Paradise Creek Education Park
CIP NO. 16-08
Contractor: C.S.Legacy
CHANGE ORDER NO. 5
June 15, 2017
Reason/Purpose for this Change Order:
Per the City's request, the trail along the creek extending to 22nd Street will not be constructed. This change
order reduces the quanitites of bender board from 2447 LF to 353 LF and stabilized decomposed granite by 70
tons. However, a quantity in the bid schedule was mis-stated by 23 tons of stabilized DG. Item 22 included 100
tons, item 23 included 25 tons and there was 23 tons missing from the garden area. A total of 148 tons should
have been included in the bid schedule. Therefore, the new adjusted line items for stabilized DG is 148 tons
minus 70 tons equaling 78 tons to be paid. In addition, the contractor was not able to procure some plant
materials in the sizes called for in the plans. A cost credit was accepted for smaller plants.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the line items will be reduced according to the quantites determined by
the designer.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
612,243.00
53,969.14
Percent change in Contract to date 4.38%
666,212.14
(27,156.77)
639,055.37
Submittedb : --"'; %
(0 /SI17
Date
J/M/17
�...: :.
P t Manager
Approved by:
n ineerDate>
gCity
7(4 -7427L.
Manager, required for Change Orders s2a,sss
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by C.S. Legacy:
Name: Date/)
Note to Contractor: If you do hot agree 'th this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
1 l /
CALIFORNIA
NATIONAL airy
ar(5NCORPORATED
Paradise Creek Education Park CHANGE ORDER NO. 5
CIP NO. 16-08
DATE: June 15, 2017
WORK PERFORMED BY: C.S. Legacy
DESCRIPTION OF WORK: Removal of trail, reduce plant material sizes
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
MATERIALS
Unit
Qty
Rate
TOTAL
1)
2)
3)
Line item 11 bender board,
reduce from 2447 LF to 353 LF
Line item 22 stabilized DG,
increase by 23 tons, subtract 70
tons (net reduction of 47 tons)
Reduce payment for plants due
to reduction of sizes
LF
TON
LS
2,094.00
(47.00)
1.00
8.00
68.00
205.25
Sub -Total Material:
(16,752.00)
(5,823.52)
(205.25)
$ (22,780.77)
TOTAL MATERIALS:
CREDIT
Unit
Qty
Rate
TOTAL
4)
Line item #11 reduced from
2,447 LF to 353 LF; 900 LF was
paid with invoice #5. 547 LF
was over paid.
LF
547.00
8.00
Sub -Total Credit:
(4,376.00)
$ (22,780.77)
TOTAL CREDIT:
$ (4,376.00)
GRAND TOTAL:
$(27,156.77)