HomeMy WebLinkAbout2016 CON West Tech Contracting - Paradise Creek Restoration Project - Change Order #14CALIFORNIA
Working days subtracted: 0
Percent change in Contract to date 0.03%
NATIONAL CITY
INCORPORATED
Paradise Creek Restoration
CIP No: 15-05
Contractor: West -Tech Contracting, Inc.
CHANGE ORDER NO. 14
November 17, 2016
Reason/Purpose for this Change Order:
Modify the diagonal parking stalls on the north side of 16th between B St. and National City Blvd.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to water blast off the existing diagonal parking stalls on the north side of
16th between B St. and National City Blvd., apply Guardtop selant to blend with the existing Type II slurry and
restripe a reverse angle parking stall with the same quantity currently striped. If additional traffic control is
required the contractor will be paid on a T&M basis for traffic control. All work excluding traffic control will be
compelted for the lump sum price [sit below.
Original Contract Amount $ 1,660,922.33
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
(3,460.20)
1,657,462.13
3,906.00
New contract amount .. $ 1,661,368.13
Working days added: 10
Sub ' d by:
Approved by:
Cit ngineer a Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are -incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed y (Contract
NaccEngebre Date 2/17/20:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
7
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WEST -TECH CONTRACTING
Change Order #14
Paradise Creek Restoration
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Order to West -Tech Contracting