Loading...
HomeMy WebLinkAbout2017 CON Dick Miller Inc - Plaza Blvd Widening - "N" Ave to I-805 SP 16-01 - Change Order #34 through #41„,, CALIFORNIA NATIONAL CITY INCORPORATED PLAZA BLVD WIDENING "N” AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. Reason/Purpose for this Change Order: Additional cross gutter at N Avenue and Starbucks frontage (sidewalk, curb/gutter, driveway, pedestrian ramp, base and asphalt) were billed per line item. Lump sump items such as traffic control, clearing and grubbing, excavation and grading proceeded under time and materials. Under direction of the Engineer the Contractor proceeded under time and materials with the additional cross gutter at N Avenue and Starbucks frontage. CHANGE ORDER NO. 34 May 25, 2017 The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with the additional cross gutter at N Avenue and the Starbucks frontage. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachment "A" for cost breakdown. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders Subtotal Amount of this change order 99,975.68 1,994,473.78 5,148.78 New contract amount $ 1,999,622.56 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 5.55% !Submitted by: 8 /W(1- Date Approved by: ngineer / ___._.._. Date Cit Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and agreed o by Dick Miller, Inc.: g /21 1(7 me: Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City BOTilevaffiT National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA N ONAL INCORPORATED ` JJJI PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification #16-01 CHANGE ORDER NO. 34 DATE: March 27, 2017 WORK PERFORMED BY: Dick Miller, Inc. DESCRIPTION OF WORK: Traffic Control, demolition, haul off and excavate for subgrade and 34A prep for crossgutter at N Ave and starbucks frontage ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) Foreman Hour 8.00 80.20 641.60 2) Laborer Hour 8.00 75.49 603.92 3) Teamster Hour 6.00 57.77 346.62 Dump Fees - Demolition 2) Dump Fees- Excavation LS EA 1.00 3.00 225.00 48.00 $ 1,592.14 225.00 144.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): $ 369.00 29.52 59.78 TOTAL MATERIALS: EQUIPMENT Unit Qty Rate Total 1) U55 Mini Excavator Hour 4.00 95.00 380.00 2) 3) U55 Mini Excavator (Idle) S530 Bobcat Hour 4.00 Hour 3.00 19.95 30.00 79.80 90.00 4) S530 Bobcat (Idle) Hour 5.00 4.20 21.00 5) Miskasa Mini Roller Hour 1.00 40.00 40.00 6) 7) 8) Miskasa Mini Roller (Idle) Traffic Control Crew Truck Chevy 3500 Hour 7.00 LS 1.00 Hour 8.00 7.60 300.00 50.00 53.20 300.00 400.00 9) 10) Super 10 Wheel Dump Truck Super 10 Wheel Dump Truck Hour 8.00 Hour 6.00 72.07 72.07 576.56 432.42 $ 2,372.98 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: SUBTOTAL: BOND AND INSURANCE (1%): $ 355.95 $ 2,728.93 $ 5,097.80 $ 50.98 GRAND TOTAL: $5,148.78 Sub -Total Labor: Labor Markup (20%): $ 318.43 TOTAL LABOR: . EA. 4,0 SUPERIOR READY MIX CONCRETE, L.P. 1508 W. MISSION RD. * ESCONDIDO, CA 92029 PHONE: (760) 745.0556' FAX: (760) 740-9557 DICK MILLER INC 930 BOARDWALK SUITE H SAN MARCOS, CA 92078 r) INVOICE MILLE005 03/27/2017 855838 1 TERMS: NET 00 DAYS A FINANCE CHARGE WILL BE IMPOSED ON PAST DUE ACCOUNTS. THE FINANCE CHARGE 15 COMPUTED BY A PERIODIC RATE OF 1 12% PEA MONTH, WHICH 15 AN ANNUAL PERCENTAGE RATE OF 16%09 A MINIMUM SERVICE CHARGE OFSSAO WHICHEVER IS GREATER. 000178 (16007) PLAZA BLVD. WIDENING CIP 16-01 PLAZA BLVD. & N AVE. NATIONAL CITY PO NUMBER: 16007 03/27/17 1.00 LD DUMP C225 DUMP CONCRETE TICKET DATE TOTALS: JOB TOTALS TICKETS: 022-330278 225.000 0.00 225.00 0.00 225.00 0.00 DICK MILLER INC. RECEIVED -��007 grilLIPO 225.00 225.00 225.00 RAD Report ID : 2/37 Billing Account # 8005787 Hauling Account # 8005787 Trans 109479414/ 10948024'v" 10948163i 10948383 s 10952925 10953378 10953722 10956978 - 10956982"' 10956994v 10957196.i 10957231v 10957500 0 10957627,7; 0 10957777" 0 10958152'', 0 10960597 0 10960739 10960784 10960858' 10961172 10961298/ Decal/Trailer 0 11W 0 52150 52150 0 0 0 0 0 0 10962243 0 10964054 • 0 10964157v 10964279 0 10964489 0 10964895 0 10964972. 0 !' Date/Time 03/03/2017 8:21:12 03/03/2017 8:57:01 Material Type SPECIAL FEE SPECIAL FEE 03/03/2017 9:48:36 SPECIAL FEE 03/03/2017 11:13:40 SPECIAL FEE 03/07/2017 9:17:51 REFUSE 03/07/2017 12:07:39 REFUSE 03/07/2017 14:07:49 REFUSE 03/10/2017 7:46:32 03/10/2017 7:47:52 03/10/2017 7:54:15 03/10/2017 9:14:48 03/10/2017 9:25:52 SPECIAL FEE SPECIAL FEE SPECIAL FEE SPECIAL FEE SPECIAL FEE 03/10/2017 10:50:56 SPECIAL FEE 03/10/2017 11:32:37 SPECIAL FEE 03/10/2017 12:21:20 SPECIAL FEE 03/10/2017 14:12:01SPECIAL FEE 03/13/2017 8:15:21 03/13/2017 9:15:21 03/13/2017 9:30:10 03/13/2017 9:55:40 SPECIAL FEE SPECIAL FEE SPECIAL FEE SPECIAL FEE 03/13/2017 11:30:04 SPECIAL FEE 03/13/2017 12:10:43SPECIAL FEE 03/14/2017 8:41:32 SPECIAL FEE 03/15/2017 11:47:23 SPECIAL FEE 03/15/2017 12:24:20 REFUSE 03/15/2017 13:04:32 SPECIAL FEE 03/15/2017 14:18:45SPECIAL FEE 03/16/2017 8:27:46 SPECIAL FEE 03/16/2017 9:09:04 SPECIAL FEE Miramar Landfill - RAD System Account Detail Report 03/01/2017 To 03/31/2017 ACCOUNT NAME: DMI ACCOUNT NAME: Gross 0 0 0 0 35980 50240 54020 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 30240 0 0 0 0 Tare 0 0 0 0 26180 26180 26180 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24520 0 0 0 0 Net Tons 0 0.00 0 0.00 0 0.00 0 0.00 9800 4.90 24060 12.03 27840 13.92 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 O 0.00 O 0.00 5720 2.86 0 0.00 0 0.00 0 0.00 0 0.00 TipFee 0.00 0.00 0.00 0.00 196.00 409.00 557.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.00 0.00 0.00 0.00 0.00 Greens TipFee 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ILLS; INC. 10 2011 Date: 04/04/2017 Time: 14:48:23 Page: 1 of 3 Tax AB939 0.00 0.00 0.00 0.00 39.00 96.00 111.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.00 132.00 153.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.00 0.00 0.00 0.00 0.00 Spec Fee 20.00 20.00 20.00 20.00 0.00 0.00 0.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 0.00 20.00 20.00 20.00 20.00 Total 20.00 20.00 20.00 20.00 289.00 637.00 821.