HomeMy WebLinkAbout2016 CON Dick Miller Inc - Plaza Blvd and 14th Street Improvements Project CIP 15-10 - Change Order #3CALIFORNIA
NATIONAL
J CITY(
INCOR#'O1
Plaza Blvd. and 14th St. Improvements
CIP No: 15-10
Contractor: Dick Miller Inc.
CHANGE ORDER NO. 3
August 25, 2016
Reason/Purpose for this Change Order:
To remove and replace additional sidewalk at the Granger Avenue Speed Table for ADA compliance, and for
additional dump fees associated with petro mat fabric not identified on the plans
The City of National City and Contractor agree to the following change to the original Contract:
The contractor shall remove and replace an additional 486 SF of concrete sidewalk at the Granger Avenue
Speed Table on both the east and west side of the improvements, as directed. The contractor also
encountered petro mat fabric in the existing asphalt removed. This material is considered hard to handle by
the recycling plant and requires a premium dump fee to be paid. All work and related costs shall be included
in the lump sum amount, below.
Original Contract Amount $ 1,276,903.10
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
220,615.00
1,497,518.10
5,761.08
$ 1,503,279.18
Percent change in Contract to date 17.73%
Subm td by:
r
Proje t Manag
8.//��
/24
Date
City Project Manager
Date
roved by:
rho.*
Cit ngineer Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor
necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is
fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision,
overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original
contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Date
Note to Contractor: If you do not agree with the Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your
claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
.�,
per...►
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228 phone / 619-336-4229 fax
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Order #3
Plaza Blvd. and 14th Street Improvements Project
Judy Hernandez (Engineering/PW) Forwarded
Copy of Change Order to Dick Miller, Inc.