prepared By:
Western Rim Construction Co. TIM
Ray Byrom EZ SIGNS USA
1785 s. escondido blvd. #c
escondido, ca. 92025 USA
Phone: 760-489-4328 Fax: Phone: 760-755-5335
Alt. Phone: Alt. Phone: 760-445-6129
Email: rbyrom@westernrim.net Email: Tim@ersignsusa.com
Fax: 760-740-0152
Description: skate park entry sign
Due Date: 5/11/2016
Quantity Description
Each Total Taxable
2 30.00 in x 39.00 in Orajet 3551 RA
Top laminated with Oracal ORAGuard 290F
Mounted on Aluminum 0.080
146.54 $293.08
2 Custom made sign posts with powder coating (per client specs -drawing) 954.84 $1,909.68
1 Custom made sign posts with powder coating (per client specs -drawing)
971.63 $971.63 ✓
Subtotal $3,174.39
TAX $230.50
Total $3,404.89
Terms: Payment due on receipt of invoice
Page 1 / 1
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
WESTERN RIM CONSTRUCTORS
Change Orders #13 and #14
Kimball Park, El Toyon Park and Kimball Skate Park Improvements
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Orders to Western Rim Constructors