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 151.00 20.00 20.00 20.00 20.00 RAD Report ID : 2/37 Billing Account # 8005787 Hauling Account # 8005787 Material Trans # DecallTrailer Date/Time Type 10965091' 0 03/16/2017 9:52:36 SPECIAL FEE 10965190 0 03/16/2017 10:30:13 SPECIAL FEE 10965276 " 0 03/16/2017 11:13:49 SPECIAL FEE 10965376� 0 10" 4.i 03/16/2017 11:55:11 SPECIAL FEE 10965835`i 0 03/16/2017 14:48:0E SPECIAL FEE 10966366'' 0 03/17/2017 9:36:01 SPECIAL FEE 10966475" 0 03/17/2017 10:24:37 SPECIAL FEE 10966739'1 0 03/17/2017 12:06:35 SPECIAL FEE 10966861 , 49115 03/17/2017 12:55:19 REFUSE 10966981 ' 0 03/17/2017 13:50:58 SPECIAL FEE 109696899, 0 03/20/2017 9:17:48 SPECIAL FEE 10971090 0 03/21/2017 9:17:19 SPECIAL FEE 10972131 0 03/21/2017 15:27:0E SPECIAL FEE 10972133 0 I�' r % 03/21/2017 15:27:11 SPECIAL FEE 10972963`v 49115 03/22/2017 14:27:0E REFUSE 10973435'v/ 0 03/23/2017 10:24:25 SPECIAL FEE 10973678 0 03/23/2017 12:23:38 SPECIAL FEE 10973894 0 03/23/2017 13:58:19 SPECIAL FEE 10974116 52150 03/23/2017 15:33:50 REFUSE 10974898ry 0 03/24/2017 11:49:39 SPECIAL FEE 10978006 0 03/27/2017 10:23:28 SPECIAL FEE 10978494 N 0 03/27/2017 13:12:51SPECIAL FEE 10978596° 0 03/27/2017 13:46:58 SPECIAL FEE 10978771w 49115 1 WO 7 03/27/2017 14:43:39 REFUSE 109796121 1491 10980311 0 10981081' 0 G ;v j 56 10983664 0 10983932 0 03/28/2017 14:19:25 SPECIAL FEE 03/29/2017 10:04:54 SPECIAL FEE 03/31/2017 8:22:50 SPECIAL FEE 03/31/2017 10:09:41SPECIAL FEE Miramar Landfill - RAD System Account Detail Report 03/01 /2017 To 03/31/2017 ACCOUNT NAME: DMI ACCOUNT NAME: Date: 04/04/2017 Time: 14:48:23 Page: 2 of 3 Greens Spec Gross Tare Net Tons TipFee TipFee Tax AB939 Fee Total 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 25220 19980 5240 2.62 89.00 0.00 21.00 29.00 0.00 139.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 23220 21280 1940 0.97 33.00 0.00 8.00 11.00 0.00 52.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 27200 26180 1020 0.51 18.00 0.00 1.00 1.00 0.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00/ 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00,E ,,1.-/ 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 21600 19980 1620 0.81 28.00 0.00 6.00 9.00 67.00 110.00 2.50 100.00 0.00 20.00 28.00 0.00 148.80, 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 0 0 0 0.00 0.00 0.00 0.00 0.00 20.00 20.00 RAD Report ID : 2/37 Billing Account # 8005787 Hauling Account # 8005787 Material Trans # Decal/Trailer Date/Time Type 10984230 0 03/31/2017 12:01:17 SPECIAL FEE 10984622 0 03/31/2017 14:16:32 SPECIAL FEE Account Totals 60 Miramar Landfill - RAD System Account Detail Report 03/01/2017 To 03/31/2017 ACCOUNT NAME: DMl ACCOUNT NAME: Greens Gross Tare Net Tons TipFee TipFee 0 0 0 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 292,700 210,460 82,240 41.12 1,527.00 0.00 Date: 04/04/2017 Time: 14:48:23 Page: 3 of 3 Spec Tax AB939 Fee Total 0.00 0.00 20.00 20.00 0.00 0.00 20.00 20.00 325.00 448.00 1087.00 3,387.00 ^- CALIFORNIA NATIONAL, CICTY INOORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 35 June 12, 2017 Reason/Purpose for this Change Order: Due to traffic and safety issues the City directed the conduit trench crossing and signal switchover be performed at night. Under direction of the Engineer the Contractor proceeded under time and materials for the additional night work costs. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with night work for the conduit trench crossings and signal switchover. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders 105,124.46 Subtotal Amount of this change order 1,999,622.56 10,814.62 New contract amount $ 2,010,437.18 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 6.12% Submitted by: 8/347 Cit Eng neer Date City Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Acted and agreed to by Dick Miller, Inc.: !Nam- — •� g/.2,1 7 Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard, National City, CA 91950 Terep one 619T 336-4380 � 1 / CALIFORNIA NATIONAL CV Livy INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: June 13, 2017 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Summary Sheet for Night Work ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) 2) 3) 4) 5) 6) Trench Crossings (11/29/16) Trench Crossings (11/30/16) Trench Crossings (12/1/16) Trench Crossings (12/6/16) Trench Crossings (12/7/16) Signal Switchover (5/11/17) LS LS LS LS LS LS 1.00 1.00 1.00 1.00 1.00 1.00 2,357.56 1,044.69 1,044.69 2,182.55 2,278.28 1,294.71 Sub -Total: 2,357.56 1,044.69 1,044.69 2,182.55 2,278.28 1,294.71 $ 10,202.48 TOTAL: PRIME CONTRACTOR MARKUP (5%) BOND AND INSURANCE (1%): $ 10,202.48 $ 510.12 $ 102.02 GRAND TOTAL: $10,814.62 +r- CALIFORNIA-- NATIONALCi i'Y INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification #16-01 DATE: November 29, 2016 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Rockwheel crossings at Night ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) UT TECH 2 - Carlos Balderas OPERATOR - Eric Schuler Hour Hour 10.00 8.00 14.50 22.37 145.00 178.96 3) UT TECH 3 - Arturo Cardenas Hour 10.00 11.25 112.50 4) 5) UT TECH 3 - G Grijalva UT TECH 2 - Robert Tesam Hour Hour 9.00 8.00 11.25 12.32 101.25 98.56 6) UT TECH 2 - JP Cruz Hour 8.00 12.32 98.56 7) OPERATOR - Todd Perry Hour 8.00 22.37 178.96 Sub -Total Labor: Labor Burden (12%): Labor Markup (20%): TOTAL LABOR: $ 913.79 $ 109.65 $ 182.76 $ 1,206.20 MATERIALS Unit Qty Rate Total 1) 2) Traffic Control (Night Time) Plant Opening Fee LS LS 1.00 1.00 54.00 750.00 54.00 750.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): $ 120.60 TOTAL MAT-TERIA11111111 $ 804.00 $ 64.32 EQUIPMENT Unit Qty Rate Total 1) 2) Light Tower Light Tower Hour Hour 8.00 8.00 7.56 7.56 60.48 60.48 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: BOND AND INSURANCE (10/0): $ 120.96 $ 18.14 $ 139.10 $ 23.34 GRAND TOTAL: $2,357.56 Robcar Corporation IbaHudson safe+'j;Llte Rentals iba Prest-O-Lite Barricade Co. 777 Gable Way, El Cajon CA Agora 4ArElti*LITE Hudson Safe-T-Lite Rentals REMIT PAYMENTS TO: PO Box 117, El Cajon, CA 92022-0117 619-441-3644 Fax 619-441-3652 T & M ELECTRIC DBA PERRY ELECTRIC P. O. BOX 710130 SANTEE, CA 92072 INVOICE Invoice Date Invoice No. 1211/2016 00040654 Terms: Net 30 Days Job ID: 125872 WILL CALL FOR PLAZA BLVD & N NATIONAL CITY, CA Will Call Customer Customer Job No. Customer P.O. No. Period Covered Foreman Name / Phone# 19500 696 11/29/2016 - 12/1/2016 CARLOS Date Description From - To Qty Days Units Price Total RENTALS 11/29/16 Sign on Flagtree Stand -High Int - Flagger Symbol 11/29 12/01 4 3 12 $3.00 $36.00 11/29/16 Sign on Flagtree Stand -High Int - Left Overlay 11/29 12/01 2 3 6 $3.00 $18.00 11/29/16 Sign on Flagtree Stand -High Int - Prepare to Stop 11/29 12/01 6 3 18 $3.00 $54.00 11/29/16 Sign on Flagtree Stand -High Int - Road Work Ahead 11/29 12/01 6 3 18 $3.00 $54.00 Note: The ' indicates taxable items. EQUIPMENT RENTAL TOTAL SALES/ONE-TIME CHARGES LABOR TOTAL SUBTOTAL SALES TAX (8.5%) TOTAL CHARGES PLEASE PAY THIS AMOUNT *** Job Complete *** S162.00 $0.00 $0.00 $162.00 $0.00 $162.00 $162.00 Page 1 Billing FaxFinderOut9 J1/1/ 1G/ •.JIGV1V vJ .vr.10. .