HomeMy WebLinkAbout2016 CON West Tech Contracting - Paradise Creek Restoration Project - Change Order #4 #5Paradsie Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
Reason/Purpose for this Change Order:
CHANGE ORDER NO. 4
July 12, 2016
For pedestrian safety, the City directed the contractor to furnish and install additional pedestrian crossing
signs at 16th and B and 18th and B.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to furnish and install four pedestrian crossing signs and associated posts at
16th and B and 18th and B. This work shall include 4 each W11-2's and 4 each W16-7p's with 4 break away
posts complete with the installation of the work described above for the lump sum price agreed.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders (48,976.24)
Subtotal 1,611,946.09
Amount of this change order 1,638.00
New contract amount
$ 1,613,584.09
Working days added: 0 Working,.days subtracted: 0 Percent change in Contract to date -2.85%
Sub itted by: 1 __
City Project Manager Date
. ."7/o
Cib'En sneer Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor
necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is
fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision,
overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original
contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor )
Accepted and a :
Name:
Vs-1
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your
claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
WEST -TECH
Project Name:
Job#: 2178
Description:
CONTRACTOR COST PROPOSAL SUMMARY SHEET FORM 1I
PARADISE CREEK RESTORATION
Cost Proposal / Field Order No. 906
Pedestrian Crossings Signs
NET COSTS: Attach supporting forms II, III, IV
COSTS
1. TOTAL NET COSTS (From Form III)
Labor-
$0
Material-
$0
Equipment-
$0
Other-
$0
2. Royalties, Permits, Etc.:
3. SUBTOTAL LINES 1 & 2
$0
4. MARKUP FEE: for actual work performed 15% of line 5
$0
5. TOTAL SUBCONTRACTOR PERFORMED WORK: Total Lines 3 & 4
$0
6. SUMMARY OF COSTS: Lower Tier Subcontractors (List each separately)
Statewide Stripes, Inc
$1,560
7, SUBTOTAL LINE 6: Subtotal of Lower Tier Subcontractors
$1,560
8. HANDLING FEE: Maximum 5.0% of Line 7
$78
9. SUBTOTAL SUBCONTRACTOR: Total Lines 5, 7, & 8
$1,638
Note: (1) Round -off all Costs to the nearest dollar. Costs from Labor Rate Breakdown sheet.
Statewide Stripes, Inc.
P.O. Box 600710
San Diego, CA 92160-0710
858.560.6887
858.560.0158 fax
Tax ID #33-0915254
SLBE #10SS0008
DBE #32232 MB/SB #40421
BILL TO
West -Tech Contracting Inc.
Attn: Accounts Payable
568 N. Tulip Street
Escondido, CA. 92025
760-233-2570 / 2580
CA Lie. #798286
Since 1990
INVOICE
DATE
6/17/2016
INVOICE NO.
13143
JOB ADDRESS
Paradise Creek Project# 15-05
SWS NO.
P.O. NO.
TERMS
DUE DATE
2155
Net 30
7/17/2016
PROJECT
Added Signs & Rem...
QTY
• DESCRIPTION
RATE
AMOUNT
8
Pedestrian Crossing signs mounted on four posts (Wii-2 &
195.00
1,560.00
Wi6-7P)
SUBTOTAL:
1,56o.00
RETENTION 5% WITHHELD:
-5.00%
-78.0o
We Appreciate Your Business
TOTAL
$1, 482.00
Amounts 30 days past due will accrue interest at 10% per annum.
Payments / Credits
Lf._
Balance Due
$1,482.00
—: 1 ORNIA �*
VfI AL CliTir
13 1
INCORPORATED
Paradsie Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
CHANGE ORDER NO. 5
July 12, 2016
Reason/Purpose for this Change Order:
The City directed the contractor to stripe an additional solid white line along 16th St. within project limits to
separate the lane of travel from the parking lane.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to add 812 linear feet of 8" solid white lane striping along 16th St. between
D St. and B. This work shall include the work described above for the lump sum price agreed.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders (47,338.24)
Subtotal
Amount of this change order
New contract amount
1,613,584.09
368.00
$ 1,613,952.09
Working days added: 0 Wor g days subtracted: 0 Percent change in Contract to date -2.83%
Su. ed by:
Pro' - t Man
pproved by:
Of
Date
C' Project Mena • er Date
City Engineer Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor
necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is
fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision,
overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original
contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed_;+. ractor's name
ame:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest, You must comply with the contract requirements of submitting a written protest to protect your
claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
WEST -TECH CONTRACTOR COST PROPOSAL SUMMARY SHEET FORM II
Project Name
Job # 2178
Description:
PARADISE CREEK RESTORATION
Cost Proposal / Field Order No. 907
Extra Striping on 16th Street
NET COSTS: Attach supporting forms II, III, IV
COSTS
1. TOTAL NET COSTS (From Form III)
Labor-
$0
Material-
$0
Equipment-
$0
Other-
$0
2. Royalties, Permits, Etc.:
3. SUBTOTAL LINES 1 & 2
$0
4. MARKUP FEE: for actual work performed 15% of line 5
$0
5. TOTAL SUBCONTRACTOR PERFORMED WORK: Total Lines 3 & 4
$0
6. SUMMARY OF COSTS: Lower Tier Subcontractors (List each separately)
Statement Stripes Estimate No. 15410 of 7/6/2016: 812 LF 8" Solid White Detail-38A
$350
7. SUBTOTAL LINE 6: Subtotal of Lower Tier Subcontractors
$350
8. HANDLING FEE: Maximum 5.0% of Line 7
$18
9. SUBTOTAL SUBCONTRACTOR: Total Lines 5, 7, & 8
$368
Note: (1) Round -off all Costs to the nearest dollar. Costs from Labor Rate Breakdown sheet
Statewide Stripes, Inc.
P.O. Box 600710
San Diego, CA 92160-0710
««««««««««««««««»»»»»»»»»»»»»»»»
858.560.6887
858.560.0158 fax
Tax ID #33-0915254
Class: C32
MB/SB# 40421 DBE# 32232
PW Contractors Reg# 1000001334
Customer Info
West -Tech Contracting Inc.
Attn: Accounts Payable
568 N. Tulip Street
Escondido, CA. 92025
760-233-2570 / 2580
PROJECT
REP
2155- Paradise Creek Restoration; A...
AJO
CA Lic..788286
Exp. 12/31/2016
Since 1990
ESTIMATE
DATE
7/62016
NO.
15410
QTY
DESCRIPTION
812
Ln Ft. Detail-38A 8" Solid White
Change order for Paradise Creek. Added D-38A on 16th street
TOTAL
S350.00
EXCLUDE: Adjust Cancellation Clause @ $250.00 ea Cert., Additional Insured Endorsements on Auto Liability @ $75.00 ea., bonds, notary services, night work,
prevailing wages (unless included above). Not responsible for A.D.A. Compliance. Items not specifically included are excluded and require an Additional Bid,
Acceptance of Estimate and Agreement.
The undersigned hereby contracts for the services noted above and agrees to pay for the services upon completion and receipt of an invoice. The undersigned agrees to
pay reasonable attomey's fees and costs if incurred in the enforcement of this contract.
STATEWIDE STRIPES, INC. REQUIRES TWO WEEKS ADVANCE WRITTEN NOTICE PRIOR TO SCHEDULING.
Co. Name:
By:
Date:
Signature:
(Print Name and Title)
OkATEI) A�
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
WEST -TECH CONTRACTING
Change Orders #4 and #5
Paradise Creek Restoration Project
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Orders to West -Tech Contracting