Kimball, El Toyon and Kimball Skate Park Improvements
CIP No: 15-04
Contractor: Western Rim Constructors, Inc.
Reason/Purpose for this Change Order:
To improve the pedestrian ADA path of travel by installing an ADA-Compliant
at El Toyon Park between the main park and field parking lot.
CHANGE ORDER NO. 23
September 22, 2016
pedestrian crossing/speed table
The City of National City and Contractor agree to the following change to the original Contract:
The contractor will field design, layout and install an ADA-compliant speed table/pedestrian crossing on U
Ave, between El Toyon main park and El Toyon field parking lot eight feet in width with three foot wings,
tactile, domes, clean out grate and all necessary signage and striping. This work also includes widening the
existing parking lot driveway, connecting sidewalk from the restroom building and the crossing and modifying
the existing sidewalk landing as needed.
Original Contract Amount $ 3,452,342.98
Net change by previously authorized Change Orders 217,575.25
Subtotal 3,669,918.23
Amount of this change order 35,829.00
New contract amount $ 3,705,747.23
Working days added: 5 Working days subtracted: 0
Submitted by:
Project Manager
Approved by:
7
City'Engineer
Date
Percent change in Contract to date 7.34%
City Project Manager Date
/od(r/� to%a-)hz.,.
Date City Manager required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the origfNI contract do > ments are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
ceptci d agre o by (Contractor's name):
Name:
i L [
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WESTERN RIM CONSTRUCTORS
Change Order #23
Kimball Park, El Toyon Park and Kimball Skate Park Improvements
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Order to Western Rim Constructors