♦, v�vv RO R N'S ROCK • SAND • BASE MATERIALS READY MIX CONCRETE (951) 685-2200 • (800) 834-7557 FED. I.D. #33-0491865 CUSTOMER JOB NUMBER / P.O. 696 JOB ADDRESS PLAZA BLVD & N AVE NATIONAL CITY DELJVERY DATE 11/30/16 PERRY ELECTRIC PO BOX 710130 10765 WOODSIDE AVE STE B SANTEE CA 92072 10 C PLANT DFL. FROM ZONE DATE 11/30/16 GUST. NO. 00458 NUMBER 904180 JCN NO. 696 REMIT TO: P.O, BOX 3600 CORONA, CA 92878 TERMS: DUE 10TH OF MONTH FOLLOWING DATE OF INVOICE / DEUVERY T ICKET I.O. 2579187 2579187 2579187 2579189 2579189 AARNE J09 1:25 3:30 FlNISH POUR 3:00 4:00 I,*,) 95 30 QUANTITY 10.00 10.00 1.00 3.50 3.50 UNIT CY PY T CY PY DESCRIPTION RC188N13 2.OSK SLURRY 2003 C C 2% 3655 PLT OPENING RC188N13 2.OSK SLURRY 2003 C C 2% TAX Y Y Y Y Y UNIT PRICE 70.50 6.00 750.00 70.50 6.00 AMOUNT 705.00 60.00 750.00 246.75 21.00 ENERGYSURCHG 20.00 ENV FEE 40.00 SUBTOTAL 1,642.75 TOTAL MIN ALLGNED MIN STANDBY MIN SALES TAX 165.85 STANDBY TIME 125 54 71 88.75 TOTAL QUANTITY TERMS: INVOICES ARE DUE 10TH OF MONTH FOLLOWING DATE OF INVOICE. PAST DUE INVOICE TOTAL 13.50 ACCOUNTS SUBJECT TO A MONTHLY SERVICE CHARGE OF 1.5%. BUYER TO PAY REASONABLE COSTS OF COLLECTION INCLUDING ATTORNEY FEES. 2,097.35 J 1/r., CALIFORNIA NATIONAL i'ION1�'�L CITT AVY INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: November 30, 2016 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Trench crossings at Night ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) UT TECH 2 - Carlos Balderas Hour 10.00 14.50 145.00 2) OPERATOR - Eric Schuler Hour 9.00 22.37 201.33 3) 4) UT TECH 3 - Arturo Cardenas UT TECH 2 - Robert Tesam Hour Hour 10.00 9.00 11.25 12.32 112.50 110.88 5) UT TECH 2 - JP Cruz 1) Traffic Control (Night time Hour Unit LS 9.00 12.32 110.88 $ 680.59 Sub -Total Labor: Labor Burden (12%): Labor Markup (20%): TOTAL LABOR: Qty 1.00 Rate 54.00 $ 81.67 $ 136.12 $ 898.38 Total 54.00 $ 54.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): TOTAL MATERIALS: $ 4.32 $ 8.10 $ 66.42 Unit Qty Rate Total 1) Light Tower Hour 8.00 7.56 60.48 $ 60.48 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: BOND AND INSURANCE (1%): $ 9.07 GRAND TOTAL: Robcar Corporation ba Hudson Safelite Rentals ba Prest-O-Lite Barricade Co. 777 Gable Way, El Cajon CA SATE TE Hudson Safe-T-Lite Rentals REMIT PAYMENTS TO: PO Box 117, El Cajon, CA 92022-0117 619-441-3644 Fax 619-441-3652 T & M ELECTRIC DBA PERRY ELECTRIC P. O. BOX 710130 SANTEE, CA 92072 INVOICE Invoice Date Invoice No. 12/1/2016 00040654 Terms: Ne 30 Days Job ID: 125872 WILL CALL FOR PLAZA BLVD & N NATIONAL CITY, CA Will CaII Customer Customer Job No. Customer P.O. No. Period Covered Foreman Name / Phone# 19500 696 11 /29/2016 - 12/1/2016 CARLOS Date Description From - To Qty Days Units Price Total RENTALS 11/29/16 Sign on Flagtree Stand -High Int- Flagger Symbol 11/29 12/01 4 3 12 $3.00 $36.00 11/29/16 Sign on Flagtree Stand -High Int - Left Overlay 11/29 12/01 2 3 6 $3.00 $18.00 11/29/16 Sign on Flagtree Stand -High Int - Prepare to Stop 11/29 12/01 6 3 18 $3.00 $54.00 11/29/16 Sign on Flagtree Stand -High Int - Road Work Ahead 11/29 12/01 6 3 18 $3.00 $54.00 Note: The' indicates taxable items. EQUIPMENT RENTAL TOTAL SALES/ONE-TIME CHARGES LABOR TOTAL SUBTOTAL SALES TAX (8.5%) TOTAL CHARGES PLEASE PAY THIS AMOUNT *** Job Complete *** $162.00 $0.00 $0.00 $162.00 $0.00 $162.00 $162.00 Page 1 I / :s CALIFORNIA NATIONAL MY e e INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: December 1, 2016 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Trench crossings at Night ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) UT TECH 2 - Carlos Balderas Hour 10.00 14.50 145.00 2) OPERATOR - Eric Schuler Hour 9.00 22.37 201.33 3) UT TECH 3 - Arturo Cardenas Hour 10.00 11.25 112.50 4) UT TECH 2 - Robert Tesam Hour 9.00 12.32 110.88 5) UT TECH 2 - JP Cruz Hour 9.00 12.32 110.88 Sub -Total Labor: Labor Burden (12%): Labor Markup (20%): TOTAL LABOR: $ 680.59 $ 81.67 $ 136.12 $ 898.38 MATER , t Unit Qty Rate Total 1) Traffic Control (Night Time) LS 1.00 54.00 54.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): TOTAL MATERIALS: $ 54.00 $ 4.32 $ 8.10 $ 66.42 EQUIPMENT Unit Qty Rate Total 1) Light Tower Hour 8.00 7.56 Sub -Total Equipment: Equipment Markup (15%): 60.48 $ 60.48 $ 9.07 TOTAL EQUIPMENT: BOND AND INSURANCE (1%): $ 69.55 $ 10.34 GRAND TOTAL: $1,044.69 Robcar Corporation ibaHudson Safe9.Lite Rentals lba Prest-O-Cite Barricade Co. 777 Gable Way, El Cajon CA CSArE'TLI!EI Hudson Safe-T-Lite Rentals REMIT PAYMENTS TO: PO Box 117, El Cajon, CA 92022-0117 619-441-3644 Fax 619-441-3652 T & M ELECTRIC DBA PERRY ELECTRIC P. O. BOX 710130 SANTEE, CA 92072 INVOICE Invoice Date Invoice No. 12/1/2016 00040654 Terms: Net 30 Days Job ID: 125872 WILL CALL FOR PLAZA BLVD & N NATIONAL CITY, CA Will CaII Customer Customer Job No. Customer P.O. No. Period Covered Foreman Name / Phone# 19500 696 11/29/2016 - 12/1/2016 CARLOS Date Description From - To Qty Days Units Price Total RENTALS 11/29/16 Sign on Flagtree Stand -High Int - Flagger Symbol 11/29 12/01 4 3 12 $3.00 $36.00 11/29/16 Sign on Flagtree Stand -High Int - Left Overlay 11/29 12/01 2 3 6 $3.00 $18.00 11/29/16 Sign on Flagtree Stand -High Int - Prepare to Stop 11/29 12/01 6 3 18 $3.00 $54.00 11/29/16 Sign on Flagtree Stand -High Int - Road Work Ahead 11/29 12/01 6 3 18 $3.00 $54.00 Note: The ' indicates taxable items. EQUIPMENT RENTAL TOTAL SALES/ONE-TIME CHARGES LABOR TOTAL SUBTOTAL SALES TAX (8.5%) TOTAL CHARGES PLEASE PAY THIS AMOUNT *** Job Complete *** U,2,Q vci $162.00 $0.00 $0.00 l7) $162.00 $0.00 $162.00 $162.00 Page 1 + CALIFORNIA NATIONAL CJrl INCORPORATED -� PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification #16-01 DATE: December 6, 2016 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Rockwheel crossings at Night ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) UT TECH 2 - Carlos Balderas Hour 10.00 14.50 145.00 2) OPERATOR - Eric Schuler Hour 5.00 22.37 111.85 3) UT TECH 3 - Arturo Cardenas Hour 10.00 11.25 112.50 4) 5) UT TECH 3 - G Grijalva UT TECH 2 - Robert Tesam Hour Hour 5.00 8.00 11.25 12.32 56.25 98.56 6) UT TECH 2 - JP Cruz Hour 8.00 12.32 98.56 7) OPERATOR - Todd Perry Hour Traffic Control (Night Time) LS 2) Plant Opening Fee LS 5.00 22.37 111.85 Sub -Total Labor: Labor Burden (12%): Labor Markup (20%): s 146.91 TOTAL LABOR: 1.00 1.00 162.00 750.