Paradise Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
Reason/Purpose for this Change Order:
Repair irrigation wires and install additional controller needed for Paradise Creek landscape.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to test and tone existingirrigation valve wires found on the Paradise Creek
project and tie those wires into the existing system wires aliowi g them to function with the newly installed
irriagation system at Paradise Creek. The contractor will also install a used irrigation controller supplied by the
city to facilitate the additional valves. The additional work was tracked on a T&M basis.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders 445.80
Subtotal 1,661,368.13
5,598.89
Amount of this change order
New contract amount $ 1,666,967.02
Working days added: 0
Submit - • bv-
days subtracted: 0
Date
-Z/Z4
(City ngineer / Date
Percent change in Contract to date 0.36%
Ci Pro ctIM'anager
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract do are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Acce • te r. _ to-bylContrac aria0
Na
CHANGE ORDER NO. 15
February 17, 2017
Date 2/17/20]
Note to Contractor: If you do not agree with tange Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
7
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA —
NATIOtNAL CITY
INCORPOR ATV)
Paradise Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
Reason/Purpose for this Change Order:
Disposal of additional asbestos pipe found during excavation of retention basin.
CHANGE ORDER NO. 16
February 17, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to propoerly handle and dispose of additional asbestos pipe found during
the excavation of the large basin. This work shall include all labor, materials and equipment necessary to
complete the disposal described above for the lump sum price agreed.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders 6,044.69
Subtotal
Amount of this change order
1,666,967.02
900.38
New contract amount
$ 1,667,867.40
Working days added: 0
Sub ;• by:
Manager
Approved by:
Working days subtracted: 0
Percent change in Contract to date 0.42%
3/7—/;
Date ('' o•
,s,(245
City Engineer Date City Manager, required for Change Orders 424,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents at costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents - «= porated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and =ed to;, Contrac
Name: Rick Engebretsen
Date 2/17/2017
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WEST -TECH CONTRACTING
Change Order #15 and #16
Paradise Creek Restoration
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Orders to West -Tech Contracting