Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
CHANGE ORDER NO. 15
July27, 2016
Reason/Purpose for this Change Order.
The City Building Department required a commercial grade water heater for each of the new buildings
constructed by this project.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to purchase and install five (5) commercial grade water heaters including
necessary plumbing and electrical, one heater for each of the five (5) newly constructed buildings at Kimball
and El Toyon Parks.
Original Contract Amount $ 3,452 342 ^;!
Net change by previously authorized Change Orders 129,475.53
Amount of this change order
New contract amount $ 3,596,471.05
3,581,818.51
14,652.54
Working days added: 0 Working days subtracted: 0
S itted by:
City ixfigineer / Date�/�
City Manager, required for Change orders>$24,sss Date
Percent change in Contract to date 4.17%
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead. , bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the o . in. contra .. ments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
to by (Contractor's name':
Name:
4 Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA —
NATIONAL Cr'r'y
133'1
INCORPORATED
Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
CHANGE ORDER NO. 16
July 29, 2016
Reason/Purpose for this Change Order.
To remove and abandoned the electrical panel that powered the old zoo and to switch the circuit to feed
electrical lines to the irrigation controller and scoreboard at Kimball Park.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to remove the abondoned zoo electrical panel and foundation near the
library and to refeed the irrigation controller and scoreboard at Kimball Park from a pedestal installed with the
City's A Ave Green Street Improvements Project. All work was completed on a T&M basis.
Original Contract Amount... $ 3,452,342.98
Net change by previously authorized Change Orders ... ............... 144,128.07
Subtotal
Amount of this change order
3,596,471.05
1,468.95
New contract amount $ 3,597,940.00
Working days added: 0 Worki days subtracted: 0 Percent change in Contract to date 4.22%
Sub itt• • by:
ngineer
1 IA
Date
roject Manager
s-fr
Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervisioverhead, fees, bo. •s, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the or . contract docum : re incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
agreed ti,i• Contractor's name):
Name:
-76(11
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
�1yhL Cj�,,
r � I
', MArc', AO
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
WESTERN RIM CONSTRUCTORS
Change Orders #15 and #16
Kimball Park, El Toyon Park and Kimball Skate Park Improvements
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Orders to Western Rim Constructors