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): TOTAL MATERIALS: $ 734.57 88.15 162.00 750.00 $ 912.00 $ 72.96 136.80 EQUIPMENT Unit Qty Rate Total 1) Light Tower Hour 8.00 7.56 60.48 Sub -Total Equipment: $ 60.48 Equipment Markup (15%): $ 9.07 TOTAL EQUIPMENT: BOND AND INSURANCE (1%): GRAND TOTAL: $2,182.55 Robcar Corporation dba Hudson Sore TLite Rentals dba Presl-O-Lite Barricade Co. 777 Gable Way, El Cajon CA EsArEi)74�TE Hudson Safe-T-Lite Rentals INVOICE REMIT PAYMENTS TO: PO Box 117, El Cajon, CA 92022-0117 619-441-3644 Fax 619-441-3652 T & M ELECTRIC DBA PERRY ELECTRIC P. O. BOX 710130 SANTEE, CA 92072 Invoice Date Invoice No. 12/1/2016 00040654 Terms: Net 30 Days Job ID: 125872 WILL CALL FOR PLAZA BLVD & N NATIONAL CITY, CA Will CaII Customer Customer Job No. Customer P.O. No. Period Covered Foreman Name 1 Phone# 19500 696 11/29/2016 -12/1/2016 CARLOS Date Description From - To Qty Days Units Price Total 11/29/16 11/29/16 11/29/16 11/29/16 RENTALS-------------- Sign on Flagtree Stand -High Int - Flagger Symbol Sign on Flagtree Stand -High Int - Left Overlay Sign on Flagtree Stand -High Int - Prepare to Stop Sign on Flagtree Stand -High Int - Road Work Ahead 11/29 12/01 11/29 12/01 11/29 12/01 11/29 12/01 4 2 6 6 3 3 3 3 12 6 18 18 $3.00 $3.00 $3.00 $3.00 $36.00 $18.00 $54.00 $54.00 Note: The * indicates taxable items. EQUIPMENT RENTAL TOTAL SALES/ONE-TIME CHARGES LABOR TOTAL SUBTOTAL SALES TAX (8.5%) TOTAL CHARGES PLEASE PAY THIS AMOUNT *** Job Complete *** $162.00 $0.00 $0.00 $162.00 $0.00 $162.00 $162.00 Page 1 filling FaxFinderOut10 Lr 1) 16/ 1'1/ c.'.a - ROBERTSON'S ROCK • SAND • BASE MATERIALS READY MIX CONCRETE (951) 685-2200 • (800) 834-7557 FED. I.D. #33.0491865 CUSTOMER JOB NUMBER / P.O. DELIVERY DATE 696 12/08/16 JOB ADDRESS PLAZA BLVD & PALM NATIONAL CITY PERRY ELECTRIC PO BOX 710130 10765 WOODSIDE AVE STE B SANTEE CA 92072 10 C PLANT DEL. FROM ZONE DATE 12/08/16 CUSI. NO. 00458 l DELIVERY TICKET NO. 2638521 2638521 2638521 2638521 AJOE 3:01 FINISH POUR 3:43 MN 42 QUANTITY UNIT 7.00 CY RC188N13 7.00 PY 2003 1.00 T 3655 7.00 PY 3100 DESCRIPTION 2.OSK SLURRY C C 2% PLT OPENING SHORT LOAD ('; NUMBER 910000 JCN NO. 696 REMIT TO: P.O. BOX 3600 CORONA, CA 92878 TERMS: OUE 10TH OF MONTH FOLLOWING DATE OF INVOICE TAX UNIT PRICE AMOUNT Y 70.50 Y 6.00 Y 750.00 493.50 42.00 750.00 30.00 STANDBY TIME TOTAL 1 IN 42 ALLOYED MIN STANDBY MIN 28 14 ENERGY SURCHG ENV FEE SUBTOTAL SALES TAX 10.00 20.00 1,345.50 121.10 TOTAL QUANTITY 7.00 TERMS: INVOICES ARE DUE 10TH OF MONTH FOLLOWING DATE OF INVOICE. PAST DUE ACCOUNTS SUBJECT TO A MONTHLY SERVICE CHARGE OF 1.5%. BUYER TO PAY REASONABLE COSTS OF COLLECTION INCLUDING ATTORNEY FEES. 17.50 INVOICE TOTAL 1,484.10 CALIFORNIA N1 JT'LONAL CI,__ y `-- INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: December 7, 2016 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Rockwheel crossings at Night ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) UT TECH 2 - Carlos Balderas Hour 10.00 14.50 145.00 2) OPERATOR - Eric Schuler Hour 6.50 22.37 145.41 3) UT TECH 3 - Arturo Cardenas Hour 10.00 11.25 112.50 4) 5) UT TECH 3 - G Grijalva UT TECH 2 - Robert Tesam Hour Hour 8.50 8.50 11.25 12.32 95.63 104.72 6) UT TECH 2 - JP Cruz Hour 8.50 12.32 104.72 7) OPERATOR - B Gunter Hour 6.50 22.37 145.41 Traffic Control (Night Time) Plant Opening Fee Unit LS LS Sub -Total Labor: Labor Burden (12%): Labor Markup (20%): S 170.68 TOTAL LABOR: Qty 1.00 1.00 Rate 108.00 750.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): $ 853.39 $ 102.41 Total 108.00 750.00 $ 858.00 68.64 TOTAL MATERIALS: EQUIPMENT Unit Qty Rate Total 1) Light Tower Hour 8.50 7.56 64.26 Sub -Total Equipment: Equipment Markup (15%): $ 9.64 TOTAL EQUIPMENT: BOND AND INSURANCE (1%): $ 64.26 $ 22.56 GRAND TOTAL: $ 2,278.28 Rohcar Corporation dba Hudson Safe'VLlte Rentals dba Prest-O-Lite Barricade Co. 777 Gable Way, El Cajon CA EsAr EITE Hudson Safe-T-Lite Rentals REMIT PAYMENTS TO: PO Box 117, El Cajon, CA 92022-0117 619-441-3644 Fax 619-441-3652 T & M ELECTRIC DBA PERRY ELECTRIC P. O. BOX 710130 SANTEE, CA 92072 Job ID: 125909 WILL CALL FOR USE PLAZA BLVD. NATIONAL CITY, CA INVOICE Invoice Date Invoice No. 12/8/2016 00040780 Terms: Net 30 Days Customer Customer Job No. Customer P.O. No. Period Covered Foreman Name / Phone# 19500 696 696 12/6/2016 - 12/8/2016 CARLOS Date Description From - To Qty Days Units Price Total RENTALS 12/06/16 Sign on Flagtree Stand -High Int - Flagger Symbol 12/06 12/08 4 3 12 $3.00 $36.00 12/06/16 Sign on Flagtree Stand -High Int - Prepare to Stop 12/06 12/08 4 3 12 $3.00 $36.00 12/06/16 Sign on Flagtree Stand -High Int - Road Work Ahead 12/06 12/08 4 3 12 $3.00 $36.00 Note: The * indicates taxable items. EQUIPMENT RENTAL TOTAL SALES/ONE-TIME CHARGES LABOR TOTAL SUBTOTAL SALES TAX (8.5%) TOTAL CHARGES PLEASE PAY THIS AMOUNT *** Job Complete *** $108.00 $0.00 $0.00 $108.00 $0.00 $108.00 $108.00 ROBERTSON'S ROCK • SAND • BASE MATERIALS READY MIX CONCRETE (951) 685-2200 • (800) 834-7557 FED. I.O. #33-0491865 CUSTOMER JOB NUMBER / P.O. 696 JOB ADDRESS PLAZA BLVD & PALM NATIONAL CITY DELIVERY DATE 12/07/16 PERRY ELECTRIC PO BOX 710130 10765 WOODSIDE AVE STE B SANTEE CA 92072 10 C PLANT DEL. FROM ZONE DATE 12/07/16 COST. NO. 00458 G rl NUMBER 909208 JCN NO. 696 REMIT TO: P.O. BOX 3600 CORONA, CA 92878 TERMS: DUE 10TH OF MONTH FOLLOWING DATE OF INVOICE DELVERY TICt r NO. 2628547 2628547 2628547 AARNE JOO 2:47 FINISH FOUR 3:26 MN 39 QUANTITY 10.00 10.00 1.00 UNIT CY PY T DESCRIPTION RC188N13 2.0SK SLURRY 2003 C C 2% 3655 PLT OPENING TAX Y Y Y UNIT PRICE 70.50 6.00 750.00 AMOUNT 705.00 60.00 750.00 ENERGYSURCRG 10.00 ENVFEE 20.00 SUBTOTAL 1,545.00 TOTAL MIN ALLOWED MIN STANDBY MIN SALESTA%( 139.05 TOTAL QUANTITY TERMS: INVOICES ARE DUE 10TH OF MONTH FOLLOWING DATE OF INVOICE. PAST DUE INVOICE 10 LAL 10.00 ACCOUNTS SUBJECT TO A MONTHLY SERVICE CHARGE OF 1.5%. BUYER TO PAY REASONABLE COSTS OF COLLECTION INCLUDING ATTORNEY FEES. 1,684.05 ./ CALIFORNIA NATIONAL My �i GS e e V INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: May 11, 2017 CHANGE ORDER NO. 35 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Taking down old poles and setting new ones at Palm Avenue ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) T Peterson E Dukes Hour Hour 12.00 12.00 17.68 14.04 212.16 168.48 3) J Axelson Hour 12.00 10.40 124.80 4) 5) D Macias L Cuevas Salazar Hour Hour 12.00 12.00 11.31 16.64 135.72 199.68 Sub -Total Labor: Labor Burden (120/0): Labor Markup (20%): TOTAL LABOR: $ 840.84 $ 100.90 $ 168.17 $ 1,109.91 ATE 1) �A Traffic Control (Night Time) Unit LS Qty 1.00 Rate 55.00 Total 55.