HomeMy WebLinkAboutA Good Sign and Graphics CO - Wayfinding Signage Project CIP No. 16-03 - Change Order Nos. 1-2G.)t1,1 ARNiA -+1-
,A;TIONAL arr
COHPO T8
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
CHANGE ORDER NO. 1
June 15, 2017
Reason/Purpose for this Change Order:
The City of National City requested for the installation of an additional forty (40) banners for the "Together We
Can" program. This change order only accounts for the installation and hardware costs for the additional
banners. Material costs for the actual banners were included in the original bid.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the installation of additional 'Together
We Can" banner signs. This change order only includes cost for the installation, hardware, and appurtenances
for the banners. The agreed upon price for all cost associated with theis work is a total of $16,441.03
Original Contract Amount...
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
Newcontract amount....................................................................................... $ 286,800.03
$
270,359.00
•3 Working days subtracted: 0 Percent change in Contract to date 6.08%
270,359.00
16,441.03
Su itte b :
_—}
Proager
j g
-7 (220( 7
Date
Approved by:
.
City ngineer
%../�.A.1/ 7
Date
City Manager, required for Change orders>s24.s99
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fa negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price Is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to byA food Sign, Inc.:
7// =-/-0r 7
Name:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Date
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA
NA'! IONI r1L CIIT
INCORPORATED
WAYFINDING SIGNAGE PROJECT
CIP NO. 17-01
DATE: June 15,2017
CHANGE ORDER NO. 1
WORK PERFORMED BY: A Good Sign, Inc.
DESCRIPTION OF WORK: Additional installation and hardware for 40 banners
1) Sign Installer
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
HRS
Qty
32.00
Wage
84.35
Total
2,699.20
2) Truck Driver/Operator
HRS
16.00
84.35
1,349.60
Sub -Total Labor:
Labor Markup (15%):
TOTAL LABOR:
$ 607.32
$ 4,656.12
Unit
Qty
Rate
Total
1) Single Pole Hardware
EA
38.00
116.25
4,417.50
2) Double Pole Hardware
EA
2.00
108.50
217.00
$ 4,634.50
$ 695.18
EQUIPMENT
Unit
Qty
Rate
Total
1)
Traffic Control Truck
EA
2.00
1,395.00
2,790.00
2)
Lift Van
EA
2.00
1,350.00
Sub -Total Equipment:
2,700.00
$ 5,490.00
Equipment Markup (15%): 823.50
TOTAL EQUIPMENT: �®
Bonding (1%)
$ 141.73
GRAND TOTAL:
$16,441.03
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 4,048.80
A GOOD SIGN & GRAPHICS CO
COR#01
Job Name: National City Wayfinding
Job Number. 1221
Full Description of Change in Sco
Date: May 17, 2017
Time Impact: 3 days
RFI:
Additional cost to Install 40 banners and include the Hardware
Breakdown
Direct Labor
Sign Type
Sign Detail
Hours Rate Cost
Banners
Install cost(2 guys 2 days) 1 guy driving and 1
guy in bucket
32.00
$84.35
$2,694.20
banners
install cost (1 guy 2 day) 1 guy in the follow
behind truck
16.00
$84.35
$1,349.60
SUBTOTALS
48.0
$4,048.80
Breakdown
Direct Materials
Sign Type
Sign Detail
Quantity
Rate
Cost
Banners
Pole Hardware Single Pole
38.00
S116.25
$4,417.50
Banners
Pole Hardware Double Pole
2.00
$108.50
$217.00
SUBTOTALS
40.0
$
$4,634.50
Breakdown
Direct Equipment
Sign Type
Sign Detail
Qty
Rate
Cost
Banners
Traffic Control Truck
200
$1,395.00
$2,790.00
Banners
Lift Van
2.00
$1,350.00
$2,700.00
SUBTOTALS
4.0
$5,490.00
Breakdown
Other
Sign Type
Sign Detail
Quantity
Rate
Cost
SUBTOTALS
$0.00
*Combined Subtotal:
$14,173.30
15% Markup:
$2,126.00
Combined Subtotal + Markup:
$16,299.30
(Including GC & First Tier Sub cost) Bond 1% (of *Subtotal):
$141.73
SUB. CON - NAME/TITLE
DATE
CALIFORNIA •—e-
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
Reason/Purpose for this Change Order:
Fourteen (14) National City map panels are proposed to be installed throughout the downtown and Kimball Park
areas of the city. According to the Contractor, these map panels will have an estimated procurement time of 8-10
weeks. The contractor received final proofs for the map panels on June 5, 2017 (41 days after the Notice to
Proceed was provided) due to design and content modifications. The Contractor will require additional days in
order to have the maps fabricated.
NATIONAL env
Il°c INCORPORATTD
CHANGE ORDER NO. 2
August 10, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the fabrication and installation of
wayfinding signs provided with the time extension noted by this change order at no cost to the City. Forty-one
(41) working days shall be added after the original completion date as desginated by the Notice to Proceed. The
new completion date of the project is October 3, 2017. The agreed upon price for all cost associated with the
additional working days is $0.00.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
270,359.00
16,441.03
286,800.03
New contract amount $ 286,800.03
Working days added: 41 Working days subtracted: 0 Percent change in Contract to date 6.08%
Approved by:
0.10 • Z017
Date
Cit�r ngineer
Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to byA Good Sign, Inc.:
Name:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Date
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
A GOOD SIGN & GRAPHICS CO
COR#02
Job Name: National City Wayfinding
Job Number. 1221
Date: August 1, 2017
ASI #: Phone Discussion
Time Impact 41 days per contract
Full Description of Change in Scope:
Additional Days at no cost added to contract for getting an approval later than expected
A. 'royal was .iven on Monda June 5th at 2:12 PM pending a actual digital print before
Breakdown Direct Labor
Sign Detail Hours Rate
Sign Type
All sigm types Additional days at no cost
$OAO
Breakdown
Sign Type
SUBTOTALS 0.0 $0.00
SUBTOTALS
0.0
Cost
$0.00
Breakdown
Sign Type
Sign Detail
Qty
Direct squi • ment
Rite
Cost
SUBTOTALS 0.0
$0.00
Breakdown
WIC
Other
(Including GC & First Tier Sub cost)
SUB. CON - NAME/TITLE
SUBTOTALS
*Combined Subtotal:
15% Markup:
Combined Subtotal + Markup:
Bond 1% (of *Subtotal):
GRAND TOTAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Wayfinding Signage Projects, CIP No. 16-03
ITEMS DELIVERED:
Change Order No.2
Delivered .y: ..'''l�tt��3_ ��__�,,� o Pro ect Professionals Corporation
Received by:
Date: 7