HomeMy WebLinkAbout2017 CON Palm Engineering - Division Street Traffic Calming - Change Order #1 and #2NATION
`- 'NCORPOIiATED
Division St. Traffic Calming Project
CIP No: 16-09
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 1
April 28, 2017
Reason/Purpose for this Change Order
Delete all contract work related to MTS bus pads as MTS is discontinuing their route on Division St.
The City of National City and Contractor agree to the following change to the original Contract:
Delete contract bid items 30-Gravity Wall, 31-Bus Pads, and 32-Bus Pad Concrete Treated Base. MTS
notified National City of the deletion of the bus route along Division St. Therefore the bus pad locations shall
be deleted from the contract work.
Original Contract Amount $ 983,756.49
Net change by previously authorized Change Orders
983,756.49
Amount of this change order (66,440.00)
New contract amount .
Working days added: 0
Subtotal
g days subtracted: 0
$ 917,316.49
Percent change in Contract to date -6.75%
rSub
ed by:
Proje t Manager
Date
City Project Manager
Date
Appr ved by:
42.............thh
er Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Name:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
1243 National City Boulevard, National City, CA 91950
cc: Engineering project file, Project Manager
C,2af6-S9
Telephone (619) 336-4380
• CALIFORNIA
NATIONAL ally
133 J -�-
INCORPORATED
Division St. Traffic Calming Project
CIP No: 16-09
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 2
April 28, 2017
Reason/Purpose for this Change Order:
Add additional ADA ramps to contract work to meet ADA compliance.
The City of National City and Contractor agree to the following change to the original Contract:
Add 4 additional ADA ramps per the contract bid items as follows: Add three additional Type A ramps at the
contract unit price of $3,000.00 each, delete one Type B ramp at a contract unit price of $3,000.00 each, add
one additional Type C ramps at an agreed to price of $6,000 due to additional removal limits and expanded
scope, and add one additional Type D ramp at the contract unit price of $2,200.00 each. All work is
performed and adjusted per the contract unit prices agreed to in the bid proposal or the agreed to price.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
$ 983,756.49
(66,440.00)
917,316.49
14,200.00
$ 931,516.49
Percent change in Contract to date -5.31%
Su ted by:
Proj ct Ma
er
Date
City Project Manager
Date
pproved by:
Cit n ineer
/
l. i ?
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there wit be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepte and agreed to by (Contractor's name):
Name:
.5 /.2 /r -7
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
C 2a/' s9
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380