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): TOTAL MATERIALS: $ 55.00 $ 4.40 $ 8.25 • EQUIPMENT Unit Qty Rate Total 1) Light Tower Hour 12.00 7.56 90.72 2) Light Tower Hour 12.00 7.56 90.72 Sub -Total Equipment: Equipment Markup (15%): $ 90.72 $ 13.61 TOTAL EQUIPMENT: BOND AND INSURANCE (1%): $ 104.33 $ 12.82 GRAND TOTAL: $1,294.71 43— CALIFORNIA ,(•.#��1 (�^ ULti INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. Reason/Purpose for this Change Order: Additional grading and subgrade preparation was required for the cross gutter at N Avenue. Under direction of the Engineer the Contractor proceeded under time and materials for the additional grading and subgrade preparation. CHANGE ORDER NO. 36 June 12, 2017 The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with the additional grading and subgrade preparation for the cross gutter at N Avenue. The agreed upon price for all costs associated with this work is as stated on this Change Order. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders 115,939.08 Subtotal 2,010,437.18 Amount of this change order 880.64 New contract amount $ 2,011,317.82 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 6.17% Submitted by: tia P;-sect Ma ger ate Approved by: Clt ngineer - Date City Manager, required for Chan a Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. At of the terms and conditions of the original contract documents are incorporated herein. Accepted and agreed to by Dick Miller, Inc.: &./2 ate Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevarc�,National City, CA 91950 Telephone (619) 336-4380 CALIFORNIA - NATIONAL CI it f- 13 3r1 . __. INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 37 July 20, 2017 rReason/Purpose for this Change Order: Due to the location of the traffic signal poles the pedestrian push buttons did not meed ADA requirements and separate push button posts had to be installed. Under direction of the Engineer the Contractor proceeded with installing 7 pedestrian push button posts at all 4 corners of Palm and Plaza and the Northwest, Northeast and Southeast corner of N Ave and Plaza. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with the installation of 7 pedestrian push button posts. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount Net change by previously authorized Change Orders Subtotal Amount of this change order 1,894,498.10 116,819.72 2,011,317.82 10,292.10 New contract amount $ 2,021,609.92 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 6.71 % Submitted by: ect Man(4ger W�1 Date !Approved by: City 7/1///7 Date ...__.._. Cif Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. ccepted and agreed to by Dick Miller, Inc.: Name: Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City BouTevar-d, National City, CA 91950 Tel ep one 619 336-4380 CALIFORNIA NATIONAL 3NCbpRPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: July 20, 2017 CHANGE ORDER NO. 31 WORK PERFORMED BY: Perry Electric DESCRIPTION OF WORK: Pedestrian Push Buttons ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) Tech 1 Hour 4.00 41.91 167.64 2) Tech 3 Hour 4.00 28.71 114.84 Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: $ 56.50 $ 338.98 A* Unit Qty Rate Total 1) Ped Post and Bolts EA 1.00 550.00 550.00 2) Concrete, Grout LS 1.00 50.00 50.00 3) Pipe, 90's, Fittings, Wire LS 1.00 50.00 50.00 Sub -Total Materials: Materials Markup (15%): TOTAL MATERIALS: 97.50 EQUIPMENT Unit Qty Rate Total 1) Chev Silvardo Hour 4.00 44.22 176.88 2) 185 CFM Compressor Hour 4.00 24.00 96.00 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 272.88 $ 40.93 SUBTOTAL: PRIME CONTRACTOR MARKUP (5%): GRAND TOTAL: $ 313.81 $ 1,400.29 $ 70.01 $1,470.30 Total for Installation of 7 pedestrian posts: $10,292.10 $ 650.00 $ 282.48 + CALIFORNIA *-t* NATIONAL r^- Q INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 38 August 3, 2017 Reason/Purpose for this Change Order: The Storm drain box on the South side of Plaza Blvd at Station 53+07 could not be adjusted to grade and had to be reconstructed. Under direction of the Engineer the Contractor proceeded under time and materials to reconstruct the storm drain box. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with reconstructing the storm drain box on the South side of Plaza blvd at Station 53+07. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders Subtotal Amount of this change order 127,111.82 2,021,609.92 2,968.17 New contract amount $ 2,024,578.09 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 6.87% Submitted by: r ct Man !Approved by: Cit n Ineer Date Daatete 1.. r_ a City Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. ted and agreed to b Dick Miller, Inc.: Y./2-3 Nam-. Date Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243National City Bou'IevaFa, National City, CA 91950 T(f) 336-4380 /// CALIFORNIA - NATIONAL Car INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: June 13, 2017 CHANGE ORDER NO. 35 WORK PERFORMED BY: Solid Structures, Inc. DESCRIPTION OF WORK: Summary Sheet for reconstruction of storm drain box ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) 2) 3) Lower Deck on Box (6/21/17) Form box, set ring, steps and pour (6/22/17) Strip, patch and load deck (6/23/17) LS LS LS 1.00 1.00 1.00 1,440.97 911.31 446.56 1,440.97 911.31 446.56 Sub -Total: $ 2,798.84 TOTAL: PRIME CONTRACTOR MARKUP (5%) BOND AND INSURANCE (1%): $ 2,798.84 $ 139.94 $ 29.39 GRAND TOTAL: $ 2,968.17 -+--= CALIFORNIA Nl AT'IO NAL INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: June 21, 2017 CHANGE ORDER NO. 38 WORK PERFORMED BY: Dick Miller Inc. DESCRIPTION OF WORK: Lower Deck on Storm drain box to match street and sidewalk grade ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) Journeyman -Michael Beeson 6th Period Apprentice -Henry Rod Hour Hour 6.00 6.00 71.69 58.12 430.14 348.72 Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: $ 778.86 $ 155.77 MATERIALS Unit Qty Rate Total $ 934.63 1) 2) Plywood - JB Lumber LF - JB Lumber LS LF 2.00 170.00 51.11 0.46 102.22 78.20 3) Rebar #4 - HD Supply LF 160.00 0.56 89.60 Sub -Total Materials: Materials Markup (15%): TOTAL MATERIALS: $ 270.02 $ 40.50 EQUIPMENT Unit Qty Rate Total 1) F-450 Ford Truck Hour 6.00 25.30 151.80 2) Honda 5000SX Hour 6.00 3.08 18.48 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 170.28 25.54 $ 195.82 GRAND TOTAL: $1,440.97 LUMBER COMPANY KMIT TQ:, Box 974 PA tkporm STANTON, OA R06�07•0974 •Stanton, CA 90680;;0074:- (714.) 