HomeMy WebLinkAbout2016 CON West Tech Contracting - Paradise Creek Restoration Project - Change Order #6Paradise Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
CHANGE ORDER NO. 6
September 23, 2016
Reason/Purpose for this Change Order:
Core concrete footings to replace existing rusted foundations bolts during bridge refurbishment.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor encountered rusted anchor bolts when removing the pedestrian bridge across Paradise Creek.
In order to make sure the bridge was secured correctly the city directed the contractor to drill out the existing
rusted foundation bolts and replace them with new bolts during the bridge removal, refurbishment and
replacement.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
(46,970.24)
1,613,952.09
2,760.00
New contract amount $ 1,616,712.09
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date -2.66%
Sub � ed by:
jectMa.-•er
A, proved by:
Cit ngineer
Date/ 2//6.
City ProjectManager
Mana er
Date
Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted - • • . •re= • to b Con - • ' • -
Name:
ick
Date 9/29/2016
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
Owner's Reference Number:
Work Performed for:
WirgTr= TEM
o ri t r a. c t i n g, I n c
CHANGE ORDER PROPOSAL FORM
2178-806
National City - Paradise Creek Restoration
6/15/2016
Description of Work:
Core Drilling Required Due to Bent lnbeds in Bridge Footing
HRLY
XTNDED
MATERIAL & SPECIALTY ITEMS
HRLY
XTNDED
EQUIPMENT
HRS
RATE
AMOUNT
DESCRIPTION
UNITS
COST
EXT
LABOR
HRS
RATE
AMOUNT
6/27/2016
Casper Core Drilling
1
$ 845.00
$ 845.00
Penhall Core Drilling
1
$ 875.00
$ 875.00
Equipment Manager
1Russ Bennett)
8
$ 85.00
$ 680.00
SUBTOTAL
$6.00
SUBTOTAL
$2,400ar0
SUBTOTAL
$0.00.
TOTAL COST OF EQUIP & MATERIALS
$2,400.00
Lbr Surcharge 0% [0%-OT]
$0.09
TOTAL COST OF LABOR
A
$0.00
SUBCONTRACTOR
NO.
COST
EXT
TOTAL EQUIP, MATERIALS, SPECIALTY
B
$2,400.00
$0.00
TOTAL SUBCONTRACTOR
C
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
% ON LABOR 20%
(A)
$0.00
TOTAL COST OF SUBCONTRACTOR
% EQ, MATLS, SPECIALTY 15%
(B)
$360.00
Rented Equip & Material Prices Snbj to Change per Final Billing from Supplier
% ON SUBS 5%
(C)
$0.00
CONTRACTOR'S RF:PRESENTnTwF.
RESIDENT ENGINEER
TOTAL THIS REPORT
$2,760.00
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WEST -TECH CONTRACTING
Change Order #6
Paradise Creek Restoration
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Order to West -Tech Contracting