HomeMy WebLinkAbout2017 CON Portillo Concrete - Sewer Line Replacement Upsizing CIP 16-05 - Change Order #6+}- CALIFORNIA - NA IONAL CI V 1CM INCORPORATED — Jl Sewer Line Replacement and Upsizing (Phase I) CIP NO. 16-05 Contractor: Portillo Concrete, Inc. CHANGE ORDER NO. 6 May 31, 2017 Reason/Purpose for this Change Order: During construction of the National City Blvd. portion of the work, it was determined that the crosswalk limit lines needed to be installed at 12 inches wide to conform to MUTCD however, the plans called for replacement in kind which was 8 inches. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with the work described above and particularly described in PCO 21, see attachment for cost breakdown. Original Contract Amount $ 2,496,925.00 Net change by previously authorized Change Orders Subtotal Amount of this change order 88,489.11 New contract amount $ Working days add: 0 g Working days subtracted: 0 Percent change in Contract to date 3.66% ubmit Project Manager Date 2,585,414.11 2,989.99 2,588,404.1 5/31/n Approved by: 2 Cit ngineer 4-/e///7 Date City Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepjd and agPortillo Concrete, Inc.: Name: 'aeiI tUrf-To Date S/.3// 1 `7 Note to Contractor: If yo do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA NATIONAL Citry j ao e INCORPORATED Sewer Line Replacement and Upsizing Project (Phase I) CIP NO. 16-05 DATE: May 31, 2017 CHANGE ORDER NO. 6 WORK PERFORMED BY: Portillo Concrete, Inc. DESCRIPTION OF WORK: Striping at 24th and National City Blvd. ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT 1) Limit line stripe at 12" wide $ 2,989.99 TOTAL: $ 2,989.99 PORTILLO CONCRETE, INC. 3527CITRUS ST LEMON GROVE, CA. 91945 OFFICE (619) 466-4639 FAX (619) 466-4685 # Equipment Hours Rate Extension Crew truck $27.33 $0.00 T.C. Truck $27.33 $0.00 Ten Wheeler $45.00 $0.00 Bobtail $40.00 $0.00 2.5 Ton Lumber Trk $25.00 $0.00 Saw Truck $50.00 $0.00 Bobcat & Attachments $50.00 $0.00 Kawasaki 65Z Loader $84.06 $0.00 #90 pound jackhammer $50.00 $0.00 Light Plants $22.00 $0.00 Equipment Move $400.00 $0.00 Excavator 135 $85.00 $0.00 Excavator 75 $50.00 $0.00 Date 5/24/2017 Job Name SEWER LINE REPLACEMENT AND UPSIZING PROJECT (PHASE 1) Job # 16-16 T/M # 20 By Mario Portillo SCOPE OF WORK: Return 8" Line - $2,281.40 Credit Restocking fee - 25% - $1,047.75 Purchase 12" Thermo - $3,833.65 Materials Qty. Unit Price Extension Concrete - Robertsons (short Load) CY $0.00 Robertsons Plant Opening EA $0.00 Rock -Vulcan TN $0.00 24" Pipe - Furgeson LF $0.00 Misc. shoring LS $0.00 Coupling EA $0.00 Subcontractors Rats Trucking (1 Equip move) HR PRSI / Lindys SF Pacific Oil Spreading SF Urbinas Sweeping HR Statewide Stripes LS 1 $0.00 $0.00 $0.00 $0.00 $2,600.00 $2,600.00 Labor Hours Rate Extension Total Prime Labor Cost $0.00 Superintendent $80.00 $0.00 Labor Mark-up 20% $0.00 Foreman - Reg $88.50 $0.00 Total Prime Equip. Cost $0.00 Cement Mason - Reg $45.55 $0.00 Equipt Mark-up 15% $0.00 Cement Mason - OT $58.20 $0.00 Total Prime Mat. Cost $0.00 Laborer - Pipelayer $63.50 $0.00 Material Mark-up 15% $0.00 Laborer - Reg $63.50 $0.00 Total Sub -Contractor Cost $2,600.00 Carpenters - Reg $63.50 $0.00 Sub Contractors Mark-up 5% $260.00 Operator - Roller $88.50 $0.00 Sub Total $2,860.00 Operator - Bobcat $88.50 $0.00 Office Overhead 3% $85.80 Operator - Excav $88.50 $0.00 Total $2,945.80 Operator - Loader $88.50 $0.00 Bond 1.5% $44.19 PROJECT / ITEM TOTAL $2,989.99