HomeMy WebLinkAboutAce Electric Inc. - El Toyon and Las Palmas Park Lighting Improvements Project - Change Order No.1Working days subtracted: 0
Percent change in Contract to dote 0.74%
717,822.46
CALIFORNIA
lost rIi Cfr
m coit PoRAT"
EL TOYON/LAS PALMAS LIGHTING IMPROVEMENTS
CIP NO. 17-01
Contractor: ACE Electric, Inc.
Reason/Purpose for this Change Order:
Due to the time constraint and schedule of the project, the City requested that the Musco Plugs required for the
light poles that will be installed in the Las Palmas Park to be expedited. This change order includes the
expedition of the ordering, delivery, and installation of the Musco plugs.
CHANGE ORDER NO. 1
May 1,2017
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall provide and procure the Musco Plugs required for the
light poles that will be installed at Las Palmas Park site. The Contractor shall have a target delivery date of
5/22/17 for the product and shall install the product per plans/engineer. The agreed upon price for all cost
associated with this work is a total of $5,253.00.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal .
Amount of this change order
712,569.00
712,569.00
5,253.46
New contract amount $
Working days added: 0
Submitte(1 by:
City ngineer Date City Manager, required (or Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is con pletety familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepte id agree o b ACE tric,rvinc
5--/31)?-.
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
+ CALIFORNIA —_
NATIONAL C r r
INCORPORATED
EL TOYON/LAS PALMAS LIGHTING IMPROVEMENTS
CIP NO. 17-08
DATE: May 1, 2017
CHANGE ORDER NO. 1
WORK PERFORMED BY: ACE Electric, Inc.
Expedited procurement and installation of Musco Plugs at Las
DESCRIPTION OF WORK: Palmas Park
MATERIALS
1)
2)
Musco Plug Material
Sales Tax (8.75%)
Unit
LS
EA
Qty
1.00
1.00
Rate
4,200.00
368.23
Total
4,200.00
368.23
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 4,568.23
$ 685.23
SUB TOTAL:
GRAND TOTAL:
$5,253.46
5/1 /2017 9:44:16 AM
Ace Electric, Inc.
Las Palmas El Toyon Community Parks 1878 CO
Totals (Summary) - Bid Summary: Default
Material
Non -Quoted
Quotes
Sales Tax (8.75%)
Total Material
Labor
Direct (0.01 hours @ $72.86)
Non -Productive Labor
Total Labor (0.01 hours)
Direct Job Expenses
Tools and Miscellaneous Materials
Subcontracts
Job Subtotal (Prime Cost)
Overhead (15.00%)
Profit (0.00%)
Job Total
Actual Bid Price
Page 1
$4,200.00
0.00
367.50
$4,567.50
$0.73
0.00
$0.73
$0.00
0.00
0.00
$4,568.23
685.23
0.00
$5,253.46
$5,253.00