PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification No. 16-01
Contractor: Dick Miller, Inc.
CHANGE ORDER NO. 8
September 26, 2016
Reason/Purpose for this Change Order:
Additional traffic control, signing and striping was required to accommodate two lanes in the west bound direction
from 1-805 to N Avenue (Stage 2 per Dokken Revised Plan). Under direction of the Engineer the Contractor is to
proceed with additional signing and striping from N Avenue to 1-805.
[The City of National City and Contractor agree to the following change to the original Contract:
;The City and the Contractor agree that the Contractor shall proceed with additional signing and striping from I-
1805 to N Avenue. The agreed upon price for all costs associated with this work is as stated on this Change
Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 1,894,498.10
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
Submitted by:
40,947.06
1,935,445.16
2,464.80
$ 1,937,909.96
Percent change in Contract to date 2.29%
Date CitManager,required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Dick Miller, Inc.:
erne: P• u NALryc.v.(PRO-Sear MAr., o.C,ESZ Date teir ire
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
-- CALIFORNIA_
INCORPORATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification # 16-01
DATE: September 6, 2016
CHANGE ORDER NO. 8
WORK PERFORMED BY: Dick Miller, Inc.
DESCRIPTION OF WORK: Revised Traffic Control Plan (Stage 2)
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
N/A
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$
MATERIALS
Unit
Qty
Rate
Total
1)
Additional Traffic Control Signs
EA
5.00
31.50
157.50
2)
Additional Plastic K-Rail - 2 Each
($108/EA/MO)
EA
2.00
216.00
432.00
Sub -Total Materials:
Sales Tax (8%):
Materials Markup (15%):
TOTAL MATERIALS:
$ 589.50
$ 47.16
$ 88.43
$ 725.09
EQUIPMENT
Unit
Qty
Rate
Total
1) Arrow Board, trailer mounted
MO
2.00
480.00
960.00
Sub -Total Equipment: $ 960.00
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 144.00
1,104.00
SUBCONTRACTOR
Unit
Qty
Rate
Total
1)
Invoice for actual stage 2 Traffic
Control
LS
1.00
8,857.20
8,857.20
2)
Quote for plan stage 2 Traffic
Control
LS
1.00
(8,275.00)
(8,275.00)
Sub -total Subcontractor:
Prime Contractor Markup (5%):
TOTAL SUBCONTRACTOR:
BOND AND INSURANCE (1%):
$ 582.20
$ 29.11
$ 611.31
$ 24.40
GRAND TOTAL:
$2,464.80
Statewide Stripes, Inc.
P.O. Box 600710
San Diego, CA 92160-0710
««««««««««c«««««»»»»»»»»»»»»»»»»
858.560.6887
858.560.0158 fax
Tax ID #33-0915254
Class: C32
MB/SB# 40421 DBE# 32232
PW Contractor Reg# 1000001334
CA Lie. #788286
ESTIMATE
DATE
9/1/2016
NO.
15568
Customer Info
Exp: 12/31/2016
Since
1990
Dick Miller, Inc.
930 Boardwalk, Ste. H
San Marcos, CA 92078
760.471.6842 x471.6178
PROJECT
REP
SWS NO.
Stage II traffic control 9/1/16
BB
QTY
DESCRIPTION
COST
TOTAL
2,300
Ln. Ft. Detail-27B 4" Right Edgeline
0.39
897.00
1,780
Ln. Ft. Detail-8 Skip Line Stripe .� w° _,
0.35
623.00
800
Ln. Ft. Double Yellow
0.54
432.00
1,180
Ln. Ft. Double Yellow Island No Reflectors
0.54
637.20
800
Detail-38A 8" Solid White
0.54
432.00
1
Black Out Stage I Striping v
1,200.00
1,200.00
85
R & R Yellow Delineators (portable and glue down class 1)
38.00
3,230.00
37
R & R White Delineators (portable and glue down class 1)
38.00
1,406.00
TOTAL
$8,857.20
EXCLUDES: Prepatory work,Waiver of Subrogation on Worker's Comp per party/policy @ $150.00 ea., Additional Insured Endorsements on Auto
Liability @ $75.00 ea., mast arm signs, electrical or FLASHING BEACON SIGNS, bonds, notary, night work, prevailing wages (unless included
above). Not responsible for A.D.A. compliance. Items not specifically included are excluded and require an additional bid. STATEWIDE STRIPES
INC. REQUIRES TWO WEEKS WRITTEN NOTICE
PRIOR TO SCHEDULING.
Acceptance of Estimate and Agreement
The undersigned hereby contracts for the services noted above and agrees to pay for the services upon completion and receipt of an invoice. The
undersigned agrees to pay reasonable attorneys' fees and costs if incurred in the enforcement of this contract.
Co. Name:
Date:
By: Signature:
(Print Name anti Title)
Statewide Stripes, Inc.
P.O. Box 600710
San Diego, CA 92160-0710
858.560.6887
858.560.0158 fax
Tax ID #33-0915254
Class: C32
MB/SB# 40421 DBE# 32232
PW Contractor Reg# 1000001334
CA Lic. #788286
ESTIMATE
DATE
1/12/2016
NO.
14915
Customer Info
Ex!): 12/31/2016
Since 1990
ESTIMATING DEPARTMENT
PROJECT
REP
SWS NO.
Plaza Blvd Widen 1/12/16
BB
QTY
DESCRIPTION
COST
TOTAL
1
1
Bid Item 2 Striping Portion of Traffic Control (Install Stage II
Striping Only)
Bid Item 45 Striping,Markings and Signs Base Bid
Optional Additional: Remove Stage II Striping and install Final
striping configuration in temporary paint for stage III @ $7,965.00
Includes: Items as listed, Prevailing Wages, Traffic control for our
operations and Waterblasting per specs. ,
Excludes: Traffic Control plans, Permits and "Mast Arm" Signs
8,275.00
8,275.00
TOTAL
EXCLUDES: Prepatory work,Waiver of Subrogation on Worker's Comp per party/policy @ $150.00 ea., Additional Insured Endorsements on Auto
Liability @ $75.00 ea., mast arm signs, electrical or FLASHING BEACON SIGNS, bonds, notary, night work, prevailing wages (unless included
above). Not responsible for A.D.A. compliance. Items not specifically included are excluded and require an additional bid. STATEWIDE STRIPES
INC. REQUIRES TWO WEEKS WRITTEN NOTICE
PRIOR TO SCHEDULING.
Acceptance of Estimate and Agreement
The undersigned hereby contracts for the services noted above and agrees to pay for the services upon completion and receipt of an invoice. The
undersigned agrees to pay reasonable attorneys' fees and costs if incurred in the enforcement of this contract.
Co. Name:
Date:
By: Signature:
(Print Name and Titlel
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Order #8
Plaza Blvd. Widening "N" Avenue to 1-805
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Order to Dick Miller, Inc.