5,7-2110 'Ak: (7t 4) 229-2233 t'sqlaD PakiTLMfl SOLD 1.)0 TiOlt 1348 TO: LA MIP.2;4., C.A 91Mt14 kTq'Frif ,-'3ALES TAX, 01.1=0- A '44 CALVORVIA 1-11-3FSMIOP • - fl .16 qt.; 040 2414 4.11.9 OM atm Irs; (ALL) :L Wilt 343 prZ4: '2011 INVOICE lt#01.9k*Tt rvipt - SHIP TO: 3\fOUtk 32 )k i(p .14 ) t 3 AI Tify( SD .) VIVO 500Cl •T.ECWT "1S6.3. crtMACIBIDA G. OF MaCi2DECT rOL1407 141 MID gPlTv-Cf; ' • . a jam lahkjgam.kunsONfill'ION oa Tug -;;;;;;Z: Seller la n44110111000 recoittMend any material ior a specific purpose or use; ftle thebuyeessole responatOlty to dyteardne the•propergrade and treatment of cnatodal for own sOeniflemay. • RUM iwitivilmegittmetotinitittertitiovitlovtivaa NatitilmlailijA4.1ianniit»4$6oilga change. from tImy to -thy. Tbecotyre, the•seIlor. reqommernie the buyer to coma the roost putroot aradyi • engineering, mariutaotudnO, and fronting- opealtloatIone before -ordering arid OsIlikany material: . ALL RETURNS ARE SUBJECT TO A 15 - 20% RESTOCKING CHARGE: NO RETURN ON MILLED 'Tads. V. Xi) satzemont wm be renooreci. :33/DBz.LQ,9 3 pc _ 1(s' )1S + TM( '14 . . 1.450 0.6.50 ' 'OICE Page 1 of 1 i 1 j -1 MeadowBu e 2835 Overpass Road Tampa , FL 33619 MBCredit@meadowBurke.com SOLO TO: 246721 MB 0.419 E0041X 10054 01975348274 S2 P3601072 0001:0001 Telephone: 813-280-8795 Fax • 855-319-0965 IIrIIIII(ii(rn)Irr)((I((1111ii11)II44(111111(III(11I(iI)1111, SOLID STRUCTURES, INC. PO BOX 848 LA MESA CA 91944-0848 Invoice No. 045352731 Remit to: Meadow Burke Products PO Box 404271 Atlanta, GA 30384 PRO number: Site: SHIP TO: Solid Structures 8517 PASEO DR SANTEE, CA 92071 4310 697215116 Canby Date 11/1/2016 Packing slip(s) ...: SP375055 Customer No. 045100207 Order Qty Item Description 500.00 BC110220 1,000.00 BC110340 1.00 9700005 Order No. S367824 BOWCO Black Step 93813-R OR Socket Delivery Charge - Non Taxable Customer PO Rocio Delivery Terms PrePd&Add Shipped Remaining Mode of Delivery UPS Freight Unit Price Amoun 500.00 0.00 3.7500 1,875.01 1,000.00 0.00 0.5900 590.01 1.00 0.00 246.2700 246.2: Tax 197.2' TOTAL AMOUNT DUE BY: 12/01/16 US 2,908.4 Minimum 10% handling charge on all returned goods. No goods to be returned without consent. Givns reference our invoke number and date. Claims for damages, back charges for labor, other expenses, will not be allowed unless authorized in writing by the seller. The articles and/or services covered by this invoice were produced in compliance with the Federal Labor Standards Act of 1938, as amended. The Customer Agrees 1. THAT THE ABOVE TOTAL IS PAST DUE IF NOT PAID 1MTHIN 30 DAYS OF DATE OF THIS INVOICE 2. TO PAY A FINANCE CHARGE OF 1.5% PER MONTH (18% PER ANNUM) ON ANY PAST DUE AMOUNT. 3. TO PAY COLLECTION COSTS, INCLUDING REASONABLE ATTORNEY FEES, AFTER DEFAULT BY THE CUSTOMER 0001:000i EMS Mai OSUPPLr CoNSTRucnot4 a INDUstrtiAL HD Supply Construction Supply; lti. CAP 001 W.Church Street, Ctie, Ft 3280&2247 IENRQL1XE C1.T0KEN:(. SKX0KLGM I SOLD TO: 230100.0 133481 M80;419 E0087X 10108 8107,0097010 82 P3540032 00010101 SOLID STRUCTURES ttdC PO BOX 848 (A MESA CA 91944-)848 10107/2010 JISH- 036 � � J41R`fJl�giaBk`q :. 0 HORDESC 11 12 8PJSOL1DFAB#1 SP/#42060DIR"' BRANCH ADDRESS 030 - EL CAJON (819) 590.2001 430 RA1..EIGH AVE EL CAJON CA 92020 TERRtrORYt IMP TO 10001078510 INVOICE iek/Or tom; 50005147886 10/12/2018 customer' P.0 i4O8 W14UE CAP 0011STSUPPLY P.O. Box 8040 CYPRESS, CA 80630.0040 SkNTEE HACIENDA & PROSPECT AVE nn END OF HACIENDA LEADS INTO YARD" SANTEE CA 02071 L 22214987 10001079518 JEFF HICKS 2% 10TH NET 11TH ' i1aaMC'fSNKaifiifilnYwiipYl�MMMi/HiitflilffY'kflafNfM1 DELIVERY TAG1: S880184 1.1011ffFi4• J.AN flfintM}itN4pf4ia •01.1. AwfNNHfltfesi +yfOLUlDATRUCTORE SPAS.BARAPERMSTy._.__ ., w4 20.0 STRAIGHT BAR DIRECT A44icto99.:,. DANIELS, TURNER 1 iPZ1'le 1 300 OUR TRUCK UNlri c% QTYBKO 0Tv$I{p;. 0 0 1 7,572.89 LOT a. 300 BARK, SHAWN E CUoyo1e :1olsNo,: SAI4TEE 0.00 7,872805.84 `4 "1,200.015 "103 s We Want To Hear From YOU! Your satisfaction is Important to us and we would like to know how to serve you batter. Please click the tint; below or type the address into your browser, and fake a quick 5 minute survey. hftp:l/www.WhiteCap.comhe-survey Thank you for your feedback and we look forward to hearing from you! Fortluesltorus ragarersi ilissinvcifce pteese c• a01�g00•WNt1Y£GAP (1-800-944-8322). NO REFUNDS OR. EXCHANGES ON NON STOCK MERCHANDISE V It btIplAvtritecep com/rmlacltarm8_and aondl110 apdd18o view complete terms and condk O L RECEIVED BY: SRONDON ;p1Y41 000t:000r SIGNATURE COPY ON FJLE ! J t TOTAL GROSS 8,868.89 TOTAL TAX 700.52 TOTAL SHIPPING ' AND HANDLING itt►tt'ECi.iltrtlJ9ify4{f 8 :6Mth& • t!ljQ; Nip lrh+t404tai 015 Tt?TA1 t1f 0.00 O,$78.41 Page 1 of 1 It, i' u 3 as pi } yotiq c �.1 " 2,00 IL) yi 406 i-) 't-3", 1.1 6" ;ER 1? 1.y,3:4 ae 14 4/ a. r-.1" 3" el9-41. 4p 5-00 ae51 ,(70. 1'11(y r 2,01 r• �`',46e.a Ica CALIFORNIA NATIONAL Orr nay ITCORpORATED � PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 CHANGE ORDER NO. 38 DATE: June 22, 2017 WORK PERFORMED BY: Dick Miller Inc. DESCRIPTION OF WORK: Complete outsides of storm drain box, set ring and steps and pour box ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) 2) 3) 4) Journeyman - Michael Beeson 6th Period Apprent. - Henry Rodr Journeyman - Ryan Chavez 5th Period Apprent.- Francisco Ri( Stepes - MeadowBurke Hour Hour Hour Hour 4.00 4.00 1.00 1.00 71.69 58.12 71.69 55.41 286.76 232.48 71.69 55.41 Sub -Total Labor: Labor Markup (20%): $ 129.27 TOTAL LABOR: $ 646.34 Unit Qty Rate LS 1.00 4.48 Sub -Total Materials: Materials Markup (15%): TOTAL MATERIALS: Unit Qty Rate Total 1) F-450 Ford Truck Hour 4.00 25.30 101.20 2) Honda 5000SX Hour 4.00 3.08 12.32 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 113.52 17.03 GRAND TOTAL: $ 911.31 CALIFORNIA -+ NATIONAL ell jNCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: June 23, 2017 CHANGE ORDER NO. 38 WORK PERFORMED BY: Dick Miller Inc. DESCRIPTION OF WORK: Strip, patch, and load deck ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit Qty Wage Total 1) 2) Journeyman - Michael Beeson 6th Period Apprent. - Henry Rodr MATERIALS 1) N/A Hour Hour Unit 2.00 3.00 71.69 58.12 143.38 174.36 Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: Qty Rate Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): $ 317.74 $ 63.55 Total TOTAL MATERIALS: EQUIPMENT Unit Qty Rate Total 1) 2) F-450 Ford Truck Honda 5000SX Hour Hour 2.00 2.00 25.30 3.08 50.60 6.16 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 56.76 $ 8.51 GRAND TOTAL: $ 381.29 $ 65.27 $ 446.56 } CALIFORNIA NATIONAL ClrTy IA J NCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 39 August 7, 2017 Reason/Purpose for this Change Order: The relocated palm tree for the North side Western Dental did not survive and had to be removed. Under direction of the Engineer the Contractor proceeded under time and materials to remove the dead palm tree. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with removing the dead palm tree on the North side of Plaza Blvd at the Western Dental. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount Net change by previously authorized Change Orders Subtotal Amount of this change order New contract amount Working days added: 0 Working days subtracted: 0 1,894,498.10 130,079.99 2,024,578.09 1,642.18 $ 2,026,220.27 Percent change in Contract to date 6.95% Submitted by: Date Approved by: City engineer Date City Manager, required for Change Orders >S24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Acce • ted and a • reed to b Dick Miller, Inc.: Name: Da e Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 National City Boulevard Nationa rty, CA 91950 Telephone (619) 336-4380 CALIFORNIA NATIONAL CITY MOV INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification # 16-01 DATE: June 9, 2017 CHANGE ORDER NO. 39 WORK PERFORMED BY: Dick Miller, Inc. DESCRIPTION OF WORK: Remove palm tree, backfill hole, repair irrigation ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT L'='' - `OR Unit Qty Wage Total 1) Foreman Hour 2.00 80.20 160.40 2) Laborer Hour 2.00 57.62 115.24 Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: $ 275.64 55.13 $ 330.77 MATERIALS Unit Qty Rate Total Misc. sprinkler parts LS 1.00 60.00 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): 60.00 60.00 4.80 9.00 TOTAL MATERIALS: EQUIPMENT Unit Qty Rate Total 1) 750 Bobcat Skidsteer Hour 1.00 49.00 49.00 2) Crew & utility truck w/ tools Hour 2.00 50.00 100.00 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: 22.35 $ 171.35 SUBCONTRACTOR Unit Qty Rate Total 1) Anton Tree Services crew LS 1.00 1,000.00 1,000.00 Sub -total Subcontractor: Prime Contractor Markup (5%): $ 1,000.00 50.00 TOTAL SUBCONTRACTOR: SU B-TOTAL: BOND AND INSURANCE (1%): $ 1,050.00 $ 1,625.92 $ 16.26 GRAND TOTAL: $1,642.18 $ 149.00 AN'ION'S maraisimminge 8865 Winter Gardens Blvd Lakeside CA 92040 General Engineering, Demolition & Clearing CA Lic. 861069 Bill To Dick Miller Inc. (DMI) 930 Boardwalk, Suite H San Marcos, CA 92078 1- 760-471-6842 DICK MILLER INlC. JUL 25 2011 t ioao-7 a' t opp,' Invoice Date Invoice # 6/30/2017 22425 PLEASE REMIT PAYMENT TO: Anton's Service, Inc. PO Box 455 Lakeside, CA 92040 Ph (619) 579-9000 Fax (619) 749-5597 P.O. No. Terms Palm Avenue Net 30 Description of work 6-9-2017, Removed one dead palm, including stump. Left hole for DMI to fill up It's been a pleasure working with youl Amount S21 1,000.00 Balance Due $1,000.00 Past Due Invoice Invoices WI 1 BE Charged 1.5% Per Month -y- CALIFORNIA -� NATIONAL cirry IaC:.1 ° U NCORPORATE PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 40 August 7, 2017 Reason/Purpose for this Change Order: The cross gutter on the North side of Plaza Blvd at Station 41+80 was redesigned with rebar and 10" thick 4,000 psi concrete because of poor subgrade. Under direction of the Engineer the Contractor proceeded under time and materials to add rebar and increase the strength and thickness of the concrete in the cross gutter. LL The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with adding rebar and increase the strength and thickness of the concrete in the cross gutter on the North side of Plaza Blvd at Station 41+80. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders Subtotal Amount of this change order 131,722.17 2,026,220.27 1,292.51 New contract amount $ 2,027,512.78 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 7.02% Submitted by: Approved by: Date ngineer_._ Date City Manager, required for Change Orders >$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. -Accepted and agreed to by Dick Miller, Inc.: Name: Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager Date 1243 Nationa City Boulevard, National City, CA 91950 TelepTione (619') 336-4380 CALIFORNIA NATI O ►N1AL Crry INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 CHANGE ORDER NO. 40 Specification # 16-01 DATE: March 29, 2017 WORK PERFORMED BY: Dick Miller, Inc. DESCRIPTION OF WORK: Change from 8" to 10"; Switch from 3250 PSI to 4000 PSI concrete ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) Cement Mason Hour 1.00 58.68 58.68 2) Cement Mason Hour 1.00 58.68 58.68 1) 20' #4 Rebar 1) 4000 PSI Concrete 2) Credit for 3250 PSI Concrete Unit Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: Qty Rate $ 117.36 $ 23.47 $ 140.83 Total EA CY CY 25.00 22.80 (18.24) 11.38 99.90 90.20 284.50 2,277.72 (1,645.25) Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): TOTAL MATERIALS: $ 916.97 73.36 $ 148.55 SUBTOTAL: BOND AND INSURANCE (1%): 1,138.88 $ 1,279.71 $ 12.80 GRAND TOTAL: $1,292.51 SUPERIOR READY MIX CONCRETE, L.P. 1508 W. MISSION RD.ESCONDIDO, CA 92029 PHONE: (760) 746.0558 • FAX: (780) 740-9557 DICK MILLER INC 930 BOARDWALK SUITE H SAN MARCOS, CA 92078 INVOICE MILLE005 03/29/2017 855701 1 TEHItS NET 3O DAYS A FINANCE CHARGE WILL BE IMPOSED ON PAST DUE ACCOUNTS, THE FINANCE CHARGE 18 COMPUTED SY A'PERIOOIC RATE OFI I12% PER MONTH, WHICH 18 AN ANNUAL PERCENTAGE RATE OF 18%ORA MINIMUM SERVICE CHARGE OF$6A0 WHICHEVER 18 GREATER, 000178 (16007) PLAZA BLVD. WIDENING CIP 16-01 PLAZA BLVD. & N AVE. NATIONAL CITY PO NUMBER: 16007 03/29/17 22.50 CY 57P 660-C-4000P , 7 SK CONCR 36.00 EA ST STAND BY TIME - MIXER 3.00 LD EE ENVIRONMENTAL/ENERGY SUR TICKET DATE TOTALS: 99.900 174.20 1.500 0.00 30.000 6.99 2391.75 181.19 JOB TOTALS 2391.75 181.19 ✓ f ,/ TICKETS: 004-243857 004-243870 004-243887 4DOio fig1 co.. k'715- 01- C4SEi7 Wr can-Tu. r'IKt o 3LSp 'Lp gevo 4 j i cw '� + DICK MILLER INC. RECEIVED fib Doi 257Z jkIlTri i°Riik1 6 2421.95 54.00 96.99 2572.94 2572.94 Attn: Customer: Location: Project: Superior Ready Mix Concrete, LP 1508 W. Mission Rd Escondido, CA 92029, Phone (760) 745-0556 Fax (760) 740-9557, WWW.SUPERIORRM.COM San Diego County dispatch areas: North County (760) 745-0556, South County (858) 695-0666, East County (619) 443-7510 DMI — DICK MILLER INC. PLAZA BLVD Date: 1/19/2016 Fax: 760-471-6178 Phone: 760-471-6842 email: MIX NUMBER MIX DESCRIPTION QUANTITY PRICE/YARD 5596 560-C-3250 CONCRETE 610 90.20 *PLEASE CALL OUT MIXES BY MIX NUMBER WHEN ORDERING TO RECEIVE QUOTED PRICE ENERGY/ENVIRONMENTAL SALES TAX: Quoted prices MINIMUM LOAD: A single STANDING TIME: Unloading SPECIAL PROVISIONS: and not an aesthetic building specifications. TEMPERATURE: Concrete SURCHARGE: $30.00 per load. Do Not include sales tax. of a continuous pour. at the time of arrival at job. flatwork. Concrete is a structural building material is batched using materials within ASTM delivery of less than 9 cubic yards will be charged minimum rates. One short load is allowed for a completion time in excess of 4 minutes per cubic yard will be charged at $1.50 per minute. Unloading time starts Prices apply during normal working hours, Monday through Friday. 3/8" pump mix is not recommended for material. Superior Ready Mix Concrete will not be held responsible for pop -outs, cracking, etc., when concrete temperature is subject to ambient conditions and is not controlled unless stated otherwise. Rock / Sand / Base MATERIAL TONS SOURCE TRUCK TYPE PRICE/TON DELIVERY SALES TAX: Sales tax will be charged on material only, not freight. Title to material passed to customer at time of loading into truck. MINIMUM LOAD: A delivery of less than 26 tons will be charged minimum rates. STANDING TIME: Unloading time in excess of 20 minutes per load will be charged at $1.80 per minute. Unloading time starts at the time arrival at the job. SPECIAL PROVISIONS: Prices apply during normal working hours, Monday through Friday. Price quoted per ton unless otherwise noted. Delivery charges are subject to PUC increase. Materials Subject to availability. PAYMENT TERMS: Net 30 days (with an open Superior Ready Mix account) INSURANCE: The insurance carrier for Superior Ready Mix Concrete, LP will not name contractor or owner as additional insured nor will it issue a Waiver of Subrogation endorsement in favor of contractor or owner. DELIVERY: Orders are taken with the intent to deliver on time. There is no guarantee as to rate or time of delivery. Additional charges may apply for canceled orders or orders put on hold. MATERIAL SELECTION: The products quoted are not warranted or suggested for any specific application. Buyer is hereby wamed that the selection and ordering of any particular product is the responsibility of the buyer and that the buyer assumes any and all risk associated with the selection of the product. QUOTED RATES: Prices apply to valid Superior Ready Mix account, check, or cash sales only. Quoted By: MATTHEW EYER Expiration: 3/31/2016 619-247-3368 Escalator: Accepted by: This proposal is subject to signed acceptance by the buyer within 30 days from date hereof after which time it will be of no force or effect except at the option of the seller. +}- CALIFORNIA* NATIoNAL acAvINCORPoAATEp PLAZA BLVD WIDENING "N" AVENUE TO 1-805 Specification No. 16-01 Contractor: Dick Miller, Inc. CHANGE ORDER NO. 41 August 10, 2017 Reason/Purpose for this Change Order: The grades for the cross gutter on the South side of Plaza Blvd at Station 43+00 did not meet ADA standards and the already set up formwork had to be taken out and redone. Under direction of the Engineer the Contractor proceeded under time and materials to redo the formwork for the cross gutter. The City of National City and Contractor agree to the following change to the original Contract: The City and the Contractor agree that the Contractor shall proceed with redoing the formwork for cross gutter on the South side of Plaza Blvd at Station 43+00. The agreed upon price for all costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown. Original Contract Amount $ 1,894,498.10 Net change by previously authorized Change Orders Subtotal Amount of this change order 133,014.68 2,027,512.78 1,443.13 New contract amount $ 2,028,955.91 Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 7.10% Submitted by: Date Date City Manager, required for Change Orders>$24,999 Date By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. Accepted and a reed to b Dick Miller, Inc.: .� you may be directed tooproceed withhthisgi4 to Name: / Note to Contractor: if you do not agree with this Change Order ......_ work under the terms of the contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim. Originals: City Clerk, Contractor cc: Engineering project file, Project Manager 1243 Nationa City BouTevara, NationaTCity,CA 91950 Telephone j619)-336-4380 -F - CALIFORNIA N TIONAL CITY INCORPORATED PLAZA BLVD WIDENING "N" AVENUE TO 1-805 CHANGE ORDER NO. 41 Specification # 16-01 DATE: November 23, 2016 WORK PERFORMED BY: H&D Construction DESCRIPTION OF WORK: Design change to IHOP crossgutter ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Total 1) 2) Foreman, Truck & Tools Cement Mason/Finisher Hour Hour 2.00 2.00 106.00 68.00 212.00 136.00 3) Cement Mason/Finisher Hour 2.00 68.00 136.00 4) Cement Mason/Finisher Hour 2.00 68.00 136.00 5) Laborer Hour 2.00 57.00 114.00 $ 734.00 $ 146.80 $ 880.80 MATERIALS Unit Qty Rate Total 1) Superior Ready Mix Invoice 8306 CY 4.00 97.85 Sub -Total Materials: Sales Tax (8%): Materials Markup (15%): 391.40 $ 391.40 31.31 58.71 TOTAL MATERIALS: $ 481.42 EQUIPMENT 1) N/A Unit Qty Rate Total Sub -Total Equipment: Equipment Markup (15%): $ TOTAL EQUIPMENT: SUBTOTAL: Prime Contractor Markup (5%): BOND AND INSURANCE (1%): GRAND TOTAL: $ 1,362.22 68.11 $ 12.80 $1,443.13 Sub -Total Labor: Labor Markup (20%): TOTAL LABOR: H & D CONSTRUCTION P.O. BOX 12859 EL CAJON, CA 92022 8015ERIOR READY MIX CONCRETE, L.P. 1506 W. MISSION RD. • ESCONDIDO. CA 92029 PHONE: (760) 745-0556 * FAX (760) 740-9557 INVOICE HDCON005 11/23/2016 830680 1 TERUS. NET 90 DAYS A FINANCE CHARGE WILL BE IMPOSED ON PAST DUE ACCOUNTS. THE FINANCE CHARGE IS COMPUTED BY A'PERIODIC RATE OF 1 113% PER MONTH, WHICH IS AN ANNUAL PERCENTAGE RATE DE IMOR A MINIMUM SERVICE CHARGE OF 99.00 WHICHEVER IS GREATER. 001611 (1611) PLAZA BLVD. ROAD WIDENING PLAZA BLVD. & PALM NATIONAL CITY PO NUMBER: 1611 11/23/16 23.50 CY 5596 560-C-3250 CONCRETE 3.00 LD EE ENVIRONMENTAL/ENERGY SUR 4.50 PY SET1-6 1 SUPERIOR SET , 6SK TICKET DATE TOTALS: JOB TOTALS 86.200 162.05 2187.75 30.000 7.20 97.20 3.000 1.08 14.58 2129.20 170.33 2299.53 2129.20 170.33 2299.53 TICKETS: 004-237398 004-237413 004-237427 COPY = `�1 Made For 3;ir7�Atlse 97.gsett439 /- AMOUNT DUE 2299.5