PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification No. 16-01
Contractor: Dick Miller, Inc.
CHANGE ORDER NO. 3
August 1, 2016
Reason/Purpose for this Change Order:
To accommodate the next phase of traffic control the #2 westbound lane on Plaza Blvd from Palm Avenue to N
Avenue had to be edge grind to smooth for traffic. Under direction of the Engineer the Contractor proceeded with
an edge grind on the #2 lane under time and materials.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with an edge grind on the #2 westbound
lane on Plaza Blvd from Palm Avenue to N Avenue. The agreed upon price for all costs associated with this work
is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount ... $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
1,894,498.10
15,142.20
1,909,640.30
1,036.82
$ 1,910,677.12
Working days added: 1 Working days subtracted: 0 Percent change in Contract to date 0.85%
Submitted by:
ager Date
Approved by:
Cit ngineer
Fit
te
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Dick Miller, Inc.:
'Rut— elitLeSE<::.i'd\frQl.PKACL-
D tks,./.4.k.
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
NATIONAL CM
y
INCORPORATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification # 16-01
DATE: July 7, 2016
CHANGE ORDER NO. 3
WORK PERFORMED BY: Dick Miller, Inc.
DESCRIPTION OF WORK: Grind uneven pavement #2 lane North side of Plaza Blvd.
from Palm Avenue to N Avenue
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
Hour
1.00
80.20
80.20
2)
3)
Operator
Teamster
Hour
Hour
2.00
1.00
77.60
57.77
155.20
57.77
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$ 58.63
$ 351.80
MATERIALS
Unit
Qty
Rate
Total
1)
Dump Fees
LS
1.00
140.00
140.00
Sub -Total Materials:
Sales Tax (8%):
Materials Markup (15%):
$ 140.00
$ 11.20
21.00
TOTAL MATERIALS:
72.20
EQUIPMENT
Unit
Qty
Rate
Total
1)
Bobcat w/ Grinder w/ Sweeper
Hour
3.00
43.00
129.00
2)
Sweeper attachment
Hour
3.00
35.00
105.00
3)
Utility Truck
Hour
1.00
50.00
50.00
4)
Super 10 Wheel Dump Truck
Hour
1.00
72.00
72.00
5)
Water Truck
Hour
1.00
81.00
81.00
$ 437.00
$ 65.55
$ 502.55
$ 10.27
GRAND TOTAL:
$1,036.82
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
BOND AND INSURANCE (1%):
$ 293.17
4- CALIFORNIA -4-
NATIONAL env
_. INCORPORATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification No. 16-01
Contractor: Dick Miller, Inc.
CHANGE ORDER NO. 4
August 1, 2016
Reason/Purpose for this Change Order:
At the NE corner of Palm Avenue and Plaza Blvd a Palm Tree had to be removed to accommodate the new
traffic signal equipment and sidewalk. Under direction of the Engineer the Contractor proceeded under time and
materials.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with removing the Palm Tree at the NE
Corner of Palm Avenue and Plaza Blvd. The agreed upon price for all costs associated with this work is as
stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 1,894,498.10
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
16,179.02
1,910,677.12
1,148.68
New contract amount $ 1,911,825.80
Working days added: 1 Working days subtracted: 0 Percent change in Contract to date 0.91%
Submitted by: _.__.
97/17/
Date
Approved by:
rAt-//‘
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Dick Miller, Inc..
.. i t 6 ...................
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
NATIONAL ,Ii, V
INCORPORATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805 CHANGE ORDER NO. 4
Specification #16-01
DATE: July 28, 2016
WORK PERFORMED BY: Dick Miller, Inc.
DESCRIPTION OF WORK: Remove and haul off Palm Tree at NE Corner of Palm Avenue
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
Hour
1.00
80.20
80.20
2)
Operator
Hour
2.00
77.60
155.20
3)
Teamster
Hour
2.00
57.77
115.54
4)
Laborer
Hour
2.00
57.63
115.26
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$ 93.24
$ 559.44
MATERIALS
Unit
Qty
Rate
Total
1)
Dump Fee
LS
1.00
79.00
79.00
Sub -Total Materials:
Sales Tax (8%):
Materials Markup (15%):
79.00
$ 6.32
11.85
TOTAL MATERIALS:
9
17
EQUIPMENT
Unit
Qty
Rate
Total
1)
138 Excavator
Hour
2.00
137.00
274.00
2)
Super 10 Wheel Dump Truck
Hour
2.00
72.00
144.00
Sub -Total Equipment:
Equipment Markup (15%):
$ 418.00
$ 62.70
TOTAL EQUIPMENT:
BOND AND INSURANCE (1%):
$ 480.70
$ 11.37
GRAND TOTAL:
$1,148.68
$ 466.20
off-`► oir,4f`4;
kAFFF,
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Orders #3 and #4
Plaza Blvd. Widening "N" Avenue to 1-805
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Orders to Dick Miller